Iris Energy Limited (NASDAQ: IREN) (“Iris Energy” or “the
Company”), a leading sustainable Bitcoin miner which is building an
institutional-grade infrastructure platform with 15 EH/s of secured
miners (10 EH/s expected to be operational by early 2023), today
published a monthly investor update for June 2022, containing its
results from operations as well as construction and development
updates.
Key highlights
Key metrics |
May-22 |
Average operating hashrate (PH/s) |
1,165 |
Bitcoin mined1 |
151 |
Mining revenue (US$'000) |
4,868 |
Electricity costs (US$'000)2 |
1,411 |
Revenue per Bitcoin (US$) |
32,264 |
Electricity costs per Bitcoin (US$) |
9,352 |
- Corporate:
- Provided business
overview and update as part of the Company’s Q3 FY22 results
- Continued to
progress additional funding options (see further details
below)
- Welcomed Belinda
Nucifora as Chief Financial Officer
- Operations:
- Increased average
operating hashrate to 1,165 PH/s (+12% increase)
- Monthly operating
revenue of US$4.9 million
- 151 Bitcoin mined
(+10% increase)
- Construction:
- Mackenzie (2.4
EH/s, 50MW initial / 80MW total – BC, Canada)
- Internal data
center fit out continues for the remainder of the first 50MW
- Initial testing
activities for the substation have commenced
- Prince George (2.4
EH/s, 50MW initial / 85MW total – BC, Canada)
- Initial building
construction well advanced on the first data center building
(20MW), with the second data center building (10MW) underway
- Foundation works
for the substation are complete and are well progressed for the
third data center building (20MW)
- Childress (9.6
EH/s, 335MW – Texas, USA)
- Procurement and
early works continued with all required construction permits in
place
- Key long-lead items
have been purchased (including step-down transformers and
associated circuit breakers)
Corporate update
Iris Energy reported its quarterly earnings for the period ended
March 31, 2022 and provided a general business update. The earnings
webcast and the Company’s latest investor presentation are
available on the Company’s website
here: https://investors.irisenergy.co/events-and-presentations.
Multiple debt processes remain underway, with
discussions involving various aspects of the capital structure, for
example, equipment financing similar to the recent $71m NYDIG
facility (1.98 EH/s of miners secured), real asset and
infrastructure financing, as well as corporate credit facilities.
The Company remains focused on prudently assessing various options
and ensuring that any decisions consider an appropriate long-term
capital structure for the Company.
Business summary (as at April 30
(unaudited)):
- $454m of total
equity
- Nil corporate-level
debt3
- $142m of cash
- $180m of
prepayments on contracted miners
- 3.7 EH/s of
operating capacity on track to come online by the end of Q3 2022;
representing illustrative annualized mining profit of $127m (based
on a $30k Bitcoin price4)
The Company also welcomed Belinda Nucifora as Chief Financial
Officer in May. Ms Nucifora is a Chartered Accountant and
experienced CFO, having worked in both listed and private companies
including CFO / senior finance roles with Merrill Lynch, Alinta
Energy, Challenger, Travelex, Slater & Gordon, and Laser
Clinics Australia. Ms Nucifora led the financial due diligence for
the ~$3.1bn5 trade sale of Alinta Energy and Slater & Gordon’s
A$640m external debt reduction and separation of its UK business.
Ms Nucifora has deep experience in financial and strategic business
leadership, including financial leadership of successful growth
companies both organically and through M&A activity.
Canal Flats update (0.8 EH/s, 30MW) – BC,
Canada
Canal Flats (100% renewable operations since
inception6) achieved average monthly operating hashrate in May of
873 PH/s, in line with April (870 PH/s). The project continues to
exceed previously announced site capacity of 0.7 EH/s.
During the month, a further ten Iris Energy
operations staff from our two operating sites in Canal Flats and
Mackenzie completed a two-week ASIC miner maintenance and repair
course provided by Bitmain (the supplier of Iris Energy's S19j Pro
and S19j miners). Iris Energy is able to perform hardware repairs
in-house to help minimize miner downtime.
