Iris Energy Limited (NASDAQ: IREN) (“Iris Energy” or “the
Company”), a leading owner and operator of institutional-grade,
highly efficient proprietary Bitcoin mining data centers powered by
100% renewable energy, today published a monthly investor update
for September 2022, containing its results from operations as
well as construction and development updates.
Key Highlights1
Key metrics |
Sep-22 |
Average operating hashrate (PH/s) |
2,729 |
Bitcoin mined2 |
325 |
Mining revenue (US$’000) |
6,224 |
Electricity costs (US$’000) |
2,829 |
Revenue per Bitcoin (US$) |
19,124 |
Electricity costs per Bitcoin (US$) |
8,691 |
- Corporate:
- Company’s third
operating site, Prince George (50MW), was energized on schedule,
increasing total Company operating capacity by >60% to exceed
3.7 EH/s
- Mackenzie expansion
from 50MW to 80MW remains on track to be energized by end of Q4
2022, increasing expected near-term Company operating capacity to
4.7 EH/s
- Initial 40MW
planned at Childress to reach 6.0 EH/s
- Reported record
full year FY22 results
- Operations:
- Average operating
hashrate of 2,729 PH/s (+24% vs. August)
- Monthly operating
revenue of US$6.2 million (-6% vs. August)
- 325 Bitcoin mined
(+8% vs. August)
- Construction:
- Mackenzie (2.5
EH/s, 80MW – BC, Canada)
- Expansion from 50MW
to 80MW on track for energization by the end Q4 2022
- Internal fit-out of
the remaining 10MW of the third data center building
progressing
- Foundations
complete and erection of structural steel has commenced for the
fourth data center building (20MW)
- Childress (1.3
EH/s, 40MW – Texas, USA)
- An initial 40MW
development is planned at the 600MW site
- Earthworks
continued and foundation preparation commenced for the substation
area and first data center building (20MW)
- Key civil, data
center building and substation contractors mobilized on site
Corporate update
On September 23, the Company entered into an
agreement with B. Riley Principal Capital II, LLC (“B. Riley”)
pursuant to which the Company has the option, but not the
obligation, to sell up to US$100 million of ordinary shares to B.
Riley over the next two years.
The Company continues to monitor funding markets
and advance prospective capital opportunities. In parallel, the
Company is also assessing various growth initiatives such as
ongoing organic expansion as well as potential M&A.
Record full year FY22 results
On September 13, Iris Energy reported record
financial results for the full year ended June 30, 2022 and
provided a general business update. The earnings webcast and the
Company’s latest investor presentation are available on the
Company’s website here:
https://investors.irisenergy.co/events-and-presentations.
Canal Flats update (0.8 EH/s, 30MW) –
BC, Canada
Canal Flats has been powered by 100% renewable
energy since inception.3
The project increased average monthly operating
hashrate to 848 PH/s in September compared to 825 PH/s last month.
Canal Flats continued to exceed previously announced site capacity
of 0.7 EH/s.
Mackenzie update (2.5 EH/s, 50MW
operating / 30MW under construction) – BC, Canada
Mackenzie has been powered by 100% renewable
energy since inception.3
The project achieved average monthly operating
hashrate of 1,579 PH/s in September compared to 1,380 PH/s in
August, reflecting a full month of operations at 50MW.
Construction activities at Mackenzie continue to
progress for the expansion from 50MW to 80MW, which will utilize
the remaining 10MW of the third data center building (20MW) and a
fourth data center building (20MW). Internal fit-out of the
remaining 10MW of the third data center building is progressing,
while the foundations are complete for the fourth data center
building and erection of structural steel has commenced. The
additional 30MW remains on track for completion by the end of Q4
2022.
Upon completion of the final phase at Mackenzie,
80MW of proprietary data centers are expected to power up to
~26,000 Bitmain S19j Pro and S19j miners4 (already under contract),
generating 2.5 EH/s of operating hashrate.
Prince George update (1.4 EH/s, 50MW) –
BC, Canada
Prince George has been powered by 100% renewable
energy since inception.3
On September 27, the Company announced the full
energization of 1.4 EH/s (50MW) at Prince George. The project was
delivered on schedule and has been performing consistently since
completion.
