Iris Energy Limited (NASDAQ: IREN) (“Iris Energy” or “the
Company”), a leading owner and operator of institutional-grade,
highly efficient proprietary Bitcoin mining data centers powered by
100% renewable energy, today published a monthly investor update
for November 2022, containing its results from operations as well
as construction and development updates.
Key Highlights1
Key metrics2 |
Nov-22 |
Average operating hashrate (PH/s) |
1,445 |
Bitcoin mined |
151 |
Mining revenue (US$’000) |
2,871 |
Electricity costs (US$’000) |
1,905 |
Revenue per Bitcoin (US$) |
18,955 |
Electricity costs per Bitcoin (US$) |
12,581 (10,168 adj)3 |
- Corporate:
- On December 6, the
Company provided an investor update – “Everything changes,
everything remains the same” – in respect of its positioning,
go-forward opportunities, and strategic priorities
- Risk-focused
approach positions the Company to weather the storm and capitalize
on the next bull run
- Liquidity (as of
month end)
- $47 million cash,
no debt4
- $21 million
estimated net capex spend to achieve 180MW5
- $75 million
remaining Bitmain prepayments
- $100 million
unutilized under B. Riley equity facility6
- Potential
monetization of assets through miner sales (2.4 EH/s down to 2.0
EH/s7)
- Opportunities
- Significant
optionality from 180MW real assets platform (e.g. self-mining or
hosting)
- Focus on expanding
self-mining capacity to 5.4 EH/s
- Potential
additional expansion from 20MW to 600MW at Childress
- On November 21, the Company also
provided a corporate update and announced certain preliminary
financial information and operational updates for Q1 FY23 and
October 2022
- Operations (for the
month of November 2022):
- Average operating
hashrate of 1,445 PH/s (-63% vs. October)8
- Monthly operating
revenue of $2.9 million (-67% vs. October)
- 151 Bitcoin mined
(-66% vs. October)
The reduction in operating metrics (vs.
October) primarily reflects termination of hosting arrangements
during the month in connection with certain of the Group’s limited
recourse equipment financing facilities following receipt of an
acceleration notice from the relevant lender under such
facilities9
- Construction:
- Mackenzie (80MW –
BC, Canada)
- Expansion from 50MW
to 80MW energized on December 6, 2022, three weeks ahead of
schedule
- Internal data
center fit-out complete for the additional 30MW
- Childress (20MW –
Texas, USA)
- Foundations and
earthworks for the substation and first data center building (20MW)
complete
- Structural steel
for the first data center building (20MW) erected
- Substation area
prepared for upcoming delivery and installation of the 600MW
transformer and main power transformers
Corporate update
Strategic update
On December 6, the Company provided an investor
update – “Everything changes, everything remains the same” – in
respect of its positioning, go-forward opportunities, and strategic
priorities.
Key takeaways included:
- Risk-focused
approach positions the Company to weather the storm and capitalize
on the next bull run
- Liquidity (as of
month end)
- $47 million cash,
no debt4
- $21 million
estimated net capex spend to achieve 180MW5
- $75 million
remaining Bitmain prepayments
- $100 million
unutilized under B. Riley equity facility6
- Potential
monetization of assets through miner sales (2.4 EH/s down to 2.0
EH/s7)
- Opportunities
- Significant
optionality from 180MW real assets platform (e.g. self-mining or
hosting)
- Focus on expanding
self-mining capacity to 5.4 EH/s
- Potential
additional expansion from 20MW to 600MW at Childress
The webcast and the Company’s latest investor
presentation are available on the Company’s website here:
https://investors.irisenergy.co/events-and-presentations
Corporate, financial and operational updates
On November 21, the Company provided a corporate
update and announced certain preliminary financial information and
operational updates for the three months ended September 30, 2022,
as well as certain additional preliminary financial information
with respect to the month of October 2022.
The update can be accessed via the following
link: https://investors.irisenergy.co/node/7706/html
Canal Flats update (0.8 EH/s, 30MW) –
BC, Canada
Canal Flats has been powered by 100% renewable
energy since inception10.
The project achieved average monthly operating
hashrate of 570 PH/s in November (0.8 EH/s of capacity)11.
Mackenzie update (2.5 EH/s, 80MW) – BC,
Canada
Mackenzie has been powered by 100% renewable
energy since inception10.
The project achieved average monthly operating
hashrate of 268 PH/s in November (2.5 EH/s of capacity)11.
