Iris Energy Limited (NASDAQ: IREN) ("Iris Energy" or "the
Company"), a leading owner and operator of institutional-grade,
highly efficient proprietary Bitcoin mining data centers powered by
100% renewable energy, today published a monthly investor update
for February 2023, containing its results from operations as well
as business updates.
Key
Highlights1
Key metrics2 |
Feb-23 |
Average operating hashrate (PH/s) |
1,730 |
Bitcoin mined |
156 |
Mining revenue (US$’000) |
3,539 |
Electricity costs (US$’000) |
1,869 |
Revenue per Bitcoin (US$) |
22,637 |
Electricity costs per Bitcoin (US$) |
11,956 (10,608 adj)3 |
- Corporate:
- US$67 million of
remaining Bitmain prepayments utilized to acquire 4.4 EH/s of new
S19j Pro miners without any additional cash outlay
- Newly acquired
miners to be installed in the Company’s data centers, increasing
self-mining operating capacity from 2.0 EH/s to 5.5 EH/s over the
coming months
- Reported financial
results for the three and six-months ended December 31, 2022 and
provided a general business update
- Operations (for the
month of February 2023):
- Average operating
hashrate of 1,730 PH/s (+10% vs. January)
- Monthly operating
revenue of US$3.5 million (+2% vs. January)
- 156 Bitcoin mined
(-9% vs. January)
- Construction:
- Childress (20MW –
Texas, USA)
- First data center
building (20MW) structure is complete and mechanical equipment
installation has commenced
- Internal data
center electrical fit out continuing
- Initial 20MW data
center nearing completion in the coming months with orders placed
for the next 20MW of low voltage building transformers
- Energization of the
600MW bulk substation (345kV) and commissioning of the 100MW
primary substation (138kV) expected in the coming months
Corporate update
Increasing self-mining capacity from 2.0 EH/s to
5.5 EH/s
On February 13, Iris Energy announced it is
increasing its self-mining capacity from 2.0 EH/s to 5.5 EH/s.
The Company successfully utilized remaining
prepayments of US$67 million under its 10 EH/s contract with
Bitmain, including a concurrent sale of 2.3 EH/s of the remaining
6.7 EH/s contracted miners to a third party, to acquire 4.4 EH/s of
new S19j Pro miners without any additional cash outlay.
Following the transaction, the Group’s
obligations under its existing 10 EH/s contract with Bitmain have
been fully resolved, with no remaining commitments. The Group
remains debt free4.
Please see link to the announcement here:
https://investors.irisenergy.co/news-releases
The Company subsequently completed the sale of
certain surplus miners, above 5.5 EH/s of self-mining capacity,
resulting in net cash proceeds of approximately $8 million.
Second quarter FY23 financial results
On February 15, Iris Energy reported financial
results for the three and six-months ended December 31, 2022 and
provided a general business update. The earnings webcast and the
Company’s latest investor presentation are available on the
Company’s website here:
https://investors.irisenergy.co/events-and-presentations
Canal Flats update (0.8 EH/s, 30MW
capacity) – BC, Canada
Canal Flats has been powered by 100% renewable
energy since inception5.
The project achieved average monthly operating
hashrate of 512 PH/s in February compared to 509 PH/s last
month.
Mackenzie update (2.5 EH/s, 80MW
capacity) – BC, Canada
Mackenzie has been powered by 100% renewable
energy since inception5.
The project achieved average monthly operating
hashrate of 798 PH/s in February compared to 654 PH/s last
month.
Prince George update (1.6 EH/s, 50MW
capacity) – BC, Canada
Prince George has been powered by 100% renewable
energy since inception5.
The project achieved average monthly operating
hashrate of 420 PH/s in February compared to 411 PH/s last
month.
Childress update (0.6 EH/s, 20MW
capacity) – Texas, USA
The first data center building (20MW) structure
is complete, and installation of mechanical equipment including
exhaust and recirculation fans has commenced. Internal data center
electrical fit out continued during the month, while energization
of the 600MW bulk substation (345kV) and commissioning of the 100MW
primary substation (138kV) is expected in the coming months.
The initial 20MW data center is nearing
completion in the coming months, with orders already placed for the
next 20MW of low voltage building transformers.
