Iris Energy Limited (NASDAQ: IREN) (“Iris Energy” or “the
Company”), a leading owner and operator of institutional-grade,
highly efficient proprietary Bitcoin mining data centers powered by
100% renewable energy, today published a monthly investor update
for July 2022, containing its results from operations as well as
construction and development updates.
Key Highlights1
Key metrics2 |
Jul-22 |
Average operating hashrate (PH/s) |
1,117 |
Bitcoin mined3 |
154 |
Mining revenue (US$'000) |
3,358 |
Electricity costs (US$'000) |
1,360 |
Revenue per Bitcoin (US$) |
21,823 |
Electricity costs per Bitcoin (US$) |
8,836 |
- Updates post month
end:
- Commissioned
remainder of the first 1.5 EH/s (50MW) at Mackenzie ahead of
schedule, approximately doubling operating capacity to exceed 2.3
EH/s
- Reached agreement
with Bitmain Technologies Limited to ship an additional 1.7 EH/s of
S19j Pro miners in August 2022, increasing expected operating
capacity from 4.3 EH/s to 6.0 EH/s
- Corporate:
- Welcomed Heather
Miller as Vice President – People, Culture and Community and Javier
Garcia as General Manager – Engineering
- Iris Energy to
present at the Canaccord Genuity 42nd Annual Growth Conference in
Boston
- Operations:
- Average operating
hashrate of 1,117 PH/s
- Monthly operating
revenue of US$3.4 million
- 154 Bitcoin
mined
- Construction:
- Mackenzie (2.1
EH/s, 80MW – BC, Canada)
- Construction
activities continue to progress for the expansion from 50MW to 80MW
and remains on track to be completed by the end of Q4 2022
- Prince George (1.4
EH/s, 50MW – BC, Canada)
- Construction
substantially complete for the first and second data center
buildings (20MW and 10MW), with the third data center building
(20MW) well advanced
- Internal fit out of
all three data center buildings underway
- Installation of
major equipment in the substation has commenced
- Childress
(preparatory construction activities – Texas, USA)
- Preparatory
construction and procurement activities remain ongoing at the 600MW
site
- Potential
development options under consideration, including with respect to
the recently announced additional 1.7 EH/s of contracted
miners
Corporate update
Miner deliveries during 2022 increased from 4.3
EH/s to 6.0 EH/s
On August 1, 2022, the Company announced that it
had reached agreement with Bitmain Technologies Limited (“Bitmain”)
to ship an additional 1.7 EH/s of S19j Pro miners in August 2022.
This increases the Company’s expected operating capacity from 4.3
EH/s to 6.0 EH/s. The Company is currently working through
deployment options across its sites, including Childress, for the
additional capacity.
$46.7 million of the previous $130 million of
payments made to Bitmain have been applied to secure the additional
1.7 EH/s, and utilization of the remaining $83.3 million of
payments in respect of additional contracted miners above the 6.0
EH/s continue to be subject to ongoing discussions with
Bitmain.4
Heather Miller, Vice President – People, Culture
and Community
The Company welcomed Heather Miller as Vice
President – People, Culture and Community. Heather has over 15
years’ senior People and Culture professional experience across all
aspects of HR and joins Iris Energy from Nutrien, a ~US$45bn5
multinational agribusiness, where she was Senior Director, Digital
HR & HR Business Relations.
Javier Garcia, General Manager – Engineering
The Company welcomed Javier Garcia as General
Manager – Engineering. Javier is a professional Engineer with over
15 years’ experience in Electrical Engineering and Power
operations, and joins us from Rio Tinto, a ~US$101bn5 multinational
mining group, where he was the Power Operations and Nechako
Reservoir Superintendent for the Kitimat alumina smelter and hydro
power generation.
Canaccord Genuity 42nd Annual Growth
Conference
Iris Energy will be participating at the
upcoming Canaccord Genuity 42nd Annual Growth Conference in Boston,
Massachusetts between August 8-11, 2022.
