Iris Energy Limited (NASDAQ: IREN) (“Iris Energy” or “the
Company”), a leading owner and operator of institutional-grade,
highly efficient proprietary Bitcoin mining data centers powered by
100% renewable energy, today published a monthly investor update
for August 2022, containing its results from operations as well as
construction and development updates.
Key Highlights1
Key metrics |
Aug-22 |
Average operating hashrate (PH/s) |
2,204 |
Bitcoin mined2 |
301 |
Mining revenue (US$'000) |
6,629 |
Electricity costs (US$'000) |
2,436 |
Revenue per Bitcoin (US$) |
22,027 |
Electricity costs per Bitcoin (US$) |
8,094 |
- Corporate:
- Prince George
(50MW) on track for energization in September 2022, increasing
total expected Company operating capacity to 3.7 EH/s
- Company operating
capacity guidance increased from 4.3 EH/s to 4.7 EH/s by the end of
Q4 2022
- Company to publish
its financial results for the full year ended June 30, 2022 on
Tuesday, September 13, 2022 Eastern Time (conference call to be
hosted at 5:00 p.m. USA Eastern Time)
- Operations:
- Average operating
hashrate of 2,204 PH/s (+97% vs. July)
- Monthly operating
revenue of US$6.6 million (+97% vs. July)
- 301 Bitcoin mined
(+96% vs. July)
- Construction:
- Mackenzie (2.5
EH/s, 80MW – BC, Canada)
- Construction
activities continue to progress for expansion from 50MW to 80MW and
remains on track to be completed by the end of Q4 2022
- Expected site
operating capacity increased from 2.1 EH/s to 2.5 EH/s by the end
of Q4 2022
- Prince George (1.4
EH/s, 50MW – BC, Canada)
- Commissioning
activities underway, with major equipment installation in the
substation close to complete
- Construction of all
three data center buildings complete
- Internal fit out
for the first and third data center buildings (20MW each) complete
and well progressed for the second data center building (10MW)
- Construction of the
high voltage connection to the BC Hydro transmission network
complete
- Childress (1.3
EH/s, 40MW – Texas, USA)
- An initial 40MW
development is planned at the 600MW site
- Earthworks have
commenced for the substation area, the first data center building
(20MW) area and internal road network
Corporate update
Updated operating guidance
As previously announced on August 1, 2022, the
Company reached agreement with Bitmain to ship an additional 1.7
EH/s of S19j Pro miners, increasing expected operating capacity
from 4.3 EH/s to 6.0 EH/s. $46.7 million of the previous $130
million of payments made to Bitmain, along with an additional
payment of $5.9 million of cash on hand, were utilized as payment
for the additional 1.7 EH/s of miners.3
0.4 EH/s of the additional miners are expected
to be deployed at Mackenzie, increasing the Company’s expected
total operating capacity from 4.3 EH/s to 4.7 EH/s by the end of Q4
2022.
An initial 40MW is planned at Childress for
deployment of the remaining 1.3 EH/s of additional miners, to reach
total expected Company operating capacity of 6.0 EH/s.
FY22 financial results
Iris Energy will publish its financial results
for the full year ended June 30, 2022 on Tuesday, September 13,
2022 Eastern Time and host a conference call to discuss its FY22
financial results including time for Q&A beginning at 5:00 p.m.
USA Eastern Time. The webcast will be recorded, and the replay will
accessible shortly after the event at
https://investors.irisenergy.co/events-and-presentations.
Webcast and Conference Details |
Date: |
Tuesday, September 13, 2022 |
Time: |
5:00 p.m. USA Eastern Time (2:00 p.m. Pacific Time or 7:00 a.m.
Australian Eastern Standard Time) |
|
Participant |
Registration Link |
|
Live Webcast |
Use this link |
|
Phone Dial-In with Live Q&A |
Use this link |
Please note, participants joining the conference
call via the phone dial-in option will receive their dial-in
number, passcode and PIN following registration using the link
above. It would be appreciated if all callers could dial in
approximately 5 minutes prior to the scheduled start time.