Mackenzie update (2.4 EH/s, 50MW initial
/ 80MW total) – BC, Canada
The initial 0.3 EH/s (9MW) at Mackenzie, the
Company’s second operating site in BC which was successfully
commissioned ahead of schedule on April 12, achieved average
monthly operating hashrate in May of 292 PH/s, a 74% increase on
April (168 PH/s) reflecting the first full month of operations.
Construction of the remainder of the first 1.5
EH/s (50MW) remains on track for Q3 2022. The internal fit out of
the first data center building is complete and continues to advance
for the second and third data center buildings. All foundation and
sub-surface works for the substation are complete, major electrical
equipment installations continue and initial testing activities
have commenced.
Upon completion, 80MW of proprietary data
centers are expected to power an additional ~24,000 Bitmain S19j
Pro and S19j miners (already secured), generating 2.4 EH/s of
incremental hashrate and adding approximately 15-20 direct
full-time local jobs in Mackenzie.
See Mackenzie construction progress video at
https://www.youtube.com/watch?v=Ac1F4h0n7xg&t=7s.
Prince George update (2.4 EH/s, 50MW
initial / 85MW total) – BC, Canada
The structural steel for the first data center
building (20MW) has been erected and the exterior roofing and
cladding materials are currently being installed. Erection of the
structural steel has commenced on the second data center building
(10MW), and the materials required to complete the building are
on-site. Foundation works are well progressed for the third data
center building (20MW) and completed for the substation.
The first 1.4 EH/s (50MW), comprising three data
centers, remains on track to be energized by the end of Q3 2022,
with the additional 1.0 EH/s (35MW) anticipated to come online in
2023.
Upon completion, 85MW of proprietary data
centers are expected to power an additional ~25,000 Bitmain S19j
Pro and S19j miners (already secured), generating 2.4 EH/s of
incremental hashrate and adding approximately 20 direct full-time
local jobs in Prince George.
Childress update (9.6 EH/s, 335MW) –
Texas, USA
Procurement and early construction activities
continued to progress (all required construction permits are in
place) in conjunction with ongoing civil works. Purchase orders
have been placed on key long-lead items, including the 345kV
step-down transformer, 138kV step-down transformers and associated
circuit breakers, and delivery timelines currently remain on track.
Tendering activities are complete with bulk earthworks and
buildings contracts in the process of being awarded.
The first 3.0 EH/s (100MW) of data center
buildings are expected to be completed by the end of 20227, with an
additional 6.6 EH/s (235MW), comprising S19j Pro miners (already
secured), expected to progressively come online through to Q3 2023.
Based upon the executed 600MW connection agreement with AEP Texas,
the site has the capability to power an additional ~8 EH/s8 (265MW)
of miners beyond the 15 EH/s already secured.
Upon completion and at full capacity, 600MW of
proprietary data centers are expected to generate ~18 EH/s8 of
incremental hashrate and add approximately 50-60 direct full-time
local jobs in Childress.
Community engagement
Iris Energy is pleased to announce the donation
of C$5,000 to the Raven’s Nest Resort, located on Akisqnuk First
Nation land just north of Fairmont Hot Springs, BC. The donation
will provide a cash prize for the PDGA (Professional Disc Golf
Association) tournament being held at the Raven’s Nest Disc Golf
Course in August.
C$5,000 was also donated to the Lheidli T’enneh Elder Society
who are hosting their first ever Moccasin Walk in June this year.
The purpose of the walk is to “promote health, fitness and
community spirit”, with the funds donated to go towards door prizes
and cash sponsorship of the event. The Lheidli T’enneh Elder
Society was established to teach the Lheidli T’enneh First Nation,
and community of Prince George, the richness of the Lheidli T’enneh
culture. For more information, please visit their website at
https://www.lheidli.ca/communication/elders-society/.
Iris Energy also participated in and sponsored
the Mackenzie, BC ‘Spring Exposition’ trade fair in May, with
members of the Iris Energy team organizing a booth to discuss with
the local community the Company’s ongoing development activities as
well as the recently announced Community Grants Program.
Future development sites
Development works continued across additional
sites in Canada, the USA and Asia-Pacific, which are expected to
support up to an additional >1GW of aggregate power capacity
capable of powering growth well beyond the Company’s 15 EH/s of
secured miners (~530MW) and 795MW of announced power capacity.
Further details will be provided in due course
including as and when development sites transition to the
construction phase.
