Iris Energy Limited (NASDAQ: IREN) (“Iris Energy” or “the
Company”), a leading sustainable Bitcoin miner which is building an
institutional-grade infrastructure platform with 15 EH/s of secured
miners (10 EH/s expected to be operational by early 2023), today
published a monthly investor update for April 2022, containing its
results from operations as well as construction and development
updates.
Key highlights
Key metrics |
Apr-22 |
Average operating hashrate (PH/s) |
1,038 |
Bitcoin mined1 |
137 |
Mining revenue (US$'000) |
5,434 |
Electricity costs (US$'000)2 |
1,205 |
Revenue per Bitcoin (US$) |
39,740 |
Electricity costs per Bitcoin (US$) |
8,810 |
|
|
- Operations:
- Commissioning of
the first 0.3 EH/s (9MW) completed ahead of schedule at Mackenzie,
BC
- Increased average
operating hashrate to 1,038 PH/s (+22% increase)
- Monthly operating
revenue of US$5.4 million (+6% increase)
- 137 Bitcoin mined
(+13% increase)
- Construction:
- Mackenzie (2.4
EH/s, 80MW – BC, Canada)
- Initial 0.3 EH/s
(9MW) commissioned ahead of schedule in April
- The remainder of
the first 1.5 EH/s (50MW) remains on track with the third 20MW data
center building structurally complete and internal fit out of all
three data center buildings progressing to plan
- See here for the
latest update on Mackenzie:
-
https://www.youtube.com/watch?v=Ac1F4h0n7xg&t=7s
- Prince George (2.4
EH/s, 85MW – BC, Canada)
- Foundation works
complete for the first two data center buildings (10MW and 20MW),
and have commenced for the third data center building (20MW)
- Structural steel
for the first 20MW data center building has arrived on site ready
for erection
- Childress (9.6
EH/s, 335MW – Texas, USA)
- Construction
commenced in April with initial ground-breaking and access road
works underway
- Delivery of the first 100MW of data
center buildings remains on track for the end of 2022, with
energization expected in Q1 2023
Canal Flats update (0.8 EH/s, 30MW) – BC,
Canada
Canal Flats (100% renewable operations since
inception3) achieved average monthly operating hashrate in April of
870 PH/s, a 2% increase on March (850 PH/s), driven by the
optimization of rack space. The project continues to exceed
previously announced site capacity of 0.7 EH/s.
Mackenzie update (2.4 EH/s, 80MW) – BC,
Canada
The initial 0.3 EH/s (9MW) at Mackenzie was
successfully commissioned ahead of schedule on April 12. The
commencement of operations marks the delivery of the Company’s
second operating site in BC, Canada. The project achieved monthly
average operating hashrate of 168 PH/s in April (reflecting
commissioning of 0.3 EH/s mid-month).
Construction of the remainder of the first 1.5
EH/s (50MW) remains on track for Q3 2022, with the additional 0.9
EH/s (30MW) expected in 2023. Major electrical equipment
installation is underway (including the substation), along with
internal fit out of all three data center buildings.
Upon completion, the proprietary data centers
are expected to power an additional ~24,000 Bitmain S19j Pro and
S19j miners (already secured), generating 2.4 EH/s of incremental
hashrate and adding approximately 15-20 direct full-time local jobs
in Mackenzie.
See Mackenzie construction progress video at
https://www.youtube.com/watch?v=Ac1F4h0n7xg&t=7s.
Prince George update (2.4 EH/s, 85MW) –
BC, Canada
Foundation works are complete for the first and
second data center buildings (10MW and 20MW) at Prince George and
have commenced for the third data center building (20MW).
Structural steel for the first 20MW data center building has
arrived on site ready for erection, with concrete work underway for
the on-site substation and the third data center building
(20MW).
The first 1.4 EH/s (50MW), comprising three data
centers, remains on track to be energized by the end of Q3 2022,
with the additional 1.0 EH/s (35MW) anticipated to come online in
2023.