Expansion from 50MW to 80MW was energized on
December 6, 2022, three weeks ahead of schedule, and will utilize
the remaining 10MW of the third data center building (20MW) and a
fourth data center building (20MW) with both internal fit-outs
complete.
Prince George update (1.4 EH/s, 50MW) –
BC, Canada
Prince George has been powered by 100% renewable
energy since inception10.
The project achieved average monthly operating
hashrate of 607 PH/s in November (1.4 EH/s of capacity)11.
Childress update (0.7 EH/s, 20MW) –
Texas, USA
Foundations and earthworks for the substation
were completed during the month. Structural steel for the first
data center building (20MW) was erected as earthworks, and the
substation area is prepared for the upcoming delivery and
installation of the 600MW transformer and main power
transformers.
Key civil, data center building, substation, and
electrical contractors continue to progress construction activities
and are being managed by a core group of Iris Energy employees
based in Childress.
Approximately $18 million in previous deposits
with AEP Texas are expected to be refunded following energization
at Childress.
Community engagement
In November 2022, Iris Energy sponsored the
Windermere Valley Saddle Club, a non-profit horse club that aims to
encourage and educate the youth of the Canal Flats Valley about
horsemanship. In Mackenzie, Iris Energy team members honoured those
who have served by laying a wreath in the Remembrance Day
ceremony.
Future development sites
Development works continued across additional
sites in Canada, the USA and Asia-Pacific, which have the potential
to support up to an additional >1GW of aggregate power capacity
capable of powering growth beyond the Company’s 795MW of announced
power capacity.
Operating and financial results
Daily average operating hashrate chart is available at
https://www.globenewswire.com/NewsRoom/AttachmentNg/a6fd0c6a-86ce-4529-b3d8-d5eaeb2b997c
Technical commentary
The Company’s average operating hashrate was 1,445 PH/s in
November 2022 (compared to 3,899 PH/s in October8), with the
decrease primarily attributable to the termination of hosting
arrangements during the month in connection with certain of the
Company’s limited recourse equipment financing facilities as
described above9. The corresponding decrease in Bitcoin mined (151
vs. 448 in October) and electricity costs ($1.9 million vs. $4.2
million in October8) were also primarily attributable to the
termination of these hosting arrangements.
The energization of the 30MW expansion at Mackenzie ahead of
schedule, increases the Company’s total available data center
capacity to 160MW, capable of powering approximately 4.7 EH/s of
miners (via self-mining and/or hosting).
The increase in the Company’s unadjusted
electricity costs per Bitcoin mined ($12.6k vs. $10.2k adj vs.
$9.3k in October8) was primarily driven by excess demand charges
attributable to average unutilized power capacity (due to
termination of relevant hosting arrangements as described above) as
well as the increase in the average difficulty-implied global
hashrate during the period.
Operating |
Sep-22 |
Oct-22 |
Nov-22 |
Renewable energy usage
(MW)12* |
84 |
123 |
46 |
Avg operating hashrate (PH/s)8* |
2,679 |
3,899 |
1,445 |
Financial (unaudited)2 |
Sep-22 |
Oct-22 |
Nov-22 |
Bitcoin mined |
325 |
448 |
151 |
Mining revenue (US$’000) |
6,224 |
8,785 |
2,871 |
Electricity costs (US$’000)8* |
2,737 |
4,167 |
1,905 |
Revenue per Bitcoin (US$) |
19,124 |
19,591 |
18,955 |
Electricity costs per Bitcoin (US$)8* |
8,410 |
9,293 |
12,581 (10,128 adj)3 |
* Restated – see section ‘Restatement of prior
period metrics’ for further details.
Restatement of prior period metrics
The Company has refined its methodology for calculating
electricity costs and monthly average operating hashrate to align
with the respective reported Bitcoin mined each month by one day as
a result of time zones and mining pool payout timing.
Please see below for the restated average operating
hashrate.
2022 |
Jan |
Feb |
Mar |
Apr |
May |
Jun |
Jul |
Aug |
Sep |
Oct |
Nov |
Avg operating hashrate (PH/s) – restated |
802 |
844 |
849 |
1,028 |
1,165 |
1,164 |
1,120 |
2,162 |
2,679 |
3,899 |
1,445 |
BTC mined – unchanged |
126 |
110 |
121 |
137 |
151 |
148 |
154 |
301 |
325 |
448 |
151* |
* Under the previous methodology, Bitcoin mined divided by
average operating hashrate (1.347 EH/s) would have been ~112 for
November (vs. ~105 under the restated methodology).
