Iris Energy Limited (NASDAQ: IREN) (“Iris Energy” or “the
Company”), a leading owner and operator of institutional-grade,
highly efficient proprietary Bitcoin mining data centers powered by
100% renewable energy, today published a monthly investor update
for October 2022, containing its results from operations as well as
construction and development updates.
The Company provided updates on November 2 and
November 7 in respect of the Group’s limited recourse equipment
financing arrangements as well as prepayments made to Bitmain
(“November Updates”). All information in this investor update is as
at October 31, 2022 (unless otherwise specified) and does not give
effect to the updates described in the November Updates (including
the termination of the relevant hosting arrangements, the purported
acceleration by the relevant lender of two of the Group’s three
limited recourse equipment financing facilities (the “Relevant
Facilities”) or the current status and outcome of discussions with
such lender in relation to the Relevant Facilities), which could
have a material impact on the Company’s operating capacity,
business, financial condition, cash flows and results of
operations.
Key Highlights1
Key metrics |
Oct-22 |
Average operating hashrate (PH/s) |
3,903 |
Bitcoin mined2 |
448 |
Mining revenue (US$’000) |
8,785 |
Electricity costs (US$’000) |
4,172 |
Revenue per Bitcoin (US$) |
19,591 |
Electricity costs per Bitcoin (US$) |
9,304 |
- Corporate:
- The Company
provided updates on November 2 and November 7 in respect of the
Group’s limited recourse equipment financing arrangements as well
as prepayments made to Bitmain
- Operations:
- Average operating
hashrate of 3,903 PH/s (+43% vs. September)
- Monthly operating
revenue of US$8.8 million (+41% vs. September)
- 448 Bitcoin mined
(+38% vs. September)
- Construction:
- Mackenzie (2.5
EH/s, 80MW – BC, Canada)
- Expansion from 50MW
to 80MW on track for energization by the end Q4 2022
- Internal fit-out
complete for the remaining 10MW of the third data center building
(20MW)
- Foundations and
erection of structural steel complete, and internal fit-out
progressing for the fourth data center building (20MW)
- Substation works to
increase capacity have commenced
- Childress (1.3
EH/s, 40MW – Texas, USA)3
- Foundation concrete
slab pouring has commenced for the substation area and first data
center building (20MW)
- Key civil, data
center building and substation contractors mobilized on site
Corporate update
Limited recourse equipment financing and Bitmain
prepayment update
The Company provided updates on November 2 and
November 7 in respect of the Group’s limited recourse equipment
financing arrangements as well as prepayments made to Bitmain.
The November Updates can be accessed via the
links below:
- November 2:
https://investors.irisenergy.co/news-releases/news-release-details/financing-and-bitmain-prepayment-update
- November
7: https://investors.irisenergy.co/node/7646/html
All information in this investor update
is as at October 31, 2022 (unless otherwise specified) and does not
give effect to the updates described in the November Updates
(including the termination of the relevant hosting arrangements,
the purported acceleration by the relevant lender of the Relevant
Facilities or the current status and outcome of discussions with
such lender in relation to the Relevant Facilities), which could
have a material impact on the Company’s operating capacity,
business, financial condition, cash flows and results of
operations.
Canal Flats update (0.8 EH/s, 30MW) –
BC, Canada
Canal Flats has been powered by 100% renewable
energy since inception.4
The project increased average monthly operating
hashrate to 862 PH/s in October compared to 848 PH/s last month.
Canal Flats continued to exceed previously announced site capacity
of 0.7 EH/s.
Mackenzie update (2.5 EH/s, 50MW
operating / 30MW under construction) – BC, Canada
Mackenzie has been powered by 100% renewable
energy since inception.4
The project achieved average monthly operating
hashrate of 1,577 PH/s in October compared to 1,579 PH/s in
September.
Construction activities at Mackenzie continue to
progress for the expansion from 50MW to 80MW, which will utilize
the remaining 10MW of the third data center building (20MW) and a
fourth data center building (20MW).
Internal fit-out of the remaining 10MW of the
third data center building (20MW) is complete. Foundations and
erection of structural steel for the additional fourth data center
building (20MW) is also complete, with internal fit-out ongoing.
The substation and on-site electrical distribution works for the
capacity increase are also underway. The additional 30MW remains on
track for completion by the end of Q4 2022.
Prince George update (1.4 EH/s, 50MW) –
BC, Canada
Prince George has been powered by 100% renewable
energy since inception.4
The project achieved average monthly operating
hashrate of 1,464 PH/s in October, being the first full month of
operations at 50MW.
Childress update (1.3 EH/s, 40MW) –
Texas, USA
Foundation and earthworks for the substation and
data center area continued throughout the month in readiness for
the 600MW transformer installation and first data center building
structure respectively.