Upon completion, the proprietary data centers
are expected to power an additional ~25,000 Bitmain S19j Pro and
S19j miners (already secured), generating 2.4 EH/s of incremental
hashrate and adding approximately 20 direct full-time local jobs in
Prince George.
Childress update (9.6 EH/s, 335MW) –
Texas, USA
Procurement and early construction activities
progressed, with first ground-breaking and access road earthworks
commencing.
Purchase orders have been placed on key
long-lead items, including the 345kV step-down transformer, 138kV
step-down transformers and associated circuit breakers.
The first 3.0 EH/s (100MW) of data center
buildings are expected to be completed by the end of 20224, with an
additional 6.6 EH/s (235MW), comprising S19j Pro miners (already
secured), expected to progressively come online through to Q3 2023.
Based upon the executed 600MW connection agreement with AEP Texas,
the site has the capability to power an additional ~8 EH/s5 (265MW)
of miners beyond the 15 EH/s already secured.
Upon completion and at full capacity, the
proprietary data centers at Childress are expected to generate ~18
EH/s5 of incremental hashrate and add approximately 50-60 direct
full-time local jobs.
Community engagement
Iris Energy is proud to announce the Community
Grants Program for Mackenzie, BC is open for applications. The
program is a key component of our commitment to making a positive
contribution to the local communities in which we operate.
The program will provide funding for local
initiatives that benefit the Mackenzie, BC community in the areas
of community participation, sustainability, safety, technology and
learning. Up to CAD$100,000 of grant funding will be available each
year.
For more information or to access the Community
Grants Program application form please click the link:
https://forms.irisenergy.co/
Future development sites
Development works continued across additional
sites in Canada, the USA and Asia-Pacific, which are expected to
support up to an additional >1GW of aggregate power capacity
capable of powering growth well beyond the Company’s 15 EH/s of
secured miners (~530MW) and 795MW of announced power capacity.
Further details will be provided in due course
including as and when development sites transition to the
construction phase.
Operating and financial results
Daily average operating hashrate chart is available
at https://www.globenewswire.com/NewsRoom/AttachmentNg/83217b88-7dc1-47cc-a1b6-14e411c900d0
Technical commentary
The Company’s average operating hashrate
increased to 1,038 PH/s in April, primarily attributable to the
commissioning of the first 9MW at Mackenzie.
Operating* |
Feb-22 |
Mar-22 |
Apr-22 |
Operating renewable power usage (MW) |
27 |
27 |
33 |
Avg operating hashrate (PH/s) |
844 |
850 |
1,038 |
|
|
|
|
* Reflects actual recorded operating power usage and hashrate
(not nameplate). Note: nameplate capacity is higher than actual
operating power usage due to features of the Company’s proprietary
data center design which utilizes variable speed fans to reduce
power consumption during cooler months, as well as the Company
maintaining a buffer within its infrastructure capacity that can be
also directed to other site uses (e.g., in-house fabrication shop
at Canal Flats is currently operating as Iris Energy has the
advantage of saving time and costs by internally constructing
certain components for its expansion sites).
Financial (unaudited)6 |
Feb-22 |
Mar-22 |
Apr-22 |
Bitcoin mined* |
110 |
121 |
137 |
Mining revenue (US$’000) |
4,495 |
5,136 |
5,434 |
Electricity costs (US$’000) |
895 |
1,029 |
1,205 |
Revenue per Bitcoin (US$) |
40,789 |
42,471 |
39,740 |
Electricity costs per Bitcoin (US$) |
8,118 |
8,512 |
8,8107 |
|
|
|
|
* Reflects Bitcoin mined post deduction of
mining pool fees (currently 0.5% x total Bitcoin mined).
