Ero Copper Corp.
(TSX: ERO, NYSE:
ERO) (the “Company”) is pleased to provide an
update on the excellent progress being made at the Company's Tucumã
Project (the "Project").
Since commencing site works in 2022, all
engineering, procurement and construction activities for the
Project remain on schedule for first copper concentrate production
in H2 2024. Total direct Project capital expenditures remain in
line with current guidance of approximately $305 million. Project
development highlights include:
- Construction:
Physical construction of the Project is now 70% complete
- Significant
advancement in mine pre-stripping, with first sulphide ore on track
to be reached in early November
- All earthworks
now completed, including the water storage reservoir, site drainage
and run-of-mine stockpiles
- Over 15,000 cubic
meters of concrete poured (over 65% complete), concluding all major
foundation requirements for the Project
- Steel structure
pre-assembly and erection tracking ahead of schedule with
approximately 1,000 tonnes of steel already in place
- Key pieces of
processing equipment arrived on site with installations either
concluded or ongoing, including the primary crusher, ball mill,
secondary and tertiary crushers, vibrating screen decks and
flotation cells
- Main substation
installed on site, primary e-room commissioned, and approximately
16 kilometer power line construction tracking ahead of schedule;
tie-in to national grid power expected during Q4 2023
- Platework, piping
and electrical cabling all commenced ahead of schedule
- People
& Safety: Peak construction
workforce successfully mobilized on the Project
- Approximately
1,750 third-party contractors and employees working on site
- To date, there
have been no lost-time injuries on the Project, with approximately
two million hours of work completed since 2022
- Commissioning: The
Company remains on track to initiate the first phase of process
plant commissioning by year-end and commence operations in H2
2024
Commenting on the progress, David Strang, Chief
Executive Officer, said "First and foremost, I would like to
congratulate each and every one of the approximately 1,750 people
on site on the remarkable progress to date, and most importantly,
for their dedication in achieving nearly two million hours of work
without a lost time injury. With over 70% of the physical work
completed, critical pieces of infrastructure in place or nearing
completion, and main equipment installations progressing according
to plan, we are confident that a major inflection point for the
Project has been reached.
"As we continue to meet our construction
milestones, we are turning our attention on site to piping,
electrical and instrumentation installation - an exciting time for
any Project. We are focused on executing the first phase of the
commissioning schedule prior to year-end to ensure a successful
ramp-up and achievement of commercial production in the second half
of 2024."
Figure 1:
Advancement of pre-stripping with first sulphide ore expected
November 2023.
Figure 2: Installation of the
Ball Mill for the Project.
Figure 3: Flotation cells and
tailings thickener foundation.
Figure 4: Installation of the
primary crusher.
Figure 5: Completed water reservoir.
Figure 6: Electrical
substation prepared for final tie-in to the national grid.
Figure 7: Project laydown area
for pre-assembly and steel storage.
ABOUT ERO
COPPER CORP
Ero is a high-margin, high-growth, low
carbon-intensity copper producer with operations in Brazil and
corporate headquarters in Vancouver, B.C. The Company's primary
asset is a 99.6% interest in the Brazilian copper mining company,
Mineração Caraíba S.A. ("MCSA"), 100% owner of the Company's
Caraíba Operations (formerly known as the MCSA Mining Complex),
which are located in the Curaçá Valley, Bahia State, Brazil and
include the Pilar and Vermelhos underground mines and the Surubim
open pit mine, and the Tucumã Project (formerly known as Boa
Esperança), an IOCG-type copper project currently under
construction in Pará State, Brazil. The Company also owns 97.6% of
NX Gold S.A. ("NX Gold") which owns the Xavantina Operations
(formerly known as the NX Gold Mine), comprised of an operating
gold and silver mine located in Mato Grosso, Brazil. Additional
information on the Company and its operations, including technical
reports on the Caraíba Operations, Xavantina Operations and Tucumã
Project, can be found on the Company's website (www.erocopper.com),
on SEDAR (www.sedar.com), and on EDGAR (www.sec.gov). The Company’s
shares are publicly traded on the Toronto Stock Exchange and the
New York Stock Exchange under the symbol “ERO”.
