Iris Energy Limited (NASDAQ: IREN) (“Iris Energy” or “the
Company”), a leading sustainable Bitcoin miner which is building an
institutional-grade infrastructure platform (4.3 EH/s expected to
be operational by the end of Q4 2022), today published a monthly
investor update for June 2022, containing its results from
operations as well as construction and development updates.
Key highlights1
Key metrics2 |
Jun-22 |
Average operating hashrate (PH/s) |
1,164 |
Bitcoin mined3 |
148 |
Mining revenue (US$'000) |
3,546 |
Electricity costs (US$'000)4 |
1,315 |
Revenue per Bitcoin (US$) |
23,925 |
Electricity costs per Bitcoin (US$) |
8,875 |
- Corporate:
- Operating capacity
guidance increased from 3.7 EH/s to 4.3 EH/s by the end of Q4
2022
- Deferral of
additional major capital expenditure for work beyond the initial
4.3 EH/s of operating capacity
- Preservation of
balance sheet flexibility having regard to market conditions and
available financing terms
- Operations:
- Average operating
hashrate of 1,164 PH/s
- Monthly operating
revenue of US$3.5 million
- 148 Bitcoin
mined
- Development:
- Development has
progressed ahead of schedule for expansion from 50MW to 80MW at the
Mackenzie site, now expected to be operating by the end of Q4 2022
(previously 2023)
- Construction:
- Mackenzie (2.1
EH/s, 50MW initial / 80MW total – BC, Canada)
- Internal data
center fit out complete for the remainder of the first 50MW
- All major equipment
installed in the substation; testing and commissioning ongoing
- Prince George (1.4
EH/s, 50MW – BC, Canada)
- Foundation works
complete for all three data center buildings (2 x 20MW, 1 x
10MW)
- Building
construction advanced on the first and second data center buildings
(20MW and 10MW), with the third data center building (20MW)
underway
- Erection of the
structural steel in the substation progressing
- Childress
(preparatory construction activities – Texas, USA)
- Preparatory
construction activities remain ongoing
- Procurement and
early works continued with all required construction permits in
place
- Key long-lead items
have been purchased (including step-down transformers and
associated circuit breakers)
Corporate update
On June 21, 2022, the Company announced that,
given current market conditions, it intends to defer additional
major capital expenditure for work beyond the initial 4.3 EH/s of
operating capacity to preserve balance sheet flexibility.
The Company has explored multiple financing
options presented to it in recent months, and has determined that
maintaining balance sheet flexibility is prudent having regard to
market conditions and available financing terms.
As market conditions have deteriorated, the
Company continues to believe this is the prudent approach. As a
result, the Company expects to defer major additional capital
expenditure until the current market uncertainty subsides and
financing terms improve. The Company will continue to monitor
funding markets closely, and if conditions become favorable, the
Company expects to explore raising additional capital.
The Company has made $130m of payments in
respect of contracted miners above the initial 4.3 EH/s, which are
subject to ongoing discussions.5 The Company’s planning and
contractual arrangements have also mitigated material financial
commitments to the broader buildout of Childress infrastructure
beyond ongoing preparatory construction activities.
While the Company continues to target expansion
of total operating capacity above 4.3 EH/s, such plans are expected
to be delayed and the Company will continue to review such plans in
light of evolving market conditions.
The Company expects to continue liquidating
Bitcoin mining rewards on a daily basis, as has been the case since
Iris Energy started mining Bitcoin in 2019, including when Bitcoin
hit an all-time high of approximately $68,000 in November 2021.
As of May 31, 2022, the Company
had approximately (preliminary unaudited)6:
- $454m of total
equity
- Nil corporate-level
debt7
- $93m of cash
(after expected remaining capital expenditure to achieve the
initial 4.3 EH/s)8
- $317m investment in
miners and infrastructure expected in order to achieve the initial
4.3 EH/s9
- $130m of
payments in respect of contracted miners above the initial 4.3
EH/s
- $19m of deposits
and prepayments10 with AEP for the 600MW high-voltage electrical
connection at Childress
4.3 EH/s of operating capacity would represent
illustrative annualized mining profit of $67m (based on a $20k
Bitcoin price11) if installed and operating today.