Key civil, data center building and substation
contractors have mobilized to site and are being managed by a core
group of Iris Energy employees based in Childress.
Community engagement
In Childress, Iris Energy continued to work with
several of the successful recipients of the Community grants
program including the 4-H Club that supports students studying
Science, Technology, Engineering and Mathematics (STEM). The Texas
4-H Development Program provides inclusive opportunities to youth
ages 8-18 in grades 3-12 for personal growth, community service,
and fun.
Iris Energy also donated a drone to the
Childress High School Athletics Department. The drone is being used
by coaches of the football team to advance their training
practices.
At the Mackenzie site, Iris Energy hosted eight
high school students from the College of New Caledonia (CNC) Trade
Discovery program. The tour provided insight into the role the
electrical trades play in the construction and ongoing operations
of our data centers.
Future development sites
Development works continued across additional
sites in Canada, the USA and Asia-Pacific, which have the potential
to support up to an additional >1GW of aggregate power capacity
capable of powering growth beyond the Company’s 795MW of announced
power capacity.
Operating and financial results
Daily average operating hashrate chart is available at
https://www.globenewswire.com/NewsRoom/AttachmentNg/e8e68f5f-6c1d-4f46-9d1b-6fb5dd3a6c63
Technical commentary
The Company’s average operating hashrate was
3,903 PH/s in October (compared to 2,729 PH/s in September), with
the increase being primarily attributable to the first full month
of operations at Prince George at 50MW. The corresponding increase
in Bitcoin mined (448 vs. 325 in September) and electricity costs
($4.2 million vs. $2.8 million in September) were also attributable
to Prince George.
The increase in Bitcoin mined during the month
(448 vs. 325 in September) was a result of the increased average
operating hashrate and was partially offset by an increase in the
average difficulty-implied global hashrate during the period (248
EH/s vs. 226 EH/s in September), which was also the primary driver
behind the increase in the Company’s electricity costs per Bitcoin
mined ($9.3k vs. $8.7k in September).
Operating* |
Aug-22 |
Sep-22 |
Oct-22 |
Renewable energy usage (MW)5 |
69 |
85 |
123 |
Avg operating hashrate (PH/s) |
2,204 |
2,729 |
3,903 |
* Reflects actual recorded operating power usage and hashrate
(not nameplate). Note: nameplate capacity is higher than actual
operating power usage due to features of the Company’s proprietary
data center design which utilizes variable speed fans to reduce
power consumption during cooler months, as well as the Company
maintaining a buffer within its infrastructure capacity that can be
also directed to other site uses (e.g. in-house fabrication shop at
Canal Flats is currently operating as Iris Energy has the advantage
of saving time and costs by internally constructing certain
components for its expansion sites).
Financial (unaudited) |
Aug-22 |
Sep-22 |
Oct-22 |
Bitcoin mined* |
301 |
325 |
448 |
Mining revenue (US$’000) |
6,629 |
6,224 |
8,795 |
Electricity costs (US$’000) |
2,436 |
2,829 |
4,172 |
Revenue per Bitcoin (US$) |
22,027 |
19,124 |
19,591 |
Electricity costs per Bitcoin (US$) |
8,094 |
8,691 |
9,304 |
* Reflects Bitcoin mined post deduction of
mining pool fees as applicable.
Miner Shipping Schedule |
Hardware |
Units |
EH/s (incremental) |
EH/s(cumulative) |
Operating (October) |
S19j Pro / S19j6 |
39,707 |
3.9 |
3.9 |
Inventory – pending deployment |
S19j Pro / S19j7 |
7,805 |
0.6 |
4.5 |
Inventory – in transit |
S19j Pro / S19j8 |
14,234 |
1.4 |
5.9 |
Q4 2022 |
S19j |
1,500 |
0.1 |
6.0 |
Total |
|
63,246 |
6.0 |
6.0 |
Site* |
Capacity(MW) |
Capacity (EH/s) |
Timing |
Status |
Canal Flats (BC, Canada) |
30 |
0.8 |
Complete |
Operating |
Mackenzie (BC, Canada) |
50 |
1.5 |
Complete |
Operating |
30 |
1.0 |
Q4 2022 |
Under construction |
Prince George (BC, Canada) |
50 |
1.4 |
Complete |
Operating |
Total (end of Q4 2022) |
160 |
4.7 |
|
|
Childress (Texas, US) |
40 |
1.3 |
2023 |
Under construction9 |
Total (2023) |
200 |
6.0 |
|
|
* All information in this investor update is as at
October 31, 2022 (unless otherwise specified) and does not give
effect to the updates described in the November Updates (including
the termination of the relevant hosting arrangements, the purported
acceleration by the relevant lender of the Relevant Facilities or
the current status and outcome of discussions with such lender in
relation to the Relevant Facilities), which could have a material
impact on the Company’s operating capacity, business, financial
condition, cash flows and results of operations.
