Chaarat Gold Holdings Ltd (AIM:CGH)  increases the strike length in multiple 
zones of  gold mineralisation drilled in the Main Zone 2400 Project Area at the 
Chaarat Property

Road Town, Tortola, British Virgin Islands (15th January 2008).

Chaarat is pleased to announce further encouraging drilling results from 8 drill
holes in the M2400 Project Area of the Main Zone at its 100% held, 604 sq km,
Chaarat Licence Area in western Kyrgyzstan. All 8 of the holes drilled,
comprising 1628 metres of drilling, intersected significant gold mineralisation
and were all drilled during the recently completed 2007 programme. This drilling
was part of a broader 53 drill hole (10,200 metre) drilling programme, completed
on the Licence Area in 2007 (see press release 6 December 2007).

The Main Zone is one of three zones in the Chaarat Licence Area, in which gold
mineralisation is developed in multiple shears (Projects) and comprises at
least 4 kilometres of strike. The recently completed exploration has extended
the strike length and down dip extent of the mineralisation within the M2400
Project Area.

Highlights

Drilling results show good continuity in the Main Zone deposit
Higher grades and thicker intersections encountered at depth
Additional Hangingwall mineralisation intersected
Apparent strike extended to approximately 680m
Confirmation that depth potential could be extended by at least 200m


Drill hole 98            4.63 metres at 4.05 g/t Au

Drill hole 99            8,51 metres at 3.55 g/t Au

Drill hole 101          21.83 metres at 5.66 g/t Au including 11.73m at 8.65 g/t

Drill hole 105           9.60 metres at 3.74 g/t Au including  3.84m at 6.93 g/t

Bulldozer Cut 762       57.00 metres at 4.66 g/t Au

CEO Dekel Golan says "We are very pleased with these results, as the M2400
Project Area, although only drilled to a down-dip depth of 150 metres, is an
important target to increase the resources on the Chaarat Property. The fact
that these results indicate an increase in the strike length and down dip
extensions to the mineralisation and that we continue to drill multiple zones of
mineralisation, many with wide or high grade intersections, is very encouraging.

Table 1: Main Zone Drilling Results, 2007

  Project     Section       DH       From (m)     To (m)   length (m)   True width (m)    Au g/t     Ag g/t
   M2400       2380        DH98         106       113.5        7.5           4.63          4.05        9
   M2400       2380        DH98        122.5       124         1.5           0.9           3.83        3
   M2400       2380        DH98        143.5      149.5         6            2.95          1.58        3
   M2400       2370        DH98        167.5       169         1.5           1.37          3.08        14
   M2400       2350        DH99         120        129          9            8.51          3.55        5
   M2400       2330        DH99        172.5      178.5         6            5.74          1.75        2
   M2400       2350        DH100       94.5         96         1.5           1.12          3.26        1
   M2400       2170        DH101       82.5        111        33.5          21.83          1.67        1
   M2400       2170      including     82.5        91.5         9            5.86          3.3         1
   M2400       2200        DH101       136.5      169.5        33            21.5          5.66        1
   M2400       2200      including     139.5      157.5        18           11.73          8.21        1
   M2400       2620        DH105        45          60         15            9.6           3.74        6
   M2400       2620      including      54          60          6            3.84          6.93        11
   M2400       2620        DH105        72         76.5        4.5           2.88          2.59        1
   M2400       2160        DH124        91        113.5       22.5           8.7           2.06        1
   M2400       2160      including     104.5      113.5         9            3.48          3.02        1
   M2400       2150        DH124        154       158.5        4.5            2            2.88        1
   M2400       2150        DH124       164.5       169         4.5            2            3.38        1
   M2400       2280      DH125bis*      210        216          6            4.91           3          1
   M2400       2270      DH125bis*      249        255          6            4.75          2.06        1
   M2400       2150        DH127       88.5        91.5         3            2.45          4.57        1
   M2400       2160        DH127       127.5      130.5         3            2.75          2.7         1
   M2400       2160        DH127       139.5      151.5        12            11.3          2.93        1
   M2400       2160      including     139.5      142.5         3            2.36          5.56        1
   M2400       2160      including     148.5      151.5         3            2.79          4.24        1
   M2400       2170        DH127        159        161          3            1.9           2.66        1

*  DH 125 bis failed to reach target depth and provides only a partial result of the zone.

QA/QC PROCEDURES

Sampling Methodology and Quality Control

All samples are sent to a laboratory in Kyrgyzstan, the Central Scientific
Research Laboratory, JSC Kara Balta, (CSRL), accredited by the UK Accreditation
Service, for sample preparation and initial assays. All samples with gold above
1 g/t are then submitted to Genalysis, Australia, a NATA ISO/IEC 17025
accredited laboratory for analysis by fire assay. Only results received from
Genalysis are included in the Mineral Resource database and the intercept
summaries in this press release. Comparison of assays from the two laboratories
shows a small bias with Genalysis reporting higher values but with an acceptable
HARD value variance on the averages. With the 817 samples submitted to
Genalysis, 71 were internationally recognised reference materials and of these
only one value was marginally outside the accepted range. It is concluded that
the Genalysis assays are of sufficient quality to be included in the Resource
database although no up-dated Resource has been estimated at this stage.