Miner Shipping Schedule8 |
Hardware |
Units |
PH/s (incremental) |
PH/s(cumulative) |
Operating (April 2022) |
S19j Pro9 |
11,480 |
1,038 |
1,038 |
Inventory – in transit |
S19j Pro / S19j |
2,709 |
266 |
1,304 |
Inventory – pending deployment |
S19j Pro / S19j10 |
15,493 |
1,464 |
2,768 |
Q2 2022 |
S19j Pro / S19j |
9,585 |
915 |
3,683 |
Q3 2022 |
S19j Pro / S19j |
7,063 |
659 |
4,342 |
Q4 2022 |
S19j Pro / S19j |
27,973 |
2,781 |
7,123 |
Q1 2023 |
S19j Pro |
26,577 |
2,658 |
9,781 |
Q2 2023 |
S19j Pro |
26,765 |
2,676 |
12,457 |
Q3 2023 |
S19j Pro |
26,952 |
2,695 |
15,152 |
Total |
|
154,597 |
15,152 |
|
|
|
|
|
|
Site Overview |
Capacity (MW) |
Capacity (EH/s) |
Timing8 |
Status |
Canal Flats (BC, Canada) |
30 |
0.8 |
Complete |
Operating |
Mackenzie (BC, Canada) |
9 |
0.3 |
Complete |
Operating |
41 |
1.2 |
Q3 2022 |
Under construction |
30 |
0.9 |
2023 |
Under construction |
Prince George (BC, Canada) |
50 |
1.4 |
Q3 2022 |
Under construction |
35 |
1.0 |
2023 |
Under construction |
Childress (Texas, USA) |
100 |
3.0 |
Q4 20224 |
Under construction |
235 |
6.6 |
2023 |
Under construction |
Total (miners secured) |
530 |
15.2 |
|
|
Childress (Texas, USA) |
265 |
~85 |
|
Potential capacity |
Total (potential expansion) |
795 |
~235 |
|
|
About Iris Energy
Iris Energy is a sustainable Bitcoin mining
company that supports local communities, as well as the
decarbonization of energy markets and the global Bitcoin
network.
- Focus on low-cost
renewables: Iris Energy targets markets with low-cost, excess
and/or under-utilized renewable energy, and where the Company can
support local communities
- Long-term security
over infrastructure, land and power supply: Iris Energy builds,
owns and operates its electrical infrastructure and proprietary
data centers, providing long-term security and operational control
over its assets
- Seasoned management
team: Iris Energy’s team has an impressive track record of success
across energy, infrastructure, renewables, finance, digital assets
and data centers
Forward Looking Statements
This investor update includes “forward-looking
statements” within the meaning of the Private Securities Litigation
Reform Act of 1995. Forward-looking statements generally relate to
future events or Iris Energy’s future financial or operating
performance. For example, forward-looking statements include but
are not limited to the expected increase in the Company’s power
capacity, the Company’s business plan, and the expected schedule
for commencing and/or expanding operations at the Company’s sites.
In some cases, you can identify forward-looking statements by
terminology such as “anticipate,” “believe,” “may,” “can,”
“should,” “could,” “might,” “plan,” “possible,” “project,”
“strive,” “budget,” “forecast,” “expect,” “intend,” “target”,
“will,” “estimate,” “predict,” “potential,” “continue,” “scheduled”
or the negatives of these terms or variations of them or similar
terminology, but the absence of these words does not mean that
statement is not forward-looking. Such forward-looking statements
are subject to risks, uncertainties, and other factors which could
cause actual results to differ materially from those expressed or
implied by such forward looking statements. In addition, any
statements or information that refer to expectations, beliefs,
plans, projections, objectives, performance or other
characterizations of future events or circumstances, including any
underlying assumptions, are forward-looking.