FOR MORE
INFORMATION, PLEASE
CONTACT
Courtney Lynn, SVP, Corporate Development, Investor Relations
& Sustainability (604) 335-7504info@erocopper.com
CAUTION REGARDING FORWARD LOOKING INFORMATION
AND STATEMENTS
This press release contains “forward-looking
statements” within the meaning of the United States Private
Securities Litigation Reform Act of 1995 and “forward-looking
information” within the meaning of applicable Canadian securities
legislation (collectively, “forward-looking statements”).
Forward-looking statements include statements that use
forward-looking terminology such as “may”, “could”, “would”,
“will”, “should”, “intend”, “target”, “plan”, “expect”, “budget”,
“estimate”, “forecast”, “schedule”, “anticipate”, “believe”,
“continue”, “potential”, “view” or the negative or grammatical
variation thereof or other variations thereof or comparable
terminology. Forward-looking statements may include, but are not
limited to, statements with respect to achieving first sulphide ore
and the expected timing of reaching first sulphide ore,
installation of main equipment, including tie-in of power line to
national grid, commissioning and first concentration production;
the estimated Project capital to be spent; and any other statement
that may predict, forecast, indicate or imply future plans,
intentions, levels of activity, results, performance or
achievements.
Forward-looking statements are not a guarantee
of future performance. There can be no assurance that
forward-looking statements will prove to be accurate, as actual
results and future events could differ materially from those
anticipated in such statements. Forward-looking statements involve
statements about the future and are inherently uncertain, and the
Company’s actual results, achievements or other future events or
conditions may differ materially from those reflected in the
forward-looking statements due to a variety of risks, uncertainties
and other factors, including, without limitation, those referred to
herein and in the AIF under the heading “Risk Factors”.
The Company’s forward-looking statements are
based on the assumptions, beliefs, expectations and opinions of
management on the date the statements are made, many of which may
be difficult to predict and beyond the Company’s control. In
connection with the forward-looking statements contained in this
press release and in the AIF, the Company has made certain
assumptions about, among other things: continued effectiveness of
the measures taken by the Company to mitigate the possible impact
of COVID-19 on its workforce and operations; favourable equity and
debt capital markets; the ability to raise any necessary additional
capital on reasonable terms to advance the production, development
and exploration of the Company’s properties and assets; future
prices of copper, gold and other metal prices; the timing and
results of exploration and drilling programs; the accuracy of any
mineral reserve and mineral resource estimates; the geology of the
Caraíba Operations, the Xavantina Operations and the Tucumã Project
being as described in the respective technical report for each
property; production costs; the accuracy of budgeted exploration,
development and construction costs and expenditures; the price of
other commodities such as fuel; future currency exchange rates and
interest rates; operating conditions being favourable such that the
Company is able to operate in a safe, efficient and effective
manner; work force continuing to remain healthy in the face of
prevailing epidemics, pandemics or other health risks (including
COVID-19), political and regulatory stability; the receipt of
governmental, regulatory and third party approvals, licenses and
permits on favourable terms; obtaining required renewals for
existing approvals, licenses and permits on favourable terms;
requirements under applicable laws; sustained labour stability;
stability in financial and capital goods markets; availability of
equipment; positive relations with local groups and the Company’s
ability to meet its obligations under its agreements with such
groups; and satisfying the terms and conditions of the Company’s
current loan arrangements. Although the Company believes that the
assumptions inherent in forward-looking statements are reasonable
as of the date of this press release, these assumptions are subject
to significant business, social, economic, political, regulatory,
competitive and other risks and uncertainties, contingencies and
other factors that could cause actual actions, events, conditions,
results, performance or achievements to be materially different
from those projected in the forward-looking statements. The Company
cautions that the foregoing list of assumptions is not exhaustive.
Other events or circumstances could cause actual results to differ
materially from those estimated or projected and expressed in, or
implied by, the forward-looking statements contained in this press
release. There can be no assurance that forward-looking statements
will prove to be accurate, as actual results and future events
could differ materially from those anticipated in such statements.
Accordingly, readers should not place undue reliance on
forward-looking statements.
Forward-looking statements contained herein are
made as of the date of this press release and the Company disclaims
any obligation to update or revise any forward-looking statement,
whether as a result of new information, future events or results or
otherwise, except as and to the extent required by applicable
securities laws.