There will be a Q&A session after the
Company delivers its FY22 financial results. Those dialling in via
phone can elect to ask a question via the moderator. Participants
on the live webcast have the ability to pre-submit a question upon
registering to join the webcast or can submit a question during the
live webcast.
Canal Flats update (0.8 EH/s, 30MW) –
BC, Canada
Canal Flats has been powered by 100% renewable
energy since inception.4
The project achieved average monthly operating
hashrate of 825 PH/s in August compared to 836 PH/s last month. The
slight reduction was due to the impact of summer temperatures on
our first-generation pilot R&D facilities. Canal Flats
continued to exceed previously announced site capacity of 0.7
EH/s.
Mackenzie update (2.5 EH/s, 50MW initial
/ 80MW total) – BC, Canada
Mackenzie has been powered by 100% renewable
energy since inception.4
The project achieved average monthly operating
hashrate of 1,380 PH/s in August compared to 282 PH/s in July,
driven by energization of the remainder of the first 1.5 EH/s
(50MW) ahead of schedule in early August.
Construction activities at Mackenzie continue to
progress for the expansion from 50MW to 80MW, utilizing the
remaining 10MW of the third data center (20MW) and a fourth data
center building (20MW) for which foundation works have commenced,
and remains on track for completion by the end of Q4 2022.
Upon completion of the final phase at Mackenzie,
80MW of proprietary data centers are expected to power up to
~26,000 Bitmain S19j Pro and S19j miners5 (already under contract),
generating 2.5 EH/s of operating hashrate.
Prince George update (1.4 EH/s, 50MW) –
BC, Canada
Commissioning activities are now underway at
Prince George, with major equipment installation in the substation
close to complete.
Construction of all three data center buildings,
including internal fit out for the first and third data center
buildings (20MW each) was completed during the month, and internal
fit out for the second data center building (10MW) is well
progressed.
The overhead and underground portions of the
on-site distribution network are now complete and construction of
the high voltage connection to the BC Hydro transmission network
was also completed during the month.
Prince George remains on track to be energized
by the end of September and, upon completion, 50MW of proprietary
data centers are expected to power ~15,000 Bitmain S19j Pro and
S19j miners (already under contract), generating 1.4 EH/s of
operating hashrate.
See construction progress video for our BC sites
here: https://www.youtube.com/watch?v=55Qd5rE9B3Q
Childress update (1.3 EH/s, 40MW) –
Texas, USA
The Company is planning the build out of an
initial 40MW development at the 600MW Childress site.
All required construction permits are in place
and earthworks have commenced for the substation area, the first
data center building (20MW) area and internal road network.
Furthermore, purchase orders are in place for key high and low
voltage electrical equipment, building structures and data center
equipment, and key construction contractors have been selected.
Community engagement
Iris Energy hosted a Community Grants Luncheon
in Mackenzie to congratulate the 2022 grant recipients in August. A
total of C$67,000 was awarded to recipients, including the
Mackenzie Community Arts Centre, the Mackenzie Community Garden,
the Mackenzie and Area Community Radio Society, the Mackenzie
Public Library, the College of New Caledonia (Mackenzie Campus),
the Mackenzie Outdoor Route and Trail Association, and the Society
of St. Vincent de Paul.
Iris Energy recently became a Corporate Member
of the Prince George Chamber of Commerce, and also sponsored the
annual Flats Fest music festival in Canal Flats.
The Childress Community Grants Program, launched
in June 2022, has received 22 grant applications (from a diverse
range of applicants), which are currently under review. The grant
recipients will be announced in the coming months.
Future development sites
Development works continued across additional
sites in Canada, the USA and Asia-Pacific, which have the potential
to support up to an additional >1GW of aggregate power capacity
capable of powering growth beyond the Company’s 795MW of announced
power capacity.
Operating and financial
results
Daily average operating hashrate chart is available
at https://www.globenewswire.com/NewsRoom/AttachmentNg/53c4fb69-7e48-4def-924a-826fafd9bdea
Technical commentary
The Company’s average operating hashrate was
2,204 PH/s in August compared to 1,117 PH/s in July, driven by
energization of the remainder of the first 1.5 EH/s (50MW) ahead of
schedule at Mackenzie, with the Company’s total operating capacity
exceeding 2.3 EH/s from August 6.