Miner Shipping Schedule* |
Hardware |
Units |
EH/s(incremental) |
EH/s(cumulative) |
Operating (as of December 12)** |
S19j Pro13 |
12,042 |
1.1 |
1.1 |
Inventory – in transit and/or pending deployment*** |
S19j Pro14 |
9,223 |
0.9 |
0.9 |
Total |
|
21,265 |
2.0 |
2.0 |
* Excludes ~3.6 EH/s of miners securing
equipment financing facilities with two of the Company’s three SPV
borrowers in respect of which the Company has received a notice of
acceleration from the relevant lender, none of which have been
operating following termination of relevant hosting arrangements
during the month as described above. Approximately $103.4m
aggregate principal amount of loans are outstanding under such
facilities as of October 31, 2022. See the Company's Report on Form
6-K filed on November 21, 2022 for further information.** Includes
~0.2 EH/s of miners securing the limited recourse equipment
financing facility with the Company’s third SPV borrower in respect
of which the Company has received a notice of acceleration from the
relevant lender. Approximately $1m aggregate principal amount of
loans are outstanding under such facility as of November 30, 2022.
See the Company's Report on Form 6-K filed on November 21, 2022 for
further information.*** Excludes ~0.4 EH/s of miners in transit
and/or pending deployment for which the Company is currently
finalizing monetization transactions. There can be no assurance as
to the timing or terms of any such transaction, or whether any such
transaction will be consummated at all.
Site |
Capacity (MW) |
Capacity(EH/s)15 |
Timing |
Status |
Canal Flats (BC, Canada) |
30 |
0.8 |
Complete |
Operating |
Mackenzie (BC, Canada) |
50 |
1.5 |
Complete |
Operating |
30 |
1.0 |
Complete |
Energized |
Prince George (BC, Canada) |
50 |
1.4 |
Complete |
Operating |
Total (BC, Canada) |
160 |
4.7 |
|
|
Childress (Texas, US) |
20 |
0.7 |
2023 |
Under construction16 |
Total (Canada & USA) |
180 |
5.4 |
|
|
About Iris Energy
Iris Energy is a sustainable Bitcoin mining
company that supports the decarbonization of energy markets and the
global Bitcoin network.
- 100% renewables:
Iris Energy targets markets with low-cost, under-utilized renewable
energy, and where the Company can support local communities
- Long-term security
over infrastructure, land and power supply: Iris Energy builds,
owns and operates its electrical infrastructure and proprietary
data centers, providing long-term security and operational control
over its assets
- Seasoned management
team: Iris Energy’s team has an impressive track record of success
across energy, infrastructure, renewables, finance, digital assets
and data centers with cumulative experience in delivering >$25bn
in energy and infrastructure projects globally
Forward-Looking Statements
This investor update includes “forward-looking
statements” within the meaning of the Private Securities Litigation
Reform Act of 1995. Forward-looking statements generally relate to
future events or Iris Energy’s future financial or operating
performance. For example, forward-looking statements include but
are not limited to, the Company’s expected power capacity and
operating capacity, and the impact of an event of default and/or
acceleration of amounts due under limited recourse equipment
financing arrangements in the Company’s special purpose vehicles.
In some cases, you can identify forward-looking statements by
terminology such as “anticipate,” “believe,” “may,” “can,”
“should,” “could,” “might,” “plan,” “possible,” ”project,”
“strive,” “budget,” “forecast,” “expect,” “intend,” “target”,
“will,” “estimate,” “predict,” “potential,” “continue”, ”scheduled”
or the negatives of these terms or variations of them or similar
terminology, but the absence of these words does not mean that
statement is not forward-looking. Such forward-looking statements
are subject to risks, uncertainties, and other factors which could
cause actual results to differ materially from those expressed or
implied by such forward looking statements. In addition, any
statements or information that refer to expectations, beliefs,
plans, projections, objectives, performance or other
characterizations of future events or circumstances, including any
underlying assumptions, are forward-looking.
