Iris Energy Limited (NASDAQ: IREN) (“Iris Energy” or “the
Company”), a leading sustainable Bitcoin miner, today re-iterated
expected total online operating capacity of 3.7 EH/s by the end of
Q3 2022.1
The Company also announced that the expansion from 50MW to 80MW
at its Mackenzie site is progressing ahead of schedule, increasing
expected total online operating capacity to 4.3 EH/s by the end of
Q4 2022.
Given current market conditions, the Company intends to defer
additional major capital expenditure for work beyond the initial
4.3 EH/s of operating capacity to preserve balance sheet
flexibility. The Company currently has no corporate debt on its
balance sheet.2
Operations & Construction Update
- Industry-leading operational uptime
and efficiency across a range of different weather conditions
- Strong and ongoing track record of
execution and project delivery:
- Existing projects delivered ahead of
schedule at each of the Canal Flats (30MW of operating capacity)
and Mackenzie (9MW of operating capacity) sites
- Construction remains on schedule for
50MW of operating capacity at each of the Mackenzie and Prince
George sites in British Columbia, Canada
- Development has progressed ahead of
schedule for expansion to 80MW at the Mackenzie site, now expected
to be operating by the end of Q4 2022
- Preparatory construction activities
are intended to continue at the Childress project in Texas, USA, to
preserve the opportunity to scale once market conditions
improve
The Company’s total online operating capacity is now expected to
be 3.7 EH/s by the end of Q3 2022 and 4.3 EH/s by the end of Q4
2022.
Site |
Capacity (MW) |
Capacity(EH/s) |
Timing |
Status |
Canal Flats (BC, Canada) |
30 |
0.8 |
Complete |
Operating |
Mackenzie (BC, Canada) |
9 |
0.3 |
Complete |
Operating |
41 |
1.2 |
Q3 2022 |
Under construction |
30 |
0.6 |
Q4 2022 |
Under construction |
Prince George (BC, Canada) |
50 |
1.4 |
Q3 2022 |
Under construction |
Total (End of Q4 2022) |
160 |
4.3 |
|
|
Funding & Capital Expenditure Deferral
The Company has explored multiple financing options presented to
it in recent months, and has determined that maintaining balance
sheet flexibility is prudent having regard to market conditions and
available financing terms.
As market conditions have deteriorated, the Company continues to
believe this is the prudent approach. As a result, the Company
expects to defer major additional capital expenditure until the
current market uncertainty subsides and financing terms improve.
The Company will continue to monitor funding markets closely, and
if conditions become favorable, the Company expects to explore
raising additional capital.
The Company has made $130m of payments in respect of
contracted miners above the initial 4.3 EH/s, which are subject to
ongoing discussions.3 The Company’s planning and contractual
arrangements have also mitigated material financial commitments to
the broader buildout of Childress infrastructure beyond ongoing
preparatory construction activities.
While the Company continues to target expansion of total
operating capacity above 4.3 EH/s, such plans are expected to be
delayed and the Company will continue to review such plans in light
of evolving market conditions.
The Company expects to continue liquidating Bitcoin mining
rewards on a daily basis, as has been the case since Iris Energy
started mining Bitcoin in 2019, including when Bitcoin hit an
all-time high of approximately $68,000 in November 2021.
Financial & Business Update
As of May 31, 2022, the Company had approximately
(preliminary unaudited)4:
- $454m of total equity
- Nil corporate-level debt5
- $93m of cash (after expected
remaining capital expenditure to achieve the initial 4.3
EH/s)6
- $317m investment in miners &
infrastructure expected in order to achieve the initial 4.3
EH/s7
- $130m of payments in respect of
contracted miners above the initial 4.3 EH/s
- $19m of deposits and prepayments8
with AEP for the 600MW high-voltage electrical connection at
Childress
Iris Energy’s Co-Founder & Co-CEO, Daniel Roberts, said:
“While we believe the long-term value proposition of Bitcoin
will continue to grow stronger, we are respectful of the current
market environment.