Operating and financial results
Daily average operating hashrate chart is available
at https://www.globenewswire.com/NewsRoom/AttachmentNg/8d79d063-7925-439e-aa8a-6f72dc55f679
Technical commentary
The Company’s average operating hashrate
increased to 1,165 PH/s in May, primarily attributable to the first
full month of operations of the initial 9MW at Mackenzie.
Operating* |
Mar-22 |
Apr-22 |
May-22 |
Operating renewable power usage (MW) |
27 |
339 |
379 |
Avg operating hashrate (PH/s) |
850 |
1,038 |
1,165 |
* Reflects actual recorded operating power usage and hashrate
(not nameplate). Note: nameplate capacity is higher than actual
operating power usage due to features of the Company’s proprietary
data center design which utilizes variable speed fans to reduce
power consumption during cooler months, as well as the Company
maintaining a buffer within its infrastructure capacity that can be
also directed to other site uses (e.g., in-house fabrication shop
at Canal Flats is currently operating as Iris Energy has the
advantage of saving time and costs by internally constructing
certain components for its expansion sites).
Financial (unaudited)10 |
Mar-22 |
Apr-22 |
May-22 |
Bitcoin mined* |
121 |
137 |
151 |
Mining revenue (US$’000) |
5,136 |
5,434 |
4,868 |
Electricity costs (US$’000) |
1,029 |
1,205 |
1,411 |
Revenue per Bitcoin (US$) |
42,471 |
39,740 |
32,264 |
Electricity costs per Bitcoin (US$) |
8,512 |
8,81011 |
9,35211** |
* Reflects Bitcoin mined post deduction of
mining pool fees (currently 0.5% x total Bitcoin mined).** The
increase in electricity costs per Bitcoin in May was primarily
attributable to: (i) ~7% increase in the difficulty-implied global
hashrate (~218 EH/s vs. ~204 EH/s) which resulted in a lower number
of Bitcoin mined per unit of operating hashrate compared to April;
and (ii) a higher interim unit cost of power at Mackenzie – 9MW at
Mackenzie is currently tapping a temporary 25kV distribution feed
which is higher cost vs. the rate paid at Canal Flats (the unit
cost of power is expected to revert to the same rate as Canal Flats
upon commissioning of the first 50MW in Q3 2022).
Miner Shipping Schedule12 |
Hardware |
Units |
PH/s (incremental) |
PH/s(cumulative) |
Operating (May 2022) |
S19j Pro13 |
11,437 |
1,165 |
1,165 |
Inventory – in transit |
S19j Pro / S19j |
3,030 |
295 |
1,460 |
Inventory – pending deployment |
S19j Pro / S19j14 |
18,645 |
1,639 |
3,099 |
Q2 2022 |
S19j Pro / S19j |
6,155 |
584 |
3,683 |
Q3 2022 |
S19j Pro / S19j |
7,063 |
659 |
4,342 |
Q4 2022 |
S19j Pro / S19j |
27,973 |
2,781 |
7,123 |
Q1 2023 |
S19j Pro |
26,577 |
2,658 |
9,781 |
Q2 2023 |
S19j Pro |
26,765 |
2,676 |
12,457 |
Q3 2023 |
S19j Pro |
26,952 |
2,695 |
15,152 |
Total |
|
154,597 |
15,152 |
|
Site Overview |
Capacity (MW) |
Capacity (EH/s) |
Timing12 |
Status |
Canal Flats (BC, Canada) |
30 |
0.8 |
Complete |
Operating |
Mackenzie (BC, Canada) |
9 |
0.3 |
Complete |
Operating |
41 |
1.2 |
Q3 2022 |
Under construction |
30 |
0.9 |
2023 |
Under construction |
Prince George (BC, Canada) |
50 |
1.4 |
Q3 2022 |
Under construction |
35 |
1.0 |
2023 |
Under construction |
Childress (Texas, USA) |
100 |
3.0 |
Q4 20227 |
Under construction |
235 |
6.6 |
2023 |
Under construction |
Total (miners secured) |
530 |
15.2 |
|
|
Childress (Texas, USA) |
265 |
~88 |
|
Potential capacity |
Total (potential expansion) |
795 |
~238 |
|
|
About Iris Energy
Iris Energy is a sustainable Bitcoin mining
company that supports local communities, as well as the
decarbonization of energy markets and the global Bitcoin
network.