Community engagement
Employees from our Mackenzie site volunteered
during the Mackenzie ‘Strong Thank You to Front Line Workers’ event
as well as providing a donation of C$5,000. This local community
event, sponsored by the Mackenzie Chamber of Commerce, was a
special occasion to honor and thank all the health care workers,
emergency responders, and essential workers in Mackenzie who have
been working hard during and following the pandemic.
In Childress, the High School chemistry
department was one of our Community Grant recipients last year and
purchased science experiment supplies which are now being used by
the students this spring semester.
Future development sites
Development works continued across additional
sites in Canada, the USA and Asia-Pacific, which have the potential
to support up to an additional >1GW of aggregate power capacity
capable of powering growth beyond the Company’s 760MW of announced
power capacity.
Operating and financial
results
Daily average operating hashrate chart is
available at
https://www.globenewswire.com/NewsRoom/AttachmentNg/7aee7027-191b-4ced-bf3c-58d3ab16cc06
Technical commentary
The Company’s average operating hashrate was
1,730 PH/s in February (compared to 1,575 PH/s in January), with
the increase primarily attributable to the installation of
additional miners at Mackenzie. Despite the increase in average
operating hashrate, the number of Bitcoin mined decreased during
the period (156 vs. 172 in January) due to an increase in the
difficulty-implied global hashrate and three fewer days in the
month of February. Adjusted electricity costs per Bitcoin was
$10.6k in February (compared to $9.8k in January), with the
increase also driven by the increase in the difficulty-implied
global hashrate.
Operating |
Dec-22 |
Jan-23 |
Feb-23 |
Renewable energy usage (MW)6 |
35 |
49 |
54 |
Avg operating hashrate (PH/s) |
1,086 |
1,575 |
1,730 |
Financial (unaudited)2 |
Dec-22 |
Jan-23 |
Feb-23 |
Bitcoin mined |
123 |
172 |
156 |
Mining revenue (US$’000) |
2,089 |
3,464 |
3,539 |
Electricity costs (US$’000) |
1,505 |
1,931 |
1,869 |
Revenue per Bitcoin (US$) |
16,999 |
20,197 |
22,637 |
Electricity costs per Bitcoin (US$) |
12,244 (9,593 adj)3 |
11,260 (9,835 adj)3 |
11,956 (10,608 adj)3 |
Miner Shipping Schedule* |
Hardware |
Units |
EH/s (incremental) |
EH/s(cumulative) |
Operating |
S19j Pro7 |
18,113 |
1.7 |
1.7 |
Inventory – pending deployment or in transit |
S19j Pro8 |
40,683 |
4.0 |
5.7 |
Total** |
|
58,796 |
5.7 |
5.7 |
* Excludes ~3.6 EH/s of miners securing
equipment financing facilities with the Company’s two remaining SPV
borrowers in respect of which a receiver has been appointed. **
Total miners comprise 5.6 EH/s of S19j Pro miners plus an
additional ~0.1 EH/s of lower efficiency miners. As noted in the
table below, the Company’s existing data center capacity is
estimated to support ~5.5 EH/s of Bitmain S19j Pro miners.
Site |
Capacity (MW) |
Capacity (EH/s)9 |
Timing |
Status |
Canal Flats (BC, Canada) |
30 |
0.8 |
Complete |
Operating |
Mackenzie (BC, Canada) |
80 |
2.5 |
Complete |
Operating |
Prince George (BC, Canada) |
50 |
1.6 |
Complete |
Operating |
Total (BC, Canada) |
160 |
4.9 |
|
|
Childress (Texas, US) |
20 |
0.6 |
2023 |
Under construction10 |
Total (Canada & USA) |
180 |
5.5 |
|
|
About Iris Energy
Iris Energy is a sustainable Bitcoin mining
company that supports the decarbonization of energy markets and the
global Bitcoin network.