The corresponding increase in Bitcoin mined (301
in August vs. 154 in July) and electricity costs ($2.4 million in
August vs. $1.4 million in July) were also primarily attributable
to the energization of the remainder of the first 50MW at Mackenzie
during the month.
We note that electricity costs did not increase
proportionally with the increase in average operating hashrate as
the power price per kWh at Mackenzie reduced by approximately 18%
as a result of moving from the distribution feed to the
transmission network, with the Company’s overall electricity cost
per Bitcoin mined falling from approximately $8.8k to $8.1k.
Operating* |
Jun-22 |
Jul-22 |
Aug-22 |
Renewable energy usage (MW)6 |
36 |
36 |
69 |
Avg operating hashrate (PH/s) |
1,164 |
1,117 |
2,204 |
* Reflects actual recorded operating power usage and hashrate
(not nameplate). Note: nameplate capacity is higher than actual
operating power usage due to features of the Company’s proprietary
data center design which utilizes variable speed fans to reduce
power consumption during cooler months, as well as the Company
maintaining a buffer within its infrastructure capacity that can be
also directed to other site uses (e.g. in-house fabrication shop at
Canal Flats is currently operating as Iris Energy has the advantage
of saving time and costs by internally constructing certain
components for its expansion sites).
Financial (unaudited) |
Jun-22 |
Jul-22 |
Aug-22 |
Bitcoin mined* |
148 |
154 |
301 |
Mining revenue (US$’000) |
3,546 |
3,358 |
6,629 |
Electricity costs (US$’000) |
1,315 |
1,360** |
2,436 |
Revenue per Bitcoin (US$) |
23,925 |
21,823 |
22,027 |
Electricity costs per Bitcoin (US$) |
8,875 |
8,836 |
8,094 |
* Reflects Bitcoin mined post deduction of
mining pool fees (currently 0.5% x total Bitcoin mined).** The
increase in electricity costs (vs. June) was primarily due to one
extra operating day in the month.
Miner Shipping Schedule |
Hardware |
Units |
EH/s (incremental) |
EH/s(cumulative) |
Operating (August 2022) |
S19j Pro / S19j7 |
23,831 |
2.2 |
2.2 |
Inventory – pending deployment |
S19j Pro / S19j8 |
16,956 |
1.6 |
3.8 |
Inventory – in transit |
S19j Pro / S19j |
3,608 |
0.4 |
4.2 |
Q3 2022 |
S19j Pro / S19j |
17,296 |
1.7 |
5.9 |
Q4 2022 |
S19j |
1,500 |
0.1 |
6.0 |
Total |
|
63,191 |
6.0 |
6.0 |
Site |
Capacity (MW) |
Capacity (EH/s) |
Timing |
Status |
Canal Flats (BC, Canada) |
30 |
0.8 |
Complete |
Operating |
Mackenzie (BC, Canada) |
50 |
1.5 |
Complete |
Operating |
30 |
1.09 |
Q4 2022 |
Under construction |
Prince George (BC, Canada) |
50 |
1.4 |
Q3 2022 |
Commissioning |
Total (end of Q4 2022) |
160 |
4.7 |
|
|
Childress (Texas, US) |
40 |
1.3 |
2023 |
Under construction |
Total (2023) |
200 |
6.0 |
|
|
About Iris Energy
Iris Energy is a sustainable Bitcoin mining
company that supports the decarbonization of energy markets and the
global Bitcoin network.