In attendance will be Daniel Roberts (Co-Founder
and Co-CEO). Daniel will be presenting an overview of the Company
on Tuesday, August 9 at 1.00 p.m. Eastern Time. Interested parties
can register to view a webcast of the presentation using this
link:
https://wsw.com/webcast/canaccord76/register.aspx?conf=canaccord76&page=iren&url=https://wsw.com/webcast/canaccord76/iren/2457306
Daniel will also be available for one-on-one
meetings with investors during the conference. For more
information, please contact a Canaccord Genuity sales
representative.
Canal Flats update (0.8 EH/s, 30MW) –
BC, Canada
Canal Flats has been powered by 100% renewable
energy since inception.6
The project achieved average monthly operating
hashrate of 836 PH/s in July compared to 872 PH/s in June. The
slight reduction from June was due to the impact of summer
temperatures on our first generation pilot R&D facilities.
Canal Flats continued to exceed previously announced site capacity
of 0.7 EH/s.
In line with our focus on sustainability across
all aspects of our operations, the Canal Flats logistics team
recently installed a new green initiative with an expanded
polyethylene (EPE) foam densifier, which has the capacity to
recycle over two tonnes of EPE per month, derived from miner
packaging. The machine reduces the volume of EPE by 90:1, which
allows densified EPE ingots to be sold and recycled into a number
of new polyethylene products.
Mackenzie update (2.1 EH/s, 50MW initial
/ 80MW total) – BC, Canada
Mackenzie has been powered by 100% renewable
energy since inception.6
On August 8, 2022, the Company announced it had
energized the remainder of the first 1.5 EH/s (50MW) at Mackenzie,
marking delivery of phase two of the project. Both initial phases
have been commissioned ahead of schedule:
- Phase one: 0.3 EH/s
(9MW) – April 13, 2022 (original target end of Q2 2022)
- Phase two: 1.2 EH/s
(41MW) – August 5, 2022 (original target end of Q3 2022)
Construction activities at Mackenzie continue to
progress for phase three, with the expansion from 50MW to 80MW
still on track to be completed by the end of Q4 2022.
The initial 9MW at Mackenzie achieved average
monthly operating hashrate of 282 PH/s in July compared to 292 PH/s
in June. The slight reduction was in line with expectations and due
to the temporary power draw cap of 9MW and increased exhaust fan
utilization during the warmer weather, along with scheduled outages
associated with the site transitioning to the high voltage
transmission network in early August as part of energization of the
full 1.5 EH/s (50MW).
Upon completion of all three phases at
Mackenzie, 80MW of proprietary data centers are expected to power
~22,000 Bitmain S19j Pro and S19j miners (already under contract),
generating 2.1 EH/s of incremental hashrate.
Prince George update (1.4 EH/s, 50MW) –
BC, Canada
Building construction is substantially complete
on the first and second data center buildings (20MW and 10MW)
including all exhaust fans installed, and is close to complete for
the third data center building (20MW). Internal fit out of all
three data center buildings is underway.
Major equipment installation in the substation
has commenced and the underground portions of the on-site
distribution network are complete.
Prince George remains on track to be energized
by the end of next month and, upon completion, 50MW of proprietary
data centers are expected to power ~15,000 Bitmain S19j Pro and
S19j miners (already under contract), generating 1.4 EH/s of
incremental hashrate.
See Prince George construction progress video
here: https://www.youtube.com/watch?v=Xgh1kiyiws8
Childress update – Texas,
USA
As previously announced, the Company continues
to progress preparatory construction and procurement activities at
the 600MW Childress site to preserve the opportunity to scale once
market conditions improve.
All required construction permits are in place,
construction of the access road to the main development area and
site civil works are ongoing, and purchase orders have been placed
on key long-lead items, including the 345kV step-down transformer,
138kV step-down transformer and associated circuit breakers.
Potential development options are under
consideration, including with respect to the recently announced
additional 1.7 EH/s of contracted miners.
Community engagement
Applications for the Community Grants Program at
Mackenzie and Childress are now closed. Applications are currently
being reviewed, with grants to be made available in due course.
Other notable local community initiatives during
the month included sponsoring the 4th of July kids parade in
Childress and renewing our support for the Columbia Valley Rockies
Hockey Club for the 2022/2023 season.