These forward-looking statements are based on
management’s current expectations and beliefs. These statements are
neither promises nor guarantees, but involve known and unknown
risks, uncertainties and other important factors that may cause
Iris Energy’s actual results, performance or achievements to be
materially different from any future results, performance or
achievements expressed or implied by the forward-looking
statements, including, but not limited to: Iris Energy’s limited
operating history with operating losses; electricity outage,
limitation of electricity supply or increase in electricity costs;
long term outage or limitation of the internet connection at Iris
Energy’s sites; any critical failure of key electrical or data
center equipment; serial defects or underperformance with respect
to Iris Energy’s equipment; failure of suppliers to perform under
the relevant supply contracts for equipment that has already been
procured which may delay Iris Energy’s expansion plans; supply
chain and logistics issues for Iris Energy or Iris Energy’s
suppliers; cancellation or withdrawal of required operating and
other permits and licenses; customary risks in developing
greenfield infrastructure projects; Iris Energy’s evolving business
model and strategy; Iris Energy’s ability to successfully manage
its growth; Iris Energy’s ability to raise additional financing
(whether because of the conditions of the markets, Iris Energy’s
financial condition or otherwise) on a timely basis, or at all,
which could adversely impact the Company’s ability to meet its
capital commitments (including payments due under its hardware
purchase contracts with Bitmain) and the Company’s growth plans;
Iris Energy’s failure to make certain payments due under any one of
its hardware purchase contracts with Bitmain on a timely basis
could result in liquidated damages, claims for specific performance
or other claims against Iris Energy, any of which could result in a
loss of all or a portion of any prepayments or deposits made under
the relevant contract or other liabilities in respect of the
relevant contract, and could also result in Iris Energy not
receiving certain discounts under the relevant contract or
receiving the relevant hardware at all, any of which could
adversely impact its business, operating expansion plans, financial
condition, cash flows and results of operations; the failure of
Iris Energy’s wholly-owned special purpose vehicles to make
required payments of principal and/or interest under their limited
recourse equipment financing arrangements when due or otherwise
comply with the terms thereof, as a result of which the lender
thereunder has declared the entire principal amount of each loan to
be immediately due and payable, and while no assurance can be
provided as to what actions may be taken, we expect such lender
will take steps to enforce the indebtedness and its rights in the
Bitcoin miners with respect to certain of such loans (and
potentially all such loans) and other assets securing such loans,
which would result in the loss of the relevant Bitcoin miners
securing such loans and materially reduce the Company’s operating
capacity, and could also lead to bankruptcy or liquidation of the
relevant special purpose vehicles, and materially and adversely
impact the Company’s business, operating expansion plans, financial
condition, cash flows and results of operations; the terms of any
additional financing or any refinancing, restructuring or
modification to the terms of any existing financing, which could be
less favorable or require Iris Energy to comply with more onerous
covenants or restrictions, any of which could restrict its business
operations and adversely impact its financial condition, cash flows
and results of operations; competition; Bitcoin prices, global
hashrate and the market value of Bitcoin miners, any of which could
adversely impact the Company’s financial condition, cashflows and
results of operations, as well as its ability to raise additional
financing and the ability of its wholly-owned special purpose
vehicles to make required payments of principal and/or interest on
their equipment financing facilities; risks related to health
pandemics including those of COVID-19; changes in regulation of
digital assets; and other important factors discussed under the
caption “Risk Factors” in Iris Energy’s Annual Report on Form 20-F
for the fiscal year ended June 30, 2022 filed with the SEC on
September 13, 2022, as such factors may be updated from time to
time in its other filings with the SEC, accessible on the SEC’s
website at www.sec.gov and the Investor Relations section of Iris
Energy’s website at https://investors.irisenergy.co.
These and other important factors could cause
actual results to differ materially from those indicated by the
forward-looking statements made in this investor update. Any
forward-looking statement that Iris Energy makes in this investor
update speaks only as of the date of such statement. Except as
required by law, Iris Energy disclaims any obligation to update or
revise, or to publicly announce any update or revision to, any of
the forward-looking statements, whether as a result of new
information, future events or otherwise.
Preliminary Financial
Information
The preliminary financial information for the
month of November 2022 included in this investor update is not
subject to the same closing procedures as our unaudited quarterly
financial results and has not been reviewed by our independent
registered public accounting firm. The preliminary financial
information included in this investor update does not represent a
comprehensive statement of our financial results or financial
position and should not be viewed as a substitute for unaudited
financial statements prepared in accordance with International
Financial Reporting Standards. Accordingly, you should not place
undue reliance on the preliminary financial information included in
this investor update.
Contacts
MediaJon SnowballDomestique+61 477 946 068
InvestorsLincoln TanIris Energy+61 407 423
395lincoln.tan@irisenergy.co
To keep updated on Iris Energy’s news releases and SEC filings,
please subscribe to email alerts at
https://investors.irisenergy.co/ir-resources/email-alerts.