- 100% renewables:
Iris Energy targets markets with low-cost, under-utilized renewable
energy, and where the Company can support local communities
- Long-term security
over infrastructure, land and power supply: Iris Energy builds,
owns and operates its electrical infrastructure and proprietary
data centers, providing long-term security and operational control
over its assets
- Seasoned management
team: Iris Energy’s team has an impressive track record of success
across energy, infrastructure, renewables, finance, digital assets
and data centers with cumulative experience in delivering >$25bn
in energy and infrastructure projects globally
Forward-Looking Statements
This press release includes “forward-looking
statements” within the meaning of the Private Securities Litigation
Reform Act of 1995. Forward-looking statements generally relate to
future events or Iris Energy’s future financial or operating
performance. For example, forward-looking statements include but
are not limited to the expected increase in the Company’s power
capacity and operating capacity, the Company’s business plan, the
Company’s capital raising plans, the Company’s anticipated capital
expenditures and additional borrowings, the impact of discussions
with Bitmain regarding the Company’s hardware purchase contract for
additional miners, and the expected schedule for hardware
deliveries and for commencing and/or expanding operations at the
Company’s sites. In some cases, you can identify forward-looking
statements by terminology such as “anticipate,” “believe,” “may,”
“can,” “should,” “could,” “might,” “plan,” “possible,” “project,”
“strive,” “budget,” “forecast,” “expect,” “intend,” “target”,
“will,” “estimate,” “predict,” “potential,” “continue,” “scheduled”
or the negatives of these terms or variations of them or similar
terminology, but the absence of these words does not mean that
statement is not forward-looking. Such forward-looking statements
are subject to risks, uncertainties, and other factors which could
cause actual results to differ materially from those expressed or
implied by such forward looking statements. In addition, any
statements or information that refer to expectations, beliefs,
plans, projections, objectives, performance or other
characterizations of future events or circumstances, including any
underlying assumptions, are forward-looking.
These forward-looking statements are based on
management’s current expectations and beliefs. These statements are
neither promises nor guarantees, but involve known and unknown
risks, uncertainties and other important factors that may cause
Iris Energy’s actual results, performance or achievements to be
materially different from any future results, performance or
achievements expressed or implied by the forward-looking
statements, including, but not limited to: Iris Energy’s limited
operating history with operating losses; electricity outage,
limitation of electricity supply or increase in electricity costs;
long term outage or limitation of the internet connection at Iris
Energy’s sites; any critical failure of key electrical or data
center equipment; serial defects or underperformance with respect
to Iris Energy’s equipment; failure of suppliers to perform under
the relevant supply contracts for equipment that has already been
procured which may delay Iris Energy’s expansion plans; supply
chain and logistics issues for Iris Energy or Iris Energy’s
suppliers; cancellation or withdrawal of required operating and
other permits and licenses; customary risks in developing
greenfield infrastructure projects; Iris Energy’s evolving business
model and strategy; Iris Energy’s ability to successfully manage
its growth; Iris Energy’s ability to raise additional financing
(whether because of the conditions of the markets, Iris Energy’s
financial condition or otherwise) on a timely basis, or at all,
which could adversely impact the Company’s ability to meet its
capital commitments (including payments due under its hardware
purchase contracts with Bitmain) and the Company’s growth plans;
Iris Energy’s failure to make certain payments due under any one of
its hardware purchase contracts with Bitmain on a timely basis
could result in liquidated damages, claims for specific performance
or other claims against Iris Energy, any of which could result in a
loss of all or a portion of any prepayments or deposits made under
the relevant contract or other liabilities in respect of the
relevant contract, and could also result in Iris Energy not
receiving certain discounts under the relevant contract or
receiving the relevant hardware at all, any of which could
adversely impact its business, operating expansion plans, financial
condition, cash flows and results of operations; the terms of any
additional financing, which could be less favorable or require Iris
Energy to comply with more onerous covenants or restrictions, any
of which could restrict its business operations and adversely
impact its financial condition, cash flows and results of
operations; competition; Bitcoin prices, which could adversely
impact its financial condition, cash flows and results of
operations, as well as its ability to raise additional financing;
risks related to health pandemics including those of COVID-19;
changes in regulation of digital assets; and other important
factors discussed under the caption “Risk Factors” in Iris Energy’s
final prospectus filed pursuant to Rule 424(b)(4) with the SEC on
November 18, 2021, as such factors may be updated from time to time
in its other filings with the SEC, accessible on the SEC’s website
at www.sec.gov and the Investor Relations section of Iris Energy’s
website at https://investors.irisenergy.co.