Future development sites
Development works continued across additional
sites in Canada, the USA and Asia-Pacific, which have the potential
to support up to an additional >1GW of aggregate power capacity
capable of powering growth beyond the Company’s 795MW of announced
power capacity.
Operating and financial
results
Daily average operating hashrate chart is available at
https://www.globenewswire.com/NewsRoom/AttachmentNg/7a205561-9c59-46ea-b59c-ef683bbaac4f
Technical commentary
The Company’s average operating hashrate was
1,117 PH/s in July compared to 1,164 PH/s in June, with the
Company’s operating capacity increasing to over 2.3 EH/s following
the transition to the high voltage transmission network in early
August as part of energization of the remainder of the first 50MW
at Mackenzie. Power prices at Mackenzie are also expected to reduce
by approximately 19% as a result of moving from the distribution
feed to the transmission network.
The Company mined 154 Bitcoin during the month,
a 4% increase from 148 Bitcoin mined during June 2022, which was
primarily attributable to a decline in the average
difficulty-implied global hashrate during the period plus one extra
operating day in the month. The fall in the global hashrate
suggests higher cost miners may have dropped out of the global
Bitcoin network during the period, thereby allowing lower cost
miners (such as Iris Energy) to increase their share of the network
and Bitcoin mined.
The increase in electricity costs in July
compared to June was primarily due to one extra operating day in
the month.
Operating* |
May-22 |
Jun-22 |
Jul-22 |
Renewable energy usage (MW)7 |
37 |
36 |
36 |
Avg operating hashrate (PH/s) |
1,165 |
1,164 |
1,117 |
* Reflects actual recorded operating power usage and hashrate
(not nameplate). Note: nameplate capacity is higher than actual
operating power usage due to features of the Company’s proprietary
data center design which utilizes variable speed fans to reduce
power consumption during cooler months, as well as the Company
maintaining a buffer within its infrastructure capacity that can be
also directed to other site uses (e.g. in-house fabrication shop at
Canal Flats is currently operating as Iris Energy has the advantage
of saving time and costs by internally constructing certain
components for its expansion sites).
Financial (unaudited) |
May-22 |
Jun-22 |
Jul-22 |
Bitcoin mined* |
151 |
148 |
154 |
Mining revenue (US$’000) |
4,868 |
3,546 |
3,358 |
Electricity costs (US$’000) |
1,411 |
1,315 |
1,360** |
Revenue per Bitcoin (US$) |
32,264 |
23,925 |
21,823 |
Electricity costs per Bitcoin (US$) |
9,352 |
8,875 |
8,836 |
* Reflects Bitcoin mined post deduction of
mining pool fees (currently 0.5% x total Bitcoin mined).** The
increase in electricity costs (vs. June) was primarily due to one
extra operating day in the month.
Miner Shipping Schedule |
Hardware |
Units |
EH/s(incremental) |
EH/s(cumulative) |
Operating (July 2022) |
S19j Pro8 |
10,529 |
1.1 |
1.1 |
Inventory – pending deployment |
S19j Pro / S19j9 |
27,031 |
2.4 |
3.5 |
Inventory – in transit |
S19j |
1,119 |
0.1 |
3.7 |
Q3 2022 |
S19j Pro / S19j |
23,012 |
2.2 |
5.9 |
Q4 2022 |
S19j |
1,500 |
0.1 |
6.0 |
Total |
|
63,191 |
6.010 |
6.0 |
Site |
Capacity(MW) |
Capacity(EH/s) |
Timing |
Status |
Canal Flats (BC, Canada) |
30 |
0.8 |
Complete |
Operating |
Mackenzie (BC, Canada) |
50 |
1.5 |
Complete |
Operating |
30 |
0.6 |
Q4 2022 |
Under construction |
Prince George (BC, Canada) |
50 |
1.4 |
Q3 2022 |
Under construction |
Total (end of Q4 2022) |
160 |
4.3 |
|
|
About Iris Energy
Iris Energy is a sustainable Bitcoin mining
company that supports the decarbonization of energy markets and the
global Bitcoin network.