Canal Flats update (0.8 EH/s, 30MW) –
BC, Canada
Canal Flats has been powered by 100% renewable
energy since inception.12
Canal Flats achieved average monthly operating
hashrate in June of 872 PH/s, in line with May (873 PH/s). The
project continues to exceed previously announced site capacity of
0.7 EH/s.
Mackenzie update (2.1 EH/s, 50MW initial
/ 80MW total) – BC, Canada
Mackenzie has been powered by 100% renewable
energy since inception.12
The initial 9MW at Mackenzie achieved average
monthly operating hashrate in June of 292 PH/s, in line with May
(292 PH/s).
Construction of the remainder of the first 1.5
EH/s (50MW) remains on track for Q3 2022. The internal fit out of
the data center buildings is complete and commissioning activities
are underway.
All major electrical equipment has been
installed in the substation and testing and commissioning
activities are ongoing. Construction of the high voltage connection
to the BC Hydro transmission network has commenced.
Upon completion, 80MW of proprietary data
centers are expected to power an additional ~22,000 Bitmain S19j
Pro and S19j miners (already under contract), generating 2.1 EH/s
of incremental hashrate.
See Mackenzie construction progress video at
https://www.youtube.com/watch?v=Ac1F4h0n7xg&t=7s.
Prince George update (1.4 EH/s, 50MW) –
BC, Canada
Foundations and structural steel for the three
data center buildings (2 x 20MW, 1 x 10MW) is complete.
Remaining building construction is advanced on
the first and second data center building (20MW and 10MW) and is
underway for the third data center building (20MW). Internal fit
out of the first data center building (20MW) and second data center
building (10MW) is also progressing.
Prince George remains on track to be energized
by the end of Q3 2022 and upon completion, 50MW of proprietary data
centers are expected to power an additional ~15,000 Bitmain S19j
Pro and S19j miners (already under contract), generating 1.4 EH/s
of incremental hashrate.
Childress update – Texas,
USA
As previously announced, the Company intends to
defer additional major capital expenditure related to the broader
buildout of Childress infrastructure. Preparatory construction
activities are intended to continue at Childress in order to
preserve the opportunity to scale once market conditions
improve.
Procurement and early construction activities
continued to progress (all required construction permits are in
place). Construction of the access road to the main development
area and site civil works are ongoing. Purchase orders have been
placed on key long-lead items, including the 345kV step-down
transformer, 138kV step-down transformer and associated circuit
breakers.
Community engagement
Iris Energy is proud to announce the Community
Grants Program for Childress is open for applications. The program
is a key component of our commitment to making a positive
contribution to the local communities in which we operate. The
program will provide funding for local initiatives that benefit the
Childress community in the areas of community participation,
sustainability, safety, diversity, technology and learning.
For more information or to access the Community
Grants Program application form please click the link:
https://forms.irisenergy.co/community-grants-program-texas.
Future development sites
Development works continued across additional
sites in Canada, the USA and Asia-Pacific, which have the potential
to support up to an additional >1GW of aggregate power capacity
capable of powering growth beyond the Company’s 795MW of announced
power capacity.
Operating and financial results
Daily average operating hashrate chart is available at
https://www.globenewswire.com/NewsRoom/AttachmentNg/59815260-e3ee-45c8-9f4d-5f5d04507372
Technical commentary
The Company’s average operating hashrate was
1,164 PH/s in June.
The decrease in electricity costs in June
compared to May was primarily due to one less day in the month as
well as foreign exchange impacts.
The comparatively higher electricity costs per
Bitcoin mined across May and June (vs. April) are attributable to
the Company paying a higher interim unit cost of power at Mackenzie
via the 9MW temporary 25kV distribution feed. Rates at Mackenzie
are expected to revert to the same lower transmission rate as Canal
Flats upon commissioning of the remainder of the first 50MW in Q3
2022.
Operating* |
Apr-22 |
May-22 |
Jun-22 |
Renewable energy usage
(MW)13 |
33 |
37 |
36 |
Avg operating hashrate (PH/s) |
1,038 |
1,165 |
1,164 |
* Reflects actual recorded operating power usage and hashrate
(not nameplate). Note: nameplate capacity is higher than actual
operating power usage due to features of the Company’s proprietary
data center design which utilizes variable speed fans to reduce
power consumption during cooler months, as well as the Company
maintaining a buffer within its infrastructure capacity that can be
also directed to other site uses (e.g. in-house fabrication shop at
Canal Flats is currently operating as Iris Energy has the advantage
of saving time and costs by internally constructing certain
components for its expansion sites).