- 100% renewables:
Iris Energy targets markets with low-cost, under-utilized renewable
energy, and where the Company can support local communities
- Long-term security
over infrastructure, land and power supply: Iris Energy builds,
owns and operates its electrical infrastructure and proprietary
data centers, providing long-term security and operational control
over its assets
- Seasoned management
team: Iris Energy’s team has an impressive track record of success
across energy, infrastructure, renewables, finance, digital assets
and data centers with cumulative experience in delivering >$25bn
in energy and infrastructure projects globally
Forward-Looking Statements
This investor update includes “forward-looking
statements” within the meaning of the Private Securities Litigation
Reform Act of 1995. Forward-looking statements generally relate to
future events or Iris Energy’s future financial or operating
performance. For example, forward-looking statements include but
are not limited to the Company’s business strategy, expected
operational and financial results and expected increase in power
capacity and hashrate. In some cases, you can identify
forward-looking statements by terminology such as “anticipate,”
“believe,” “may,” “can,” “should,” “could,” “might,” “plan,”
“possible,” “project,” “strive,” “budget,” “forecast,” “expect,”
“intend,” “target”, “will,” “estimate,” “predict,” “potential,”
“continue,” “scheduled” or the negatives of these terms or
variations of them or similar terminology, but the absence of these
words does not mean that statement is not forward-looking. Such
forward-looking statements are subject to risks, uncertainties, and
other factors which could cause actual results to differ materially
from those expressed or implied by such forward looking statements.
In addition, any statements or information that refer to
expectations, beliefs, plans, projections, objectives, performance
or other characterizations of future events or circumstances,
including any underlying assumptions, are forward-looking.
These forward-looking statements are based on
management’s current expectations and beliefs. These statements are
neither promises nor guarantees, but involve known and unknown
risks, uncertainties and other important factors that may cause
Iris Energy’s actual results, performance or achievements to be
materially different from any future results, performance or
achievements expressed or implied by the forward-looking
statements, including, but not limited to: Iris Energy’s limited
operating history with operating losses; electricity outage,
limitation of electricity supply or increase in electricity costs,
as well as limitations on the availability of electrical supply for
Bitcoin mining due to restrictions imposed by governmental
authorities or otherwise; long term outage or limitation of the
internet connection at Iris Energy’s sites; any critical failure of
key electrical or data center equipment; serial defects or
underperformance with respect to Iris Energy’s equipment; failure
of suppliers to perform under the relevant supply contracts for
equipment that has already been procured which may delay Iris
Energy’s expansion plans; supply chain and logistics issues for
Iris Energy or Iris Energy’s suppliers; cancellation or withdrawal
of required operating and other permits and licenses; customary
risks in developing greenfield infrastructure projects; Iris
Energy’s evolving business model and strategy; Iris Energy’s
ability to successfully manage its growth; Iris Energy’s ability to
raise additional financing (whether because of the conditions of
the markets, Iris Energy’s financial condition or otherwise) on a
timely basis, or at all, which could adversely impact the Company’s
ability to meet its capital commitments (including payments due
under any hardware purchase contracts or debt financing
obligations) and the Company’s growth plans; the failure of Iris
Energy’s wholly-owned special purpose vehicles to make required
payments of principal and/or interest under their limited recourse
equipment financing arrangements when due or otherwise comply with
the terms thereof, as a result of which the lender thereunder has
declared the entire principal amount of each loan to be immediately
due and payable, and is taking steps to enforce the
indebtedness and its rights in the Bitcoin miners with respect to
certain of such loans and other assets securing such
loans, including appointing a receiver with respect to such
special purpose vehicles, which is expected to result in the
loss of the relevant Bitcoin miners securing such loans and has
materially reduced the Company’s operating capacity, and could also
lead to bankruptcy or liquidation of the relevant special purpose
vehicles, and materially and adversely impact the Company’s
business, operating expansion plans, financial condition, cash
flows and results of operations; the terms of any additional
financing or any refinancing, restructuring or modification to the
terms of any existing financing, which could be less favorable or
require Iris Energy to comply with more onerous covenants or
restrictions, any of which could restrict its business operations
and adversely impact its financial condition, cash flows and
results of operations; competition; Bitcoin prices, global hashrate
and the market value of Bitcoin miners, any of which could
adversely impact its financial condition, cash flows and results of
operations, as well as its ability to raise additional financing
and the ability of its wholly owned special purpose vehicles to
make required payments of principal and/or interest on their
equipment financing facilities; risks related to health pandemics
including those of COVID-19; changes in regulation of digital
assets; and other important factors discussed under the caption
“Risk Factors” in Iris Energy’s annual report on Form 20-F filed
with the SEC on September 13, 2022, and the Company’s report on
Form 6 K filed with the SEC on February 15, 2023, as such factors
may be updated from time to time in its other filings with the SEC,
accessible on the SEC’s website at www.sec.gov and the Investor
Relations section of Iris Energy’s website at
https://investors.irisenergy.co.