These forward-looking statements are based on
management’s current expectations and beliefs. These statements are
neither promises nor guarantees, but involve known and unknown
risks, uncertainties and other important factors that may cause
Iris Energy’s actual results, performance or achievements to be
materially different from any future results, performance or
achievements expressed or implied by the forward-looking
statements, including, but not limited to: Iris Energy’s limited
operating history with operating losses; electricity outage,
limitation of electricity supply or increase in electricity costs;
long-term outage or limitation of the internet connection at Iris
Energy’s sites; any critical failure of key electrical or data
center equipment; serial defects or underperformance with respect
to Iris Energy’s equipment; failure of suppliers to perform under
the relevant supply contracts for equipment that has already been
procured which may delay Iris Energy’s expansion plans; supply
chain and logistics issues for Iris Energy or Iris Energy’s
suppliers; cancellation or withdrawal of required operating and
other permits and licenses; customary risks in developing
greenfield infrastructure projects; Iris Energy’s evolving business
model and strategy; Iris Energy’s ability to successfully manage
its growth; Iris Energy’s ability to raise additional capital;
competition; Bitcoin prices; risks related to health pandemics
including those of COVID-19; changes in regulation of digital
assets; and other important factors discussed under the caption
“Risk Factors” in Iris Energy’s final prospectus filed pursuant to
Rule 424(b)(4) with the SEC on November 18, 2021, as such factors
may be updated from time to time in its other filings with the SEC,
accessible on the SEC’s website at www.sec.gov and the Investor
Relations section of Iris Energy’s website at
https://investors.irisenergy.co.
These and other important factors could cause
actual results to differ materially from those indicated by the
forward-looking statements made in this investor update. Any
forward-looking statement that Iris Energy makes in this investor
update speaks only as of the date of such statement. Except as
required by law, Iris Energy disclaims any obligation to update or
revise, or to publicly announce any update or revision to, any of
the forward-looking statements, whether as a result of new
information, future events or otherwise.
ContactsMediaJon
SnowballDomestique+61 477 946 068
InvestorsKane DoyleIris Energy+61 422 013
860kane.doyle@irisenergy.co
To keep updated on Iris Energy’s news releases and SEC filings,
please subscribe to email alerts at
https://investors.irisenergy.co/ir-resources/email-alerts.
_______________1 Reflects Bitcoin mined post deduction of mining
pool fees (currently 0.5% x total Bitcoin mined).2 Electricity
costs include actual cost of electricity at Canal Flats and the
estimated cost of electricity at Mackenzie (based on 19 days of
operations which commenced on April 12, 2022), for which BC Hydro
has not yet issued the first monthly invoice.3 Currently 98%
directly from renewable energy sources; 2% from purchase of RECs.4
Data center buildings targeted for completion by end of 2022;
energization of data centers targeted for Q1 2023.5 Equivalent
hashrate potential for the available power capacity assuming
installation of additional Bitmain S19j Pro miners.6 Monthly U.S.
dollar values shown have been translated from Australian dollars
(A$) at the noon buying rate of the Federal Reserve Bank of New
York on the last working day of each month. The rate applied for
April 2022 is A$1 to US$0.7101.7 Electricity costs include actual
cost of electricity at Canal Flats and the estimated cost of
electricity at Mackenzie (based on 19 days of operations which
commenced on April 12, 2022), for which BC Hydro has not yet issued
the first monthly invoice. 8 All timing references are to calendar
quarters and years.9 Includes mix of lower efficiency hardware,
which is estimated to represent less than 2% of the operating 1,038
PH/s.10 Includes mix of lower efficiency hardware, which is
estimated to represent less than 9% of miners pending
deployment.
Photos accompanying this announcement are available at:
https://www.globenewswire.com/NewsRoom/AttachmentNg/b749e65c-5fdf-459a-a1bc-81a45797338d
https://www.globenewswire.com/NewsRoom/AttachmentNg/5693b0fc-ec9b-42c8-94f8-fbc5885c5367
https://www.globenewswire.com/NewsRoom/AttachmentNg/00934821-2881-4a54-b439-cc261dd6be1f
https://www.globenewswire.com/NewsRoom/AttachmentNg/b311e012-7306-4b74-ae7d-eebf27ffc2f8
https://www.globenewswire.com/NewsRoom/AttachmentNg/cab046c8-fe68-4257-b6e5-e2aea83abdd5
https://www.globenewswire.com/NewsRoom/AttachmentNg/b2f489fa-6bc8-4056-8d83-355efe105a35
Iris Energy (NASDAQ:IREN)
Gráfico Histórico do Ativo
De Mai 2023 até Jun 2023
Iris Energy (NASDAQ:IREN)
Gráfico Histórico do Ativo
De Jun 2022 até Jun 2023