_____________________
1 All timing references in this investor update are to calendar
quarters and calendar years, in each case unless otherwise
specified.2 Bitcoin and Bitcoin mined in this investor update are
presented in accordance with our revenue recognition policy which
is determined on a Bitcoin received basis (post deduction of mining
pool fees as applicable). 3 The increase in the Company’s
unadjusted electricity costs per Bitcoin mined ($12.6k vs. $10.2k
adj vs. $9.3k in October) was primarily driven by excess demand
charges attributable to average unutilized power capacity (due to
termination of hosting arrangements in connection with certain of
the Group’s limited recourse equipment financing facilities) as
well as the increase in the average difficulty-implied global
hashrate during the period. The adjusted electricity costs per
Bitcoin mined ($10.2k) excludes such excess demand charges (i.e.
assumes unit electricity costs of ~$0.046/kWh).4 Reflects USD
equivalent, unaudited preliminary cash balance as of November 30,
2022 (excluding cash held by the two relevant SPV borrowers).
Reflects acceleration of outstanding loans under two of the Group's
three outstanding limited recourse equipment financing facilities
and assumes foreclosure by the lender thereunder against the
collateral securing such facilities held by the applicable
non-recourse SPV borrowers, and also assumes repayment by the Group
on behalf of the applicable SPV borrower of $1m of outstanding
loans under the Group's third limited recourse equipment financing
facility. See the Company's Report on Form 6-K filed on November
21, 2022 for further information. Following such acceleration and
foreclosure, and such repayment, as applicable, the Group would not
have any indebtedness for borrowed money outstanding.5 Indicative
estimated remaining net capital expenditure to build out 180MW of
infrastructure and repay $1m of outstanding loans under the Group’s
third limited recourse equipment financing facility (net of
anticipated proceeds from hardware sales and anticipated tax and
deposit refunds). Excludes impact of all other potential future
cash movements (e.g. operating cashflows and financing cashflows).6
Subject to market conditions and regulatory approvals.7 Comprises
~1.1 EH/s of miners in operation as of December 12 (including ~0.2
EH/s of miners securing the facility with the Company’s third
limited recourse equipment financing facility in respect of which
the Company has received a notice of acceleration as described in
the Company's Report on Form 6-K filed on November 21, 2022) and
~0.9 EH/s of miners in transit and/or pending deployment. The
Company is currently finalizing monetization transactions with
respect to ~0.4 EH/s of miners which are in transit and/or pending
deployment. There can be no assurance as to the timing or terms of
any such transaction, or whether any such transaction will be
consummated at all.8 Certain metrics reported for prior periods
have been restated in this investor update to reflect refined
methodology. See section ‘Restatement of prior period metrics’ for
further details.9 Refer to the Company’s announcements on November
7, 2022 and November 21, 2022.10 Currently approximately 97%
directly from renewable energy sources; approximately 3% from
purchase of RECs.11 However figures are post impact of termination
of hosting arrangements associated with certain of the Company’s
limited recourse equipment financing facilities as described
above.12 Comprises actual power usage for Canal Flats, Mackenzie
and Prince George.13 Includes mix of lower efficiency hardware,
which is estimated to represent less than 10% of the operating 1.1
EH/s.14 Includes mix of lower efficiency hardware, which is
estimated to represent less than 4% of miners in transit and/or
pending deployment.15 Reflects estimated hashrate capacity by site
assuming full utilization of available data center capacity with
additional Bitmain S19j Pro miners.16 Decisions around how much,
and when, data center capacity above an initial 20MW will be built
at Childress are being assessed.
Photos accompanying this announcement are available at:
https://www.globenewswire.com/NewsRoom/AttachmentNg/62b18a9d-4dbb-457e-ba5a-47d5d72f41b3
https://www.globenewswire.com/NewsRoom/AttachmentNg/2014ef4e-f053-47dc-98f8-0f53d2b9cd97
https://www.globenewswire.com/NewsRoom/AttachmentNg/0be1738e-84bf-494d-9384-9a0ac8b9f120
Iris Energy (NASDAQ:IREN)
Gráfico Histórico do Ativo
De Mai 2023 até Jun 2023
Iris Energy (NASDAQ:IREN)
Gráfico Histórico do Ativo
De Jun 2022 até Jun 2023