These and other important factors could cause
actual results to differ materially from those indicated by the
forward-looking statements made in this investor update. Any
forward-looking statement that Iris Energy makes in this investor
update speaks only as of the date of such statement. Except as
required by law, Iris Energy disclaims any obligation to update or
revise, or to publicly announce any update or revision to, any of
the forward-looking statements, whether as a result of new
information, future events or otherwise.
Preliminary Financial
Information
The preliminary financial information for the
month of February 2023 included in this investor update is not
subject to the same closing procedures as our unaudited quarterly
financial results and has not been reviewed by our independent
registered public accounting firm. The preliminary financial
information included in this investor update does not represent a
comprehensive statement of our financial results or financial
position and should not be viewed as a substitute for unaudited
financial statements prepared in accordance with International
Financial Reporting Standards. Accordingly, you should not place
undue reliance on the preliminary financial information included in
this investor update.
Contacts
MediaJon SnowballDomestique+61
477 946 068
InvestorsLincoln TanIris
Energy+61 407 423 395lincoln.tan@irisenergy.co
To keep updated on Iris Energy’s news releases and
SEC filings, please subscribe to email alerts at
https://investors.irisenergy.co/ir-resources/email-alerts.
_______________________
1 All timing references in this investor update are to calendar
quarters and calendar years, in each case unless otherwise
specified.2 Bitcoin and Bitcoin mined in this investor update are
presented in accordance with our revenue recognition policy which
is determined on a Bitcoin received basis (post deduction of mining
pool fees as applicable).3 The Company’s unadjusted electricity
costs per Bitcoin mined are currently elevated primarily due to
excess demand charges attributable to average unutilized power
capacity (due to termination of hosting arrangements in connection
with certain of the Group’s limited recourse equipment financing
facilities). The adjusted electricity costs per Bitcoin mined
excludes such excess demand charges (i.e., assumes unit electricity
costs of ~$0.046/kWh). As our operating capacity ramps up and
demand charges are amortized over a greater energy consumption, all
else being equal, we currently expect our electricity cost per
Bitcoin to normalize at approximately 90MW of energy usage.4
Reflects acceleration of outstanding loans under the Group's two
outstanding limited recourse equipment financing facilities, in
respect of which the relevant lender is pursuing enforcement
proceedings, and assumes foreclosure by the lender thereunder
against the collateral securing such facilities held by the
relevant SPV borrowers. See the Company's Reports on Form 6-K filed
on November 21, 2022 and February 15, 2023, and Registration
Statement on Form F-1, as amended, initially filed on September 23,
2022, for further information. Following such acceleration and
foreclosure, the Group would not have any indebtedness for borrowed
money outstanding.5 Currently approximately 97% directly from
renewable energy sources; approximately 3% from purchase of RECs.6
Comprises actual power usage for Canal Flats, Mackenzie and Prince
George.7 Includes mix of lower efficiency hardware, which is
estimated to represent less than 6% of the operating 1.7 EH/s.8
Includes mix of lower efficiency hardware, which is estimated to
represent less than 3% of non-operating miners in transit and/or
pending deployment.9 Reflects estimated hashrate capacity by site
assuming full utilization of available data center capacity with
Bitmain S19j Pro miners.10 Decisions around how much, and when,
data center capacity above an initial 20MW will be built at
Childress are being assessed.
Photos accompanying this announcement are available at:
https://www.globenewswire.com/NewsRoom/AttachmentNg/cd1d3374-11bc-4cc3-b82b-f1de2520fba0
https://www.globenewswire.com/NewsRoom/AttachmentNg/9fe6103f-172d-4cab-8df4-57870c7d317c
https://www.globenewswire.com/NewsRoom/AttachmentNg/9563acec-e619-4861-a217-89d465754825
Iris Energy (NASDAQ:IREN)
Gráfico Histórico do Ativo
De Mai 2023 até Jun 2023
Iris Energy (NASDAQ:IREN)
Gráfico Histórico do Ativo
De Jun 2022 até Jun 2023