Financial (unaudited)14 |
Apr-22 |
May-22 |
Jun-22 |
Bitcoin mined* |
137 |
151 |
148 |
Mining revenue (US$’000) |
5,434 |
4,868 |
3,546 |
Electricity costs (US$’000) |
1,205 |
1,411 |
1,315** |
Revenue per Bitcoin (US$) |
39,740 |
32,264 |
23,925 |
Electricity costs per Bitcoin (US$)15 |
8,810 |
9,352 |
8,875 |
* Reflects Bitcoin mined post deduction of
mining pool fees (currently 0.5% x total Bitcoin mined).** The
decrease in electricity costs (vs. May) was primarily due to one
less day in the month and foreign exchange impacts.
Miner Shipping Schedule |
Hardware |
Units |
EH/s(incremental) |
EH/s(cumulative) |
Operating (June 2022) |
S19j Pro16 |
11,298 |
1.2 |
1.2 |
Inventory – pending deployment |
S19j Pro / S19j17 |
24,276 |
2.2 |
3.4 |
Inventory – in transit |
S19j |
670 |
0.1 |
3.4 |
Q3 2022 |
S19j Pro / S19j |
8,537 |
0.8 |
4.2 |
Q4 2022 |
S19j |
1,500 |
0.1 |
4.3 |
Total |
|
46,281 |
4.318 |
4.3 |
Site |
Capacity (MW) |
Capacity(EH/s) |
Timing |
Status |
Canal Flats (BC, Canada) |
30 |
0.8 |
Complete |
Operating |
Mackenzie (BC, Canada) |
9 |
0.3 |
Complete |
Operating |
41 |
1.2 |
Q3 2022 |
Under construction |
30 |
0.6 |
Q4 2022 |
Under construction |
Prince George (BC, Canada) |
50 |
1.4 |
Q3 2022 |
Under construction |
Total (End of Q4 2022) |
160 |
4.3 |
|
|
About Iris Energy
Iris Energy is a sustainable Bitcoin mining
company that supports local communities, as well as the
decarbonization of energy markets and the global Bitcoin
network.
- Focus on low-cost
renewables: Iris Energy targets markets with low-cost, excess
and/or under-utilized renewable energy, and where the Company can
support local communities
- Long-term security
over infrastructure, land and power supply: Iris Energy builds,
owns and operates its electrical infrastructure and proprietary
data centers, providing long-term security and operational control
over its assets
- Seasoned management
team: Iris Energy’s team has an impressive track record of success
across energy, infrastructure, renewables, finance, digital assets
and data centers
Forward Looking Statements
This investor update includes “forward-looking
statements” within the meaning of the Private Securities Litigation
Reform Act of 1995. Forward-looking statements generally relate to
future events or Iris Energy’s future financial or operating
performance. For example, forward-looking statements include but
are not limited to the expected increase in the Company’s power
capacity and operating capacity, the Company’s business plan, the
Company’s capital raising plans, the Company’s anticipated capital
expenditures and additional borrowings, the impact of discussions
with Bitmain Technologies Limited regarding the Company’s hardware
purchase contract for additional miners, and the expected schedule
for commencing and/or expanding operations at the Company’s sites,
and illustrative mining economics. In some cases, you can identify
forward-looking statements by terminology such as “anticipate,”
“believe,” “may,” “can,” “should,” “could,” “might,” “plan,”
“possible,” “project,” “strive,” “budget,” “forecast,” “expect,”
“intend,” “target”, “will,” “estimate,” “predict,” “potential,”
“continue,” “scheduled” or the negatives of these terms or
variations of them or similar terminology, but the absence of these
words does not mean that statement is not forward-looking. Such
forward-looking statements are subject to risks, uncertainties, and
other factors which could cause actual results to differ materially
from those expressed or implied by such forward looking statements.
In addition, any statements or information that refer to
expectations, beliefs, plans, projections, objectives, performance
or other characterizations of future events or circumstances,
including any underlying assumptions, are forward-looking.