Childress update (1.3 EH/s, 40MW) –
Texas, USA
The Company is planning the build out of an
initial 40MW development at the 600MW Childress site.
All required construction permits are in place
and earthworks continued during the month for the substation area,
the first data center building (20MW) and internal road network.
Substation foundation preparations are also underway in readiness
for scheduled transformer deliveries. Furthermore, purchase orders
continue to be placed for key high and low voltage electrical
equipment, building structures and data center equipment.
Key civil, data center building and substation
contractors have mobilized to site and are being managed by a core
group of Iris Energy employees based in Childress.
Community engagement
Iris Energy was one of the primary sponsors of
the Mackenzie Senior’s Week celebrating seniors who have been
recognized for their contributions and the impact they have had on
the community. They were recognized through an appreciation lunch
and an upcoming wine and cheese event.
A dinner was held in Childress to celebrate the
successful recipients under the Company’s Childress Community
Grants Program for 2022. Over US$85,000 is being awarded to 12
recipients including for the provision of safety equipment for the
Little League, jackets for the disadvantaged, shade at a local
playground, and chemistry class labs at a local high school. Iris
Energy also joined the Childress Rotary Club (another Childress
Community Grants recipient) to serve the community and partner with
other local businesses.
Future development sites
Development works continued across additional
sites in Canada, the USA and Asia-Pacific, which have the potential
to support up to an additional >1GW of aggregate power capacity
capable of powering growth beyond the Company’s 795MW of announced
power capacity.
Operating and financial results
Daily average operating hashrate chart is available
at https://www.globenewswire.com/NewsRoom/AttachmentNg/7aa15a2a-db6c-4cf4-871d-cfcbb414ea8b
Technical commentary
The Company’s average operating hashrate was
2,729 PH/s in September (compared to 2,204 PH/s in August), driven
by the energization of 50MW at Prince George, with total Company
operating capacity exceeding 3.7 EH/s from September 27 onwards.
The corresponding increase in Bitcoin mined (325 vs. 301 in August)
and electricity costs ($2.9 million vs. $2.4 million in August)
were also primarily attributable to full energization of Prince
George during the month.
The increase in Bitcoin mined during the month
(325 vs. 301 in August) was not proportional to the growth in the
Company’s average operating hashrate due to an increase in the
average difficulty-implied global hashrate during the period, which
was also the primary driver behind the increase in the Company’s
electricity costs per Bitcoin mined during the month.
Operating* |
Jul-22 |
Aug-22 |
Sep-22 |
Renewable energy usage (MW)5 |
36 |
69 |
85 |
Avg operating hashrate (PH/s) |
1,117 |
2,204 |
2,729 |
* Reflects actual recorded operating power usage and hashrate
(not nameplate). Note: nameplate capacity is higher than actual
operating power usage due to features of the Company’s proprietary
data center design which utilizes variable speed fans to reduce
power consumption during cooler months, as well as the Company
maintaining a buffer within its infrastructure capacity that can be
also directed to other site uses (e.g. in-house fabrication shop at
Canal Flats is currently operating as Iris Energy has the advantage
of saving time and costs by internally constructing certain
components for its expansion sites).
Financial (unaudited) |
Jul-22 |
Aug-22 |
Sep-22 |
Bitcoin mined* |
154 |
301 |
325 |
Mining revenue (US$’000) |
3,358 |
6,629 |
6,224 |
Electricity costs (US$’000) |
1,360 |
2,436 |
2,829 |
Revenue per Bitcoin (US$) |
21,823 |
22,027 |
19,124 |
Electricity costs per Bitcoin (US$) |
8,836 |
8,094 |
8,691 |
* Reflects Bitcoin mined post deduction of
mining pool fees as applicable.