These and other important factors could cause
actual results to differ materially from those indicated by the
forward-looking statements made in this press release. Any
forward-looking statement that Iris Energy makes in this press
release speaks only as of the date of such statement. Except as
required by law, Iris Energy disclaims any obligation to update or
revise, or to publicly announce any update or revision to, any of
the forward-looking statements, whether as a result of new
information, future events or otherwise.
Preliminary Financial
Information
The preliminary financial information for the
month of August 2022 included in this investor update is not
subject to the same closing procedures as our unaudited quarterly
financial results and has not been reviewed by our independent
registered public accounting firm. The preliminary financial
information included in this investor update does not represent a
comprehensive statement of our financial results or financial
position, and should not be viewed as a substitute for unaudited
financial statements prepared in accordance with International
Financial Reporting Standards. Accordingly, you should not place
undue reliance on the preliminary financial information included in
this investor update.
ContactsMediaJon
SnowballDomestique+61 477 946 068
InvestorsBom ShinIris Energy+61 411 376
332bom.shin@irisenergy.co
To keep updated on Iris Energy’s news releases and SEC filings,
please subscribe to email alerts at
https://investors.irisenergy.co/ir-resources/email-alerts.
_____________________________
1 All timing references in this investor update are to calendar
quarters and calendar years, unless otherwise specified.2 Reflects
Bitcoin mined post deduction of mining pool fees (currently 0.5% x
total Bitcoin mined).3 Utilization of the remaining $83.3 million
of payments in respect of additional contracted miners above 6.0
EH/s continue to be subject to ongoing discussions with Bitmain.
The Company has not made all recent scheduled payments under the
separate $400 million hardware purchase contract and does not
currently expect to make upcoming scheduled payments in respect of
future deliveries. The timing and volume of any additional future
deliveries under that contract (including utilization of the
remaining $83.3 million of payments) is subject to ongoing
discussions with Bitmain. The Company can make no assurances as to
the outcome of these discussions, including the impact on timing of
any future deliveries or payments made under that contract.4
Currently approximately 97% directly from renewable energy sources;
approximately 3% from purchase of RECs.5 May potentially be
supplemented with a small portion of non S19j Pro and S19j miners
as part of miner fleet optimization across our sites following the
agreement with Bitmain in August to ship the additional 1.7 EH/s of
miners.6 Comprises actual power usage for Canal Flats and estimated
power usage for Mackenzie.7 Includes mix of lower efficiency
hardware, which is estimated to represent less than 1% of the
operating 2.2 EH/s.8 Includes mix of lower efficiency hardware,
which is estimated to represent less than 8% of miners pending
deployment.9 Operating capacity with respect to the final 30MW
phase at Mackenzie is expected to increase from 0.6 EH/s to 1.0
EH/s to support 0.4 EH/s of the recently announced 1.7 EH/s of
additional Bitmain S19j Pro miners.
Photos accompanying this announcement are available at:
https://www.globenewswire.com/NewsRoom/AttachmentNg/4b3c0900-988f-46f2-8084-d3405642dded
https://www.globenewswire.com/NewsRoom/AttachmentNg/110100a7-9fd6-4789-9aae-dc389a729557
https://www.globenewswire.com/NewsRoom/AttachmentNg/072113b0-384b-4cd8-b33c-3cbc593a2bdc
https://www.globenewswire.com/NewsRoom/AttachmentNg/3cf34e65-f13b-41f9-87ed-f664c446ef17
https://www.globenewswire.com/NewsRoom/AttachmentNg/c86d66fe-ef1e-4268-9dea-8e4cf9380714
https://www.globenewswire.com/NewsRoom/AttachmentNg/a8ae5fcd-83cd-4a05-98ba-ed67ca1433d8
Iris Energy (NASDAQ:IREN)
Gráfico Histórico do Ativo
De Mai 2023 até Jun 2023
Iris Energy (NASDAQ:IREN)
Gráfico Histórico do Ativo
De Jun 2022 até Jun 2023