These forward-looking statements are based on
management’s current expectations and beliefs. These statements are
neither promises nor guarantees, but involve known and unknown
risks, uncertainties and other important factors that may cause
Iris Energy’s actual results, performance or achievements to be
materially different from any future results, performance or
achievements expressed or implied by the forward-looking
statements, including, but not limited to: Iris Energy’s limited
operating history with operating losses; electricity outage,
limitation of electricity supply or increase in electricity costs;
long-term outage or limitation of the internet connection at Iris
Energy’s sites; any critical failure of key electrical or data
center equipment; serial defects or underperformance with respect
to Iris Energy’s equipment; failure of suppliers to perform under
the relevant supply contracts for equipment that has already been
procured which may delay Iris Energy’s expansion plans; supply
chain and logistics issues for Iris Energy or Iris Energy’s
suppliers; cancellation or withdrawal of required operating and
other permits and licenses; customary risks in developing
greenfield infrastructure projects; Iris Energy’s evolving business
model and strategy; Iris Energy’s ability to successfully manage
its growth; Iris Energy’s ability to raise additional financing
(whether because of the conditions of the markets, Iris Energy’s
financial condition or otherwise) on a timely basis, or at all,
which could adversely impact the Company’s ability to meet its
capital commitments (including payments due under its hardware
purchase contracts with Bitmain Technologies Limited) and the
Company’s growth plans; failure to make payments under any hardware
purchase contract with Bitmain on a timely basis could result in
liquidated damages or other claims against Iris Energy, any of
which could result in a loss of all or a portion of any prepayments
or deposits made under the relevant contract or other liabilities
in respect of the relevant contract, and could also result in Iris
Energy not receiving certain discounts under the relevant contract
or receiving the relevant hardware at all, any of which could
adversely impact its business, operating expansion plans, financial
condition, cash flows and results of operations; the terms of any
additional financing, which could be less favorable or require Iris
Energy to comply with more onerous covenants or restrictions, any
of which could restrict its business operations and adversely
impact its financial condition, cash flows and results of
operations; competition; Bitcoin prices; risks related to health
pandemics including those of COVID-19; changes in regulation of
digital assets; and other important factors discussed under the
caption “Risk Factors” in Iris Energy’s final prospectus filed
pursuant to Rule 424(b)(4) with the SEC on November 18, 2021, as
such factors may be updated from time to time in its other filings
with the SEC, accessible on the SEC’s website at www.sec.gov and
the Investor Relations section of Iris Energy’s website at
https://investors.irisenergy.co.
These and other important factors could cause
actual results to differ materially from those indicated by the
forward-looking statements made in this investor update. Any
forward-looking statement that Iris Energy makes in this investor
update speaks only as of the date of such statement. Except as
required by law, Iris Energy disclaims any obligation to update or
revise, or to publicly announce any update or revision to, any of
the forward-looking statements, whether as a result of new
information, future events or otherwise.
ContactsMediaJon
SnowballDomestique+61 477 946 068
InvestorsKane DoyleIris Energy+61 422 013
860kane.doyle@irisenergy.co
To keep updated on Iris Energy’s news releases and SEC filings,
please subscribe to email alerts at https://
investors.irisenergy.co/ir-resources/email-alerts.
_________________________
1 All timing references in this investor update
are to calendar quarters and calendar years, unless otherwise
specified. 2 U.S. dollar values shown for the month of June
2022 have been translated from Australian dollars (A$) at the
published noon buying rate of the Federal Reserve Bank of New York
available on the last working day of June 2022. The rate applied
for June 2022 is A$1 to US$0.6946. The preliminary financial
information for the month of June 2022 included in this investor
update is not subject to the same closing procedures as our
unaudited quarterly financial results and has not been reviewed by
our independent registered public accounting firm. The preliminary
financial information included in this investor update does not
represent a comprehensive statement of our financial results or
financial position, and should not be viewed as a substitute for
unaudited financial statements prepared in accordance with
International Financial Reporting Standards. Accordingly, you
should not place undue reliance on the preliminary financial