- Focus on low-cost
renewables: Iris Energy targets markets with low-cost, excess
and/or under-utilized renewable energy, and where the Company can
support local communities
- Long-term security
over infrastructure, land and power supply: Iris Energy builds,
owns and operates its electrical infrastructure and proprietary
data centers, providing long-term security and operational control
over its assets
- Seasoned management
team: Iris Energy’s team has an impressive track record of success
across energy, infrastructure, renewables, finance, digital assets
and data centers with cumulative experience in delivering >$25bn
in energy and infrastructure projects globally
Forward-Looking Statements
This press release includes “forward-looking
statements” within the meaning of the Private Securities Litigation
Reform Act of 1995. Forward-looking statements generally relate to
future events or Iris Energy’s future financial or operating
performance. For example, forward-looking statements include but
are not limited to the expected increase in the Company’s power
capacity and operating capacity, the Company’s business plan, the
Company’s capital raising plans, the Company’s anticipated capital
expenditures and additional borrowings, the impact of discussions
with Bitmain regarding the Company’s hardware purchase contract for
additional miners, and the expected schedule for hardware
deliveries and for commencing and/or expanding operations at the
Company’s sites. In some cases, you can identify forward-looking
statements by terminology such as “anticipate,” “believe,” “may,”
“can,” “should,” “could,” “might,” “plan,” “possible,” “project,”
“strive,” “budget,” “forecast,” “expect,” “intend,” “target”,
“will,” “estimate,” “predict,” “potential,” “continue,” “scheduled”
or the negatives of these terms or variations of them or similar
terminology, but the absence of these words does not mean that
statement is not forward-looking. Such forward-looking statements
are subject to risks, uncertainties, and other factors which could
cause actual results to differ materially from those expressed or
implied by such forward looking statements. In addition, any
statements or information that refer to expectations, beliefs,
plans, projections, objectives, performance or other
characterizations of future events or circumstances, including any
underlying assumptions, are forward-looking.
These forward-looking statements are based on
management’s current expectations and beliefs. These statements are
neither promises nor guarantees, but involve known and unknown
risks, uncertainties and other important factors that may cause
Iris Energy’s actual results, performance or achievements to be
materially different from any future results, performance or
achievements expressed or implied by the forward-looking
statements, including, but not limited to: Iris Energy’s limited
operating history with operating losses; electricity outage,
limitation of electricity supply or increase in electricity costs;
long term outage or limitation of the internet connection at Iris
Energy’s sites; any critical failure of key electrical or data
center equipment; serial defects or underperformance with respect
to Iris Energy’s equipment; failure of suppliers to perform under
the relevant supply contracts for equipment that has already been
procured which may delay Iris Energy’s expansion plans; supply
chain and logistics issues for Iris Energy or Iris Energy’s
suppliers; cancellation or withdrawal of required operating and
other permits and licenses; customary risks in developing
greenfield infrastructure projects; Iris Energy’s evolving business
model and strategy; Iris Energy’s ability to successfully manage
its growth; Iris Energy’s ability to raise additional financing
(whether because of the conditions of the markets, Iris Energy’s
financial condition or otherwise) on a timely basis, or at all,
which could adversely impact the Company’s ability to meet its
capital commitments (including payments due under its hardware
purchase contracts with Bitmain) and the Company’s growth plans;
Iris Energy’s failure to make certain payments due under any one of
its hardware purchase contracts with Bitmain on a timely basis
could result in liquidated damages, claims for specific performance
or other claims against Iris Energy, any of which could result in a
loss of all or a portion of any prepayments or deposits made under
the relevant contract or other liabilities in respect of the
relevant contract, and could also result in Iris Energy not
receiving certain discounts under the relevant contract or
receiving the relevant hardware at all, any of which could
adversely impact its business, operating expansion plans, financial
condition, cash flows and results of operations; the terms of any
additional financing, which could be less favorable or require Iris
Energy to comply with more onerous covenants or restrictions, any
of which could restrict its business operations and adversely
impact its financial condition, cash flows and results of
operations; competition; Bitcoin prices, which could adversely
impact its financial condition, cash flows and results of
operations, as well as its ability to raise additional financing;
risks related to health pandemics including those of COVID-19;
changes in regulation of digital assets; and other important
factors discussed under the caption “Risk Factors” in Iris Energy’s
final prospectus filed pursuant to Rule 424(b)(4) with the SEC on
November 18, 2021, as such factors may be updated from time to time
in its other filings with the SEC, accessible on the SEC’s website
at www.sec.gov and the Investor Relations section of Iris Energy’s
website at https://investors.irisenergy.co.