CAUTIONARY NOTES REGARDING MINERAL RESOURCE AND
MINERAL RESERVE ESTIMATES
Unless otherwise indicated, all reserve and
resource estimates included in this press release and the documents
incorporated by reference herein have been prepared in accordance
with National Instrument 43-101, Standards of Disclosure for
Mineral Projects (“NI 43-101") and the Canadian Institute of
Mining, Metallurgy and Petroleum (the “CIM”) — CIM Definition
Standards on Mineral Resources and Mineral Reserves, adopted by the
CIM Council, as amended (the “CIM Standards”). NI 43-101 is a rule
developed by the Canadian Securities Administrators that
establishes standards for all public disclosure an issuer makes of
scientific and technical information concerning mineral projects.
Canadian standards, including NI 43-101, differ significantly from
the requirements of the United States Securities and Exchange
Commission (the “SEC”), and reserve and resource information
included herein may not be comparable to similar information
disclosed by U.S. companies. In particular, and without limiting
the generality of the foregoing, this press release and the
documents incorporated by reference herein use the terms “measured
resources,” “indicated resources” and “inferred resources” as
defined in accordance with NI 43-101 and the CIM Standards.
Further to recent amendments, mineral property
disclosure requirements in the United States (the “U.S. Rules”) are
governed by subpart 1300 of Regulation S-K of the U.S. Securities
Act of 1933, as amended (the “U.S. Securities Act”) which differ
from the CIM Standards. As a foreign private issuer that is
eligible to file reports with the SEC pursuant to the
multi-jurisdictional disclosure system (the “MJDS”), Ero is not
required to provide disclosure on its mineral properties under the
U.S. Rules and will continue to provide disclosure under NI 43-101
and the CIM Standards. If Ero ceases to be a foreign private issuer
or loses its eligibility to file its annual report on Form 40-F
pursuant to the MJDS, then Ero will be subject to the U.S. Rules,
which differ from the requirements of NI 43-101 and the CIM
Standards.
Pursuant to the new U.S. Rules, the SEC
recognizes estimates of “measured mineral resources”, “indicated
mineral resources” and “inferred mineral resources.” In addition,
the definitions of “proven mineral reserves” and “probable mineral
reserves” under the U.S. Rules are now “substantially similar” to
the corresponding standards under NI 43-101. Mineralization
described using these terms has a greater amount of uncertainty as
to its existence and feasibility than mineralization that has been
characterized as reserves. Accordingly, U.S. investors are
cautioned not to assume that any measured mineral resources,
indicated mineral resources, or inferred mineral resources that Ero
reports are or will be economically or legally mineable. Further,
“inferred mineral resources” have a greater amount of uncertainty
as to their existence and as to whether they can be mined legally
or economically. Under Canadian securities laws, estimates of
“inferred mineral resources” may not form the basis of feasibility
or pre-feasibility studies, except in rare cases. While the above
terms under the U.S. Rules are “substantially similar” to the
standards under NI 43-101 and CIM Standards, there are differences
in the definitions under the U.S. Rules and CIM Standards.
Accordingly, there is no assurance any mineral reserves or mineral
resources that Ero may report as “proven mineral reserves”,
“probable mineral reserves”, “measured mineral resources”,
“indicated mineral resources” and “inferred mineral resources”
under NI 43-101 would be the same had Ero prepared the reserve or
resource estimates under the standards adopted under the U.S.
Rules.
Photos accompanying this announcement are available at
https://www.globenewswire.com/NewsRoom/AttachmentNg/bf0a1d58-d5bf-4ff3-bef4-ad657fb9c8c4
https://www.globenewswire.com/NewsRoom/AttachmentNg/d06db9f7-a60e-4afb-b1ca-3fa2ea2b3ec1
https://www.globenewswire.com/NewsRoom/AttachmentNg/6743d8e1-6e8d-480e-81a9-2a82a7142dee
https://www.globenewswire.com/NewsRoom/AttachmentNg/3d6a5699-fac7-4d6c-bc49-45ee13cc1b3f
https://www.globenewswire.com/NewsRoom/AttachmentNg/d58d259e-2a0b-4c01-9002-448c4e60e219
https://www.globenewswire.com/NewsRoom/AttachmentNg/de1a8a0f-41dd-4442-8307-f29b6555e723
https://www.globenewswire.com/NewsRoom/AttachmentNg/5b843529-65da-4973-9d73-edc39645bf15
Ero Copper (TSX:ERO)
Gráfico Histórico do Ativo
De Ago 2024 até Set 2024
Ero Copper (TSX:ERO)
Gráfico Histórico do Ativo
De Set 2023 até Set 2024