We continue to be excited about the opportunities in front of
us; the exceptional facilities we are building, our operational
performance and the way our experienced global team continues to
deliver project after project.
Now is the time to be circumspect, monitor the market closely
and then continue our growth trajectory.”
Iris Energy’s President, Lindsay Ward, said:
“Following delivery of the first two projects ahead of schedule,
the team has continued to keep construction and execution
activities on track at Mackenzie and Prince George despite market
volatility.
We look forward to commissioning the initial 50MW at each
project by the end of Q3 2022 as planned, as well as accelerating
the expansion to 80MW at Mackenzie by the end of Q4 2022.
We expect to continue work at Childress to preserve optionality
going into 2023 for our 600MW project in Texas.”
About Iris
Energy
Iris Energy is a sustainable Bitcoin mining
company that supports local communities, as well as the
decarbonization of energy markets and the global Bitcoin
network.
- Focus on
low-cost renewables: Iris Energy targets markets with low-cost,
excess and/or under-utilized renewable energy, and where the
Company can support local communities
- Long-term
security over infrastructure, land and power supply: Iris Energy
builds, owns and operates its electrical infrastructure and
proprietary data centers, providing long-term security and
operational control over its assets
- Seasoned
management team: Iris Energy’s team has an impressive track record
of success across energy, infrastructure, renewables, finance,
digital assets and data centers with cumulative experience in
delivering >$25bn in energy and infrastructure projects
globally
Forward-Looking Statements
This press release includes “forward-looking statements” within
the meaning of the Private Securities Litigation Reform Act of
1995. Forward-looking statements generally relate to future events
or Iris Energy’s future financial or operating performance. For
example, forward-looking statements include but are not limited to
the expected increase in the Company’s power capacity and operating
capacity, the Company’s business plan, the Company’s capital
raising plans, the Company’s anticipated capital expenditures and
additional borrowings, the impact of discussions with Bitmain
Technologies Limited regarding the Company’s hardware purchase
contract for additional miners, and the expected schedule for
commencing and/or expanding operations at the Company’s sites. In
some cases, you can identify forward-looking statements by
terminology such as “anticipate,” “believe,” “may,” “can,”
“should,” “could,” “might,” “plan,” “possible,” “project,”
“strive,” “budget,” “forecast,” “expect,” “intend,” “target”,
“will,” “estimate,” “predict,” “potential,” “continue,” “scheduled”
or the negatives of these terms or variations of them or similar
terminology, but the absence of these words does not mean that
statement is not forward-looking. Such forward-looking statements
are subject to risks, uncertainties, and other factors which could
cause actual results to differ materially from those expressed or
implied by such forward looking statements. In addition, any
statements or information that refer to expectations, beliefs,
plans, projections, objectives, performance or other
characterizations of future events or circumstances, including any
underlying assumptions, are forward-looking.
These forward-looking statements are based on management’s
current expectations and beliefs. These statements are neither
promises nor guarantees, but involve known and unknown risks,
uncertainties and other important factors that may cause Iris
Energy’s actual results, performance or achievements to be
materially different from any future results, performance or
achievements expressed or implied by the forward-looking
statements, including, but not limited to: Iris Energy’s limited
operating history with operating losses; electricity outage,
limitation of electricity supply or increase in electricity costs;
long term outage or limitation of the internet connection at Iris
Energy’s sites; any critical failure of key electrical or data
center equipment; serial defects or underperformance with respect
to Iris Energy’s equipment; failure of suppliers to perform under
the relevant supply contracts for equipment that has already been
procured which may delay Iris Energy’s expansion plans; supply
chain and logistics issues for Iris Energy or Iris Energy’s
suppliers; cancellation or withdrawal of required operating and
other permits and licenses; customary risks in developing
greenfield infrastructure projects; Iris Energy’s evolving business
model and strategy; Iris Energy’s ability to successfully manage
its growth; Iris Energy’s ability to raise additional financing
(whether because of the conditions of the markets, Iris Energy’s