- Focus on low-cost
renewables: Iris Energy targets markets with low-cost, excess
and/or under-utilized renewable energy, and where the Company can
support local communities
- Long-term security
over infrastructure, land and power supply: Iris Energy builds,
owns and operates its electrical infrastructure and proprietary
data centers, providing long-term security and operational control
over its assets
- Seasoned management
team: Iris Energy’s team has an impressive track record of success
across energy, infrastructure, renewables, finance, digital assets
and data centers
Forward Looking Statements
This investor update includes “forward-looking
statements” within the meaning of the Private Securities Litigation
Reform Act of 1995. Forward-looking statements generally relate to
future events or Iris Energy’s future financial or operating
performance. For example, forward-looking statements include but
are not limited to the expected increase in the Company’s power
capacity, the Company’s business plan, the Company’s capital
raising plans (including expectations regarding debt processes that
are currently underway), and the expected schedule for commencing
and/or expanding operations at the Company’s sites, and
illustrative mining economics. In some cases, you can identify
forward-looking statements by terminology such as “anticipate,”
“believe,” “may,” “can,” “should,” “could,” “might,” “plan,”
“possible,” “project,” “strive,” “budget,” “forecast,” “expect,”
“intend,” “target”, “will,” “estimate,” “predict,” “potential,”
“continue,” “scheduled” or the negatives of these terms or
variations of them or similar terminology, but the absence of these
words does not mean that statement is not forward-looking. Such
forward-looking statements are subject to risks, uncertainties, and
other factors which could cause actual results to differ materially
from those expressed or implied by such forward looking statements.
In addition, any statements or information that refer to
expectations, beliefs, plans, projections, objectives, performance
or other characterizations of future events or circumstances,
including any underlying assumptions, are forward-looking.
These forward-looking statements are based on
management’s current expectations and beliefs. These statements are
neither promises nor guarantees, but involve known and unknown
risks, uncertainties and other important factors that may cause
Iris Energy’s actual results, performance or achievements to be
materially different from any future results, performance or
achievements expressed or implied by the forward-looking
statements, including, but not limited to: Iris Energy’s limited
operating history with operating losses; electricity outage,
limitation of electricity supply or increase in electricity costs;
long-term outage or limitation of the internet connection at Iris
Energy’s sites; any critical failure of key electrical or data
center equipment; serial defects or underperformance with respect
to Iris Energy’s equipment; failure of suppliers to perform under
the relevant supply contracts for equipment that has already been
procured which may delay Iris Energy’s expansion plans; supply
chain and logistics issues for Iris Energy or Iris Energy’s
suppliers; cancellation or withdrawal of required operating and
other permits and licenses; customary risks in developing
greenfield infrastructure projects; Iris Energy’s evolving business
model and strategy; Iris Energy’s ability to successfully manage
its growth; Iris Energy’s ability to raise additional financing
(whether because of the conditions of the markets, Iris Energy’s
financial condition or otherwise) on a timely basis, or at all,
which could impact the Company’s growth plans; the terms of any
additional financing, which could be less favorable or require Iris
Energy to comply with more onerous covenants or restrictions, any
of which could restrict its business operations and adversely
impact its financial condition, cash flows and results of
operations; competition; Bitcoin prices; risks related to health
pandemics including those of COVID-19; changes in regulation of
digital assets; and other important factors discussed under the
caption “Risk Factors” in Iris Energy’s final prospectus filed
pursuant to Rule 424(b)(4) with the SEC on November 18, 2021, as
such factors may be updated from time to time in its other filings
with the SEC, accessible on the SEC’s website at www.sec.gov and
the Investor Relations section of Iris Energy’s website at
https://investors.irisenergy.co.
These and other important factors could cause
actual results to differ materially from those indicated by the
forward-looking statements made in this investor update. Any
forward-looking statement that Iris Energy makes in this investor
update speaks only as of the date of such statement. Except as
required by law, Iris Energy disclaims any obligation to update or
revise, or to publicly announce any update or revision to, any of
the forward-looking statements, whether as a result of new
information, future events or otherwise.