About Iris Energy
Iris Energy is a sustainable Bitcoin mining
company that supports the decarbonization of energy markets and the
global Bitcoin network.
- 100% renewables:
Iris Energy targets markets with low-cost, under-utilized renewable
energy, and where the Company can support local communities
- Long-term security
over infrastructure, land and power supply: Iris Energy builds,
owns and operates its electrical infrastructure and proprietary
data centers, providing long-term security and operational control
over its assets
- Seasoned management
team: Iris Energy’s team has an impressive track record of success
across energy, infrastructure, renewables, finance, digital assets
and data centers with cumulative experience in delivering >$25bn
in energy and infrastructure projects globally
Forward-Looking Statements
This press release includes “forward-looking
statements” within the meaning of the Private Securities Litigation
Reform Act of 1995. Forward-looking statements generally relate to
future events or Iris Energy’s future financial or operating
performance. For example, forward-looking statements include but
are not limited to, the Company’s expected power capacity and
operating capacity, and the impact of an event of default and/or
acceleration of amounts due under limited recourse equipment
financing arrangements in the Company’s special purpose vehicles.
In some cases, you can identify forward-looking statements by
terminology such as “anticipate,” “believe,” “may,” “can,”
“should,” “could,” “might,” “plan,” “possible,” “project,”
“strive,” “budget,” “forecast,” “expect,” “intend,” “target”,
“will,” “estimate,” “predict,” “potential,” “continue,” “scheduled”
or the negatives of these terms or variations of them or similar
terminology, but the absence of these words does not mean that
statement is not forward-looking. Such forward-looking statements
are subject to risks, uncertainties, and other factors which could
cause actual results to differ materially from those expressed or
implied by such forward looking statements. In addition, any
statements or information that refer to expectations, beliefs,
plans, projections, objectives, performance or other
characterizations of future events or circumstances, including any
underlying assumptions, are forward-looking.
These forward-looking statements are based on
management’s current expectations and beliefs. These statements are
neither promises nor guarantees, but involve known and unknown
risks, uncertainties and other important factors that may cause
Iris Energy’s actual results, performance or achievements to be
materially different from any future results, performance or
achievements expressed or implied by the forward-looking
statements, including, but not limited to: Iris Energy’s limited
operating history with operating losses; electricity outage,
limitation of electricity supply or increase in electricity costs;
long term outage or limitation of the internet connection at Iris
Energy’s sites; any critical failure of key electrical or data
center equipment; serial defects or underperformance with respect
to Iris Energy’s equipment; failure of suppliers to perform under
the relevant supply contracts for equipment that has already been
procured which may delay Iris Energy’s expansion plans; supply
chain and logistics issues for Iris Energy or Iris Energy’s
suppliers; cancellation or withdrawal of required operating and
other permits and licenses; customary risks in developing
greenfield infrastructure projects; Iris Energy’s evolving business
model and strategy; Iris Energy’s ability to successfully manage
its growth; Iris Energy’s ability to raise additional financing
(whether because of the conditions of the markets, Iris Energy’s
financial condition or otherwise) on a timely basis, or at all,
which could adversely impact the Company’s ability to meet its
capital commitments (including payments due under its hardware
purchase contracts with Bitmain) and the Company’s growth plans;
Iris Energy’s failure to make certain payments due under any one of
its hardware purchase contracts with Bitmain on a timely basis
could result in liquidated damages, claims for specific performance
or other claims against Iris Energy, any of which could result in a
loss of all or a portion of any prepayments or deposits made under
the relevant contract or other liabilities in respect of the
relevant contract, and could also result in Iris Energy not
receiving certain discounts under the relevant contract or
receiving the relevant hardware at all, any of which could
adversely impact its business, operating expansion plans, financial
condition, cash flows and results of operations; the failure of
Iris Energy’s wholly-owned special purpose vehicles to make
required payments of principal and/or interest under their limited
recourse equipment financing arrangements when due or otherwise
comply with the terms thereof, as a result of which the lender
thereunder has purported to declare the entire principal amount of
the relevant loans to be immediately due and payable and we expect
that those entities would not have sufficient funds to repay such
facilities absent a refinancing, restructuring or modification of
the terms of the relevant facility or other relief or waiver from
the lender (which those entities may not be able to obtain on
commercially reasonable terms or without significant additional
cost) and as a result such lender could seek to foreclose on the
Bitcoin miners and other assets securing the relevant loans and
would have recourse to the assets of the relevant special purpose
vehicle, any of which could result in the loss of such Bitcoin
miners, materially reduce the Company’s operating capacity, lead to
bankruptcy or liquidation of the relevant special purpose vehicles,
and materially and adversely impact the Company’s business,
operating expansion plans, financial condition, cash flows and
results of operations; the terms of any additional financing or any
refinancing, restructuring or modification to the terms of any
existing financing, which could be less favorable or require Iris
Energy to comply with more onerous covenants or restrictions, any
of which could restrict its business operations and adversely
impact its financial condition, cash flows and results of
operations; competition; Bitcoin prices, global hashrate and the
market value of Bitcoin miners, any of which could adversely impact
the Company’s financial condition, cash flows and results of
operations, as well as its ability to raise additional financing
and the ability of its wholly-owned special purpose vehicles to
make required payments of principal and/or interest on their
equipment financing facilities; risks related to health pandemics
including those of COVID-19; changes in regulation of digital
assets; and other important factors discussed under the caption
“Risk Factors” in Iris Energy’s annual report on Form 20-F filed
with the SEC on September 13, 2022, as such factors may be updated
from time to time in its other filings with the SEC, accessible on
the SEC’s website at www.sec.gov and the Investor Relations section
of Iris Energy’s website at https://investors.irisenergy.co.