Miner Shipping Schedule |
Hardware |
Units |
EH/s (incremental) |
EH/s(cumulative) |
Operating (September 2022) |
S19j Pro / S19j 6 |
27,244 |
2.7 |
2.7 |
Inventory – pending deployment |
S19j Pro / S19j 7 |
18,248 |
1.6 |
4.3 |
Inventory – in transit |
S19j Pro / S19j |
14,754 |
1.4 |
5.7 |
Q4 2022 |
S19j |
3,000 |
0.3 |
6.0 |
Total |
|
63,246 |
6.0 |
6.0 |
Site |
Capacity (MW) |
Capacity (EH/s) |
Timing |
Status |
Canal Flats (BC, Canada) |
30 |
0.8 |
Complete |
Operating |
Mackenzie (BC, Canada) |
50 |
1.5 |
Complete |
Operating |
30 |
1.0 |
Q4 2022 |
Under construction |
Prince George (BC, Canada) |
50 |
1.4 |
Complete |
Operating |
Total (end of Q4 2022) |
160 |
4.7 |
|
|
Childress (Texas, US) |
40 |
1.3 |
2023 |
Under construction |
Total (2023) |
200 |
6.0 |
|
|
About Iris Energy
Iris Energy is a sustainable Bitcoin mining
company that supports the decarbonization of energy markets and the
global Bitcoin network.
- 100% renewables:
Iris Energy targets markets with low-cost, under-utilized renewable
energy, and where the Company can support local communities
- Long-term security
over infrastructure, land and power supply: Iris Energy builds,
owns and operates its electrical infrastructure and proprietary
data centers, providing long-term security and operational control
over its assets
- Seasoned management
team: Iris Energy’s team has an impressive track record of success
across energy, infrastructure, renewables, finance, digital assets
and data centers with cumulative experience in delivering >$25bn
in energy and infrastructure projects globally
Forward-Looking Statements
This press release includes “forward-looking
statements” within the meaning of the Private Securities Litigation
Reform Act of 1995. Forward-looking statements generally relate to
future events or Iris Energy’s future financial or operating
performance. For example, forward-looking statements include but
are not limited to the expected increase in the Company’s power
capacity and operating capacity, the Company’s business plan, the
Company’s capital raising plans, the Company’s anticipated capital
expenditures and additional borrowings, the impact of discussions
with Bitmain regarding the Company’s hardware purchase contract for
additional miners, and the expected schedule for hardware
deliveries and for commencing and/or expanding operations at the
Company’s sites. In some cases, you can identify forward-looking
statements by terminology such as “anticipate,” “believe,” “may,”
“can,” “should,” “could,” “might,” “plan,” “possible,” “project,”
“strive,” “budget,” “forecast,” “expect,” “intend,” “target”,
“will,” “estimate,” “predict,” “potential,” “continue,” “scheduled”
or the negatives of these terms or variations of them or similar
terminology, but the absence of these words does not mean that
statement is not forward-looking. Such forward-looking statements
are subject to risks, uncertainties, and other factors which could
cause actual results to differ materially from those expressed or
implied by such forward looking statements. In addition, any
statements or information that refer to expectations, beliefs,
plans, projections, objectives, performance or other
characterizations of future events or circumstances, including any
underlying assumptions, are forward-looking.
These forward-looking statements are based on
management’s current expectations and beliefs. These statements are
neither promises nor guarantees, but involve known and unknown
risks, uncertainties and other important factors that may cause
Iris Energy’s actual results, performance or achievements to be
materially different from any future results, performance or
achievements expressed or implied by the forward-looking
statements, including, but not limited to: Iris Energy’s limited
operating history with operating losses; electricity outage,
limitation of electricity supply or increase in electricity costs;
long term outage or limitation of the internet connection at Iris
Energy’s sites; any critical failure of key electrical or data
center equipment; serial defects or underperformance with respect
to Iris Energy’s equipment; failure of suppliers to perform under
the relevant supply contracts for equipment that has already been
procured which may delay Iris Energy’s expansion plans; supply
chain and logistics issues for Iris Energy or Iris Energy’s
suppliers; cancellation or withdrawal of required operating and
other permits and licenses; customary risks in developing
greenfield infrastructure projects; Iris Energy’s evolving business
model and strategy; Iris Energy’s ability to successfully manage
its growth; Iris Energy’s ability to raise additional financing
(whether because of the conditions of the markets, Iris Energy’s
financial condition or otherwise) on a timely basis, or at all,
which could adversely impact the Company’s ability to meet its
capital commitments (including payments due under its hardware
purchase contracts with Bitmain) and the Company’s growth plans;
Iris Energy’s failure to make certain payments due under any one of
its hardware purchase contracts with Bitmain on a timely basis
could result in liquidated damages, claims for specific performance
or other claims against Iris Energy, any of which could result in a
loss of all or a portion of any prepayments or deposits made under
the relevant contract or other liabilities in respect of the
relevant contract, and could also result in Iris Energy not
receiving certain discounts under the relevant contract or
receiving the relevant hardware at all, any of which could
adversely impact its business, operating expansion plans, financial
condition, cash flows and results of operations; the terms of any
additional financing, which could be less favorable or require Iris
Energy to comply with more onerous covenants or restrictions, any
of which could restrict its business operations and adversely
impact its financial condition, cash flows and results of
operations; competition; Bitcoin prices, which could adversely
impact its financial condition, cash flows and results of
operations, as well as its ability to raise additional financing;
risks related to health pandemics including those of COVID-19;
changes in regulation of digital assets; and other important
factors discussed under the caption “Risk Factors” in Iris Energy’s
annual report on Form 20-F filed with the SEC on September 13,
2022, as such factors may be updated from time to time in its other
filings with the SEC, accessible on the SEC’s website at
www.sec.gov and the Investor Relations section of Iris Energy’s
website at https://investors.irisenergy.co.