ContactsMediaJon
SnowballDomestique+61 477 946 068
InvestorsKane DoyleIris Energy+61 422 013
860kane.doyle@irisenergy.co
To keep updated on Iris Energy’s news releases and SEC filings,
please subscribe to email alerts at
https://investors.irisenergy.co/ir-resources/email-alerts.
__________________________________
1 Reflects Bitcoin mined post deduction of mining pool fees
(currently 0.5% x total Bitcoin mined).2 Electricity costs include
actual cost of electricity at Canal Flats and estimated cost of
electricity at Mackenzie (as BC Hydro has not yet issued monthly
invoices for Mackenzie).3 Equipment financing is limited recourse
financing within wholly owned subsidiaries of the Company.4 Please
see the Coinwarz Bitcoin Mining Calculator
(https://www.coinwarz.com/mining/bitcoin/calculator). Inputs for
3.7 EH/s: 3,700 PH/s (hashrate), 130MW (power consumption) and
$0.04 / kWh (electricity costs). Illustrative outputs assume, as a
placeholder only, as at June 3, 2022, Bitcoin price of ~US$30k,
global hashrate (implied by network difficulty) of ~214 EH/s and
transaction fees of ~0.1 BTC per block. Assumes pool fees of 0.5%
of mining rewards and mining hardware operates at 100% uptime.
Note: Online calculator provides illustrative mining profit based
on mining revenue less electricity costs, however, excludes all
other costs e.g., overheads, financing costs and fees (except
mining pool fees). The illustrative outputs assume nameplate
hashrate is fully installed and operating today using the above
assumptions. These assumptions are likely to be different in the
future and users should input their own assumptions.5 Publicly
reported value.6 Currently 98% directly from renewable energy
sources; 2% from purchase of RECs.7 Data center buildings targeted
for completion by end of 2022; energization of data centers
targeted for Q1 2023.8 Equivalent hashrate potential for the
available power capacity assuming installation of additional
Bitmain S19j Pro miners.9 Comprises actual power usage for Canal
Flats and estimated power usage for Mackenzie (as BC Hydro has not
yet issued monthly invoices for Mackenzie disclosing actual billed
power usage). 10 Monthly U.S. dollar values shown have
been translated from Australian dollars (A$) at the noon buying
rate of the Federal Reserve Bank of New York on the last published
working day of each month. The rate applied for May 2022 is A$1 to
US$0.7155.11 Electricity costs include actual cost of electricity
at Canal Flats and estimated cost of electricity at Mackenzie (as
BC Hydro has not yet issued monthly invoices for Mackenzie).12 All
timing references are to calendar quarters and years.13 Includes
mix of lower efficiency hardware, which is estimated to represent
less than 2% of the operating 1,165 PH/s.14 Includes mix of lower
efficiency hardware, which is estimated to represent less than 8%
of miners pending deployment.
Photos accompanying this announcement are available at:
https://www.globenewswire.com/NewsRoom/AttachmentNg/33b54305-ea31-462d-89bf-48caf47e6175
https://www.globenewswire.com/NewsRoom/AttachmentNg/5bb3e775-77df-403b-96ff-d33d97ab13eb
https://www.globenewswire.com/NewsRoom/AttachmentNg/d5d8c701-79ea-4f83-838a-19dccde47d89
https://www.globenewswire.com/NewsRoom/AttachmentNg/89c21fcd-7342-41e2-803a-8c0ae420fc22
https://www.globenewswire.com/NewsRoom/AttachmentNg/a5793a15-00a1-45df-ba13-1eacaae52c9a
https://www.globenewswire.com/NewsRoom/AttachmentNg/fe780622-640a-4ddb-887a-db9aaa135a3d
https://www.globenewswire.com/NewsRoom/AttachmentNg/36bd3282-5876-408e-ad9c-b47eb982d923
https://www.globenewswire.com/NewsRoom/AttachmentNg/1ebdc20f-4004-4c64-a44f-6ccb397a5b0b
https://www.globenewswire.com/NewsRoom/AttachmentNg/c7e0ba66-13e2-48f4-bead-34868e400e28
Iris Energy (NASDAQ:IREN)
Gráfico Histórico do Ativo
De Mai 2023 até Jun 2023
Iris Energy (NASDAQ:IREN)
Gráfico Histórico do Ativo
De Jun 2022 até Jun 2023