These and other important factors could cause
actual results to differ materially from those indicated by the
forward-looking statements made in this press release. Any
forward-looking statement that Iris Energy makes in this press
release speaks only as of the date of such statement. Except as
required by law, Iris Energy disclaims any obligation to update or
revise, or to publicly announce any update or revision to, any of
the forward-looking statements, whether as a result of new
information, future events or otherwise.
Contacts
MediaJon SnowballDomestique+61 477 946 068
InvestorsBom ShinIris Energy+61 411 376
332bom.shin@irisenergy.co
To keep updated on Iris Energy’s news releases and SEC filings,
please subscribe to email alerts at
https://investors.irisenergy.co/ir-resources/email-alerts.
________________________________1 All timing references in this
investor update are to calendar quarters and calendar years, unless
otherwise specified.2 The preliminary financial information for the
month of July 2022 included in this investor update is not subject
to the same closing procedures as our unaudited quarterly financial
results and has not been reviewed by our independent registered
public accounting firm. The preliminary financial information
included in this investor update does not represent a comprehensive
statement of our financial results or financial position, and
should not be viewed as a substitute for unaudited financial
statements prepared in accordance with International Financial
Reporting Standards. Accordingly, you should not place undue
reliance on the preliminary financial information included in this
investor update.3 Reflects Bitcoin mined post deduction of mining
pool fees (currently 0.5% x total Bitcoin mined).4 The timing and
volume of any additional future deliveries (i.e. beyond the 1.7
EH/s scheduled for shipment in August 2022) under the separate
$400m hardware purchase contract for miners are subject to ongoing
discussions with Bitmain. The Company has not made all recent
payments under that contract and does not currently expect to make
upcoming payments in respect of any such additional future
deliveries under that contract. The Company can make no assurances
as to the outcome of these discussions (including any impact on the
Company’s expansion plans or payments made under that contract).5
Approximate market capitalizations as at August 5, 2022. Source:
Bloomberg.6 Currently 98% directly from renewable energy sources;
2% from purchase of RECs.7 Comprises actual power usage for Canal
Flats and estimated power usage for Mackenzie.8 Includes mix of
lower efficiency hardware, which is estimated to represent less
than 1% of the operating 1.1 EH/s.9 Includes mix of lower
efficiency hardware, which is estimated to represent less than 6%
of miners pending deployment.10 The Company has made $83m of
payments in respect of contracted miners above the initial 6.0
EH/s, which are subject to ongoing discussions with Bitmain. Please
see footnote 4 for more details.
Photos accompanying this announcement are available at
https://www.globenewswire.com/NewsRoom/AttachmentNg/f2c942ee-ad6b-4aaf-b194-246830dc4585
https://www.globenewswire.com/NewsRoom/AttachmentNg/abc79b1c-4e9c-4bcd-8186-b506c00e8185
https://www.globenewswire.com/NewsRoom/AttachmentNg/3647ba2c-6bd3-48d9-9683-3fdbbd0544e4
https://www.globenewswire.com/NewsRoom/AttachmentNg/fa0a3a4b-b83c-4a56-b973-17ea7e4fb2fe
https://www.globenewswire.com/NewsRoom/AttachmentNg/9d299fde-5643-4e1b-bedc-67abb7c53b68
https://www.globenewswire.com/NewsRoom/AttachmentNg/1dd2625c-ee69-42a6-9454-411d9391fcf7
https://www.globenewswire.com/NewsRoom/AttachmentNg/d501da45-a289-4c06-a140-6bcf66e2b8b6
Iris Energy (NASDAQ:IREN)
Gráfico Histórico do Ativo
De Mai 2023 até Jun 2023
Iris Energy (NASDAQ:IREN)
Gráfico Histórico do Ativo
De Jun 2022 até Jun 2023