information included in this investor update. 3 Reflects Bitcoin
mined post deduction of mining pool fees (currently 0.5% x total
Bitcoin mined).4 Electricity costs include actual cost of
electricity at Canal Flats and estimated cost of electricity at
Mackenzie.5 The timing and volume of any future deliveries in
respect of the separate $400m hardware purchase contract for miners
in excess of the initial 4.3 EH/s are expected to be impacted, with
upcoming payments under that contract not currently expected to be
made. The Company can make no assurances as to the outcome of these
discussions (including any impact on the Company’s expansion plans
or payments made under that contract).6 The preliminary financial
information as of May 31, 2022 included in this investor update is
not subject to the same closing procedures as our unaudited
quarterly financial results and has not been reviewed by our
independent registered public accounting firm. The preliminary
financial information included in this investor update does not
represent a comprehensive statement of our financial results or
financial position, and should not be viewed as a substitute for
unaudited financial statements prepared in accordance with
International Financial Reporting Standards. Accordingly, you
should not place undue reliance on the preliminary financial
information included in this investor update.7 Existing equipment
financing is limited recourse financing within wholly owned
subsidiaries of the Company. Estimated balance outstanding under
existing facilities is not anticipated to increase above $109.4m
(expected balance outstanding as of June 30, 2022) following
anticipated drawdowns and scheduled amortization.8 $118m cash
balance as of May 31, 2022, less $25m of expected remaining capital
expenditure to achieve the initial 4.3 EH/s (net of anticipated
additional drawdowns under existing equipment financing and
anticipated sales tax refunds).9 Figure includes estimated
remaining capital expenditure in relation to the initial 4.3
EH/s.10 Up to approximately $15.5m is refundable upon energization
of the Childress project.11 Please see the Coinwarz Bitcoin Mining
Calculator (https://www.coinwarz.com/mining/bitcoin/calculator).
Inputs for 4.3 EH/s: 4,300 PH/s (hashrate), 150MW (power
consumption) and $0.05 / kWh (electricity costs inclusive of fixed
demand charge). Illustrative outputs assume, as a placeholder only,
Bitcoin price of ~US$20k, global hashrate (implied by network
difficulty) of ~215 EH/s and transaction fees of ~0.1 BTC per
block. Assumes pool fees of 0.5% of mining rewards and mining
hardware operates at 100% uptime. Note: Online calculator provides
illustrative mining profit based on mining revenue less electricity
costs, however, excludes all other costs e.g., overheads, financing
costs and fees (except mining pool fees). The illustrative outputs
assume nameplate hashrate is fully installed and operating today
using the above assumptions. These assumptions are likely to be
different in the future and users should input their own
assumptions. Accordingly, you should not place undue reliance on
the illustrative metrics. 12 Currently 98% directly from renewable
energy sources; 2% from purchase of RECs.13 Comprises actual power
usage for Canal Flats and estimated power usage for
Mackenzie.14U.S. dollar values shown for the month of June 2022
have been translated from Australian dollars (A$) at the published
noon buying rate of the Federal Reserve Bank of New York available
on the last working day of June 2022. The rate applied for June
2022 is A$1 to US$0.6946. The rates applied for April and May 2022
are consistent with the rates applied in the corresponding investor
updates. 15Electricity costs include actual cost of electricity at
Canal Flats and estimated cost of electricity at Mackenzie. 16
Includes mix of lower efficiency hardware, which is estimated to
represent less than 2% of the operating 1.2 EH/s.17 Includes mix of
lower efficiency hardware, which is estimated to represent less
than 6% of miners pending deployment.18 The Company has made $130m
of payments in respect of contracted miners above the initial 4.3
EH/s, which are subject to ongoing discussions with
Bitmain. Please see footnote 5 for more details.
Photos accompanying this announcement are available
at:https://www.globenewswire.com/NewsRoom/AttachmentNg/43e25336-9ddc-40b3-9cf7-bbbcf6a7d0f7
https://www.globenewswire.com/NewsRoom/AttachmentNg/75b1c444-9923-4d7d-801a-92a37c899d9b
https://www.globenewswire.com/NewsRoom/AttachmentNg/c3dbc7ac-9c8e-47f0-8f03-66f53353ab4c
https://www.globenewswire.com/NewsRoom/AttachmentNg/e9694906-1a0c-4290-9750-6396dd0a7306
https://www.globenewswire.com/NewsRoom/AttachmentNg/8c0d24ba-6d3b-4038-9b42-0946f292c9e1
https://www.globenewswire.com/NewsRoom/AttachmentNg/426e0374-5cca-4a1c-9789-0fe83e6b9dd4
Iris Energy (NASDAQ:IREN)
Gráfico Histórico do Ativo
De Abr 2023 até Mai 2023
Iris Energy (NASDAQ:IREN)
Gráfico Histórico do Ativo
De Mai 2022 até Mai 2023