These and other important factors could cause
actual results to differ materially from those indicated by the
forward-looking statements made in this press release. Any
forward-looking statement that Iris Energy makes in this press
release speaks only as of the date of such statement. Except as
required by law, Iris Energy disclaims any obligation to update or
revise, or to publicly announce any update or revision to, any of
the forward-looking statements, whether as a result of new
information, future events or otherwise.
Preliminary Financial
Information
The preliminary financial information for the
month of October 2022 included in this investor update is not
subject to the same closing procedures as our unaudited quarterly
financial results and has not been reviewed by our independent
registered public accounting firm. The preliminary financial
information included in this investor update does not represent a
comprehensive statement of our financial results or financial
position and should not be viewed as a substitute for unaudited
financial statements prepared in accordance with International
Financial Reporting Standards. Accordingly, you should not place
undue reliance on the preliminary financial information included in
this investor update.
Contacts
MediaJon SnowballDomestique+61 477 946 068
InvestorsBom ShinIris Energy+61 411 376
332bom.shin@irisenergy.co
To keep updated on Iris Energy’s news releases and SEC filings,
please subscribe to email alerts at
https://investors.irisenergy.co/ir-resources/email-alerts.
________________________________1 All timing references in this
investor update are to calendar quarters and calendar years, in
each case unless otherwise specified.2 Reflects Bitcoin mined post
deduction of mining pool fees as applicable.3 Decisions around how
much, and when, data center capacity above an initial 20MW will be
built at Childress are being assessed. See the Company’s November 7
update at: https://investors.irisenergy.co/node/7646/html.4
Currently approximately 97% directly from renewable energy sources;
approximately 3% from purchase of RECs.5 Comprises actual power
usage for Canal Flats and estimated power usage for Mackenzie and
Prince George.6 Includes mix of lower efficiency hardware, which is
estimated to represent less than 1% of the operating 3.9 EH/s.
Includes 1.0 EH/s not subject to the Relevant Facilities. The
Company continues to assess installation plans for the balance of
the Group’s 2.4 EH/s, and opportunities to utilize available data
center capacity to either host third-party miners or to self-mine
utilizing additional miners that the Company elects to purchase (or
a combination thereof).7 Includes mix of lower efficiency hardware,
which is estimated to represent less than 21% of miners pending
deployment. Includes 0.1 EH/s not subject to the Relevant
Facilities.8 Includes 1.3 EH/s not subject to the Relevant
Facilities.9 Decisions around how much, and when, data center
capacity above an initial 20MW will be built at Childress are being
assessed. See the Company’s November 7 update at:
https://investors.irisenergy.co/node/7646/html.
Photos accompanying this announcement are available at
https://www.globenewswire.com/NewsRoom/AttachmentNg/4870733d-8ae9-43c7-b873-b6bc34c7f7a4
https://www.globenewswire.com/NewsRoom/AttachmentNg/b370ade0-6798-413c-81b2-d176b0dfce60
https://www.globenewswire.com/NewsRoom/AttachmentNg/7358264a-a798-48a6-8051-b29f417e35e8
https://www.globenewswire.com/NewsRoom/AttachmentNg/a34bfd1a-55dc-4a9c-b0e5-fbc7be8c4a8e
https://www.globenewswire.com/NewsRoom/AttachmentNg/a7f75e74-802e-4131-8836-d2cd2cbb84a5
https://www.globenewswire.com/NewsRoom/AttachmentNg/f2cf5d0b-7dbb-4d5c-83d0-890d439beef0
Iris Energy (NASDAQ:IREN)
Gráfico Histórico do Ativo
De Abr 2023 até Mai 2023
Iris Energy (NASDAQ:IREN)
Gráfico Histórico do Ativo
De Mai 2022 até Mai 2023