These and other important factors could cause
actual results to differ materially from those indicated by the
forward-looking statements made in this press release. Any
forward-looking statement that Iris Energy makes in this press
release speaks only as of the date of such statement. Except as
required by law, Iris Energy disclaims any obligation to update or
revise, or to publicly announce any update or revision to, any of
the forward-looking statements, whether as a result of new
information, future events or otherwise.
Preliminary Financial
Information
The preliminary financial information for the
month of September 2022 included in this investor update is not
subject to the same closing procedures as our unaudited quarterly
financial results and has not been reviewed by our independent
registered public accounting firm. The preliminary financial
information included in this investor update does not represent a
comprehensive statement of our financial results or financial
position, and should not be viewed as a substitute for unaudited
financial statements prepared in accordance with International
Financial Reporting Standards. Accordingly, you should not place
undue reliance on the preliminary financial information included in
this investor update.
Contacts
MediaJon SnowballDomestique+61 477 946 068
InvestorsBom ShinIris Energy+61 411 376
332bom.shin@irisenergy.co
To keep updated on Iris Energy’s news releases and SEC filings,
please subscribe to email alerts at
https://investors.irisenergy.co/ir-resources/email-alerts.
__________________1 All timing references in this investor
update are to calendar quarters and calendar years, unless
otherwise specified.2 Reflects Bitcoin mined post deduction of
mining pool fees as applicable.3 Currently approximately 97%
directly from renewable energy sources; approximately 3% from
purchase of RECs.4 May potentially be supplemented with a small
portion of non S19j Pro and S19j miners as part of miner fleet
optimization across our sites following the agreement with Bitmain
in August to ship the additional 1.7 EH/s of miners.5 Comprises
actual power usage for Canal Flats and estimated power usage for
Mackenzie and Prince George.6 Includes mix of lower efficiency
hardware, which is estimated to represent less than 1% of the
operating 2.7 EH/s.7 Includes mix of lower efficiency hardware,
which is estimated to represent less than 8% of miners pending
deployment.
Photos accompanying this announcement are available at
https://www.globenewswire.com/NewsRoom/AttachmentNg/0d282096-1b0e-42c8-a12f-e2815d457cda
https://www.globenewswire.com/NewsRoom/AttachmentNg/852443d1-ca24-43e8-9c4f-0a0985d0e117
https://www.globenewswire.com/NewsRoom/AttachmentNg/0710bc9f-e9e7-4c4a-8f39-d25fe80da34d
https://www.globenewswire.com/NewsRoom/AttachmentNg/ba099434-573f-4d1b-9ec7-6bf87f6770dc
https://www.globenewswire.com/NewsRoom/AttachmentNg/477906f2-3c9b-4c89-8d11-e1d708990bfb
https://www.globenewswire.com/NewsRoom/AttachmentNg/3ea78499-68a1-4d33-8874-edfa63536022
Iris Energy (NASDAQ:IREN)
Gráfico Histórico do Ativo
De Mai 2023 até Jun 2023
Iris Energy (NASDAQ:IREN)
Gráfico Histórico do Ativo
De Jun 2022 até Jun 2023