financial condition or otherwise) on a timely basis, or at all,
which could adversely impact the Company’s ability to meet its
capital commitments (including payments due under its hardware
purchase contracts with Bitmain Technologies Limited) and the
Company’s growth plans; failure to make payments under any hardware
purchase contract with Bitmain on a timely basis could result in
liquidated damages or other claims against Iris Energy, any of
which could result in a loss of all or a portion of any prepayments
or deposits made under the relevant contract or other liabilities
in respect of the relevant contract, and could also result in Iris
Energy not receiving certain discounts under the relevant contract
or receiving the relevant hardware at all, any of which could
adversely impact its business, operating expansion plans, financial
condition, cash flows and results of operations; the terms of any
additional financing, which could be less favorable or require Iris
Energy to comply with more onerous covenants or restrictions, any
of which could restrict its business operations and adversely
impact its financial condition, cash flows and results of
operations; competition; Bitcoin prices, which could adversely
impact its financial condition, cash flows and results of
operations, as well as its ability to raise additional financing;
risks related to health pandemics including those of COVID-19;
changes in regulation of digital assets; and other important
factors discussed under the caption “Risk Factors” in Iris Energy’s
final prospectus filed pursuant to Rule 424(b)(4) with the SEC on
November 18, 2021 , as such factors may be updated from time to
time in its other filings with the SEC, accessible on the SEC’s
website at www.sec.gov and the Investor Relations section of Iris
Energy’s website at https://investors.irisenergy.co.
These and other important factors could cause actual results to
differ materially from those indicated by the forward-looking
statements made in this press release. Any forward-looking
statement that Iris Energy makes in this press release speaks only
as of the date of such statement. Except as required by law, Iris
Energy disclaims any obligation to update or revise, or to publicly
announce any update or revision to, any of the forward-looking
statements, whether as a result of new information, future events
or otherwise.
Contacts Media
Jon Snowball Domestique+61 477 946 068
Investors Kane Doyle Iris Energy+61 422 013
860kane.doyle@irisenergy.co
To keep updated on Iris Energy’s news releases and SEC filings,
please subscribe to email alerts at
https://investors.irisenergy.co/ir-resources/email-alerts.
___________________
1 All timing references in this release are to calendar quarters
and calendar years, unless otherwise specified.2 Existing equipment
financing is limited recourse financing within wholly owned
subsidiaries of the Company.3 The timing and volume of any future
deliveries in respect of the separate $400m hardware purchase
contract for miners in excess of the initial 4.3 EH/s are expected
to be impacted, with upcoming payments under that contract not
currently expected to be made. The Company can make no assurances
as to the outcome of these discussions (including any impact on the
Company’s expansion plans or payments made under that contract).4
The preliminary financial information as of May 31, 2022 included
in this release is not subject to the same closing procedures as
our unaudited quarterly financial results and has not been reviewed
by our independent registered public accounting firm. The
preliminary financial information included in this release does not
represent a comprehensive statement of our financial results or
financial position, and should not be viewed as a substitute for
unaudited financial statements prepared in accordance with
International Financial Reporting Standards. Accordingly, you
should not place undue reliance on the preliminary financial
information included in this release.5 Existing equipment financing
is limited recourse financing within wholly owned subsidiaries of
the Company. Estimated balance outstanding under existing
facilities is not anticipated to increase above $109.4m (expected
balance outstanding as of June 30, 2022) following anticipated
drawdowns and scheduled amortization.6 $118m cash balance as of May
31, 2022, less $25m of expected remaining capital expenditure to
achieve the initial 4.3 EH/s (net of anticipated additional
drawdowns under existing equipment financing and anticipated sales
tax refunds).7 Figure includes estimated remaining capital
expenditure in relation to the initial 4.3 EH/s.8 Up to
approximately $15.5m is refundable upon energization of the
Childress project.
Iris Energy (NASDAQ:IREN)
Gráfico Histórico do Ativo
De Mai 2023 até Jun 2023
Iris Energy (NASDAQ:IREN)
Gráfico Histórico do Ativo
De Jun 2022 até Jun 2023