The Main Zone

Mineralisation in the Main Zone is hosted in a shear zone, which is up to 15
metres wide, and which extends for at least 4 kilometres on strike, as an
anatomising strike slip fault system, within the Ordovician age Chaarat
Formation (siltstones and sandstones). The mineralised zones dip at 70-80
degrees to the NW. The gold is associated with sulphides, sericitic alteration
and minor quartz veinlets. Prospecting, to date, within the Main Zone  has been
focused on four Project Areas -  the M2400, M3000, M3900 and M4000 Project
Areas, and the mineralisation has been traced over a cumulative strike length of
3000 metres, out of the total 4km strike length of the Main Zone.

Based on drilling completed in 2006, a JORC compliant (indicated and inferred)
resource containing 923,500 oz at a grade of 4.29 g/t Au had been delineated in
the Main Zone Project Areas to depths varying between 80 metres to 250m metres
down the dip from outcrop. The mineralisation remains open down dip all along
the Main Zone. Surface exploration undertaken this year discovered additional
mineralisation along strike in the now designated M4600 and M5000 Project Areas
(See attached maps).

http://www.rns-pdf.londonstockexchange.com/rns/7623l_-2008-1-14.pdf

M2400 Project Area

Resources of 2.06 M at 4.5g/t Au (JORC compliant indicated and inferred) were
delineated in the mineralised zone in the M2400 Project Area, based on the 2006
drilling data. The average true width of the mineralised zone was measured at
7.5 metres.

During 2007, a total of 8 drill holes (1628.1metres) were completed on the M2400
Project Area, bringing the total number of holes drilled to 16. Of the recently
completed holes, four were infill drilling, which reduced the drill spacing to
40 metres in some parts of the mineralised zone, and four tested the down dip
extension to the mineralisation. In addition, the surface expression of the
mineralisation was exposed in a bulldozer cut, DC762, along strike on the
northern part of the Project Area, with a channel sampled width of 57 metres at
a grade of 4.66 g/t Au.  This increased the strike length of the mineralisation
from 570 metres to 620 metres.

Of significance, 7 of the 8 drill holes reported here intersected multiple zones
of mineralisation, which in the case of DH 98 and DH 127, both intersected four
such zones within the shear zone. The additional mineralised intersections are
developed both in the hanging wall and the footwall of the main mineralised zone
and have the potential to add to the resource in this Project Area. In
particular, the significant intersection in DH 101 of wide, high grade
mineralisation (21.83 metres at a grade of 5.66 g/t Au) in the hanging wall of
the main mineralised zone represents an attractive additional exploration target
for the forthcoming spring drilling programme.

Furthermore, all the drilling completed to date on this Project Area has
intersected mineralisation to a depth, down dip below outcrop, of only 150
metres and it remains open both along strike and down dip. Furthermore,
elsewhere in the Main Zone, drilling has established that the mineralisation
extends for an additional 200 metres below from the corresponding current lower
limit of drilling in the M2400 Project Area. Drilling of both the down dip and
strike extensions to the mineralisation will also be a focus of the proposed
spring drilling programme.

The drilling results reported here will be incorporated into the resource
estimate, which will be revised by March 2008. The Company continues to process
drilling and sampling results from another seven Project Areas, in the Main,
Contact and Tulkubash Zones, as well as from regional targets, as they are
received. These results will be reported, in batches, in the coming weeks.

Competent Person

The Competent Person with overall responsibility for this press release is
Anthony Martin, PrSciNat, MGSZ, MAuS IMM, PhD who is an employee of SRK
(Zimbabwe) (Pvt) Limited.  Dr Anthony Martin is an exploration geologist with 35
years experience in the resource industry and has been responsible for the
reviewing of exploration programmes on various properties internationally during
the past five years and the Chaarat project since August 2005; he has made four
site visits since that time.

About the Chaarat Gold Project

The Chaarat project is situated within the Middle Tien Shan Mountains of
Kyrgyzstan which form part of the Tien Shan gold belt.  At the completion of the
2006 exploration season, a Mineral Resource of 1.87Moz Au (JORC compliant in the
Indicated and Inferred categories) had been delineated. The Company's
exploration programme is aimed at increasing the confidence levels in this
Resource through infill drilling and increasing the resource through down-dip
and along-strike extension drilling.  In addition the company intends to explore
the remaining gold occurrences outside of those currently drilled in the central
6km of the 40km strike length within the Chaarat Licence Area.

About Chaarat Gold Holdings or the Company

Chaarat Gold Holdings is an exploration company founded for the purpose of
developing its sole asset, being the Chaarat License Area. Chaarat was admitted
to AIM on 8 November 2007.

Chaarat has 71.9 million outstanding shares and approximately $12.8million in
cash allowing it to comfortably continue its exploration program for 2008 and
beyond.

Disclaimer

This press release includes forward-looking statements. Such forward-looking
statements involve known and unknown risks, uncertainties and other important
factors beyond Chaarat's control that would cause the actual results,
performance or achievements of Chaarat to be materially different from future
results, performance or achievements expressed or implied by such forward-
looking statements. Such forward-looking statements are based on numerous
assumptions regarding Chaarat's present and future business strategies and the
environment in which Chaarat will operate in the future. Any forward-looking
statements speak only as at the date of this document. Chaarat expressly
disclaims any obligation or undertaking to disseminate any updates or revisions
to any forward-looking statements contained herein to reflect any change in
Chaarat's expectations with regard thereto or any change in events, conditions
or circumstances on which any such statements are based. As a result of these
factors, the events described in the forward-looking statements in this press
release may not occur either partially or at all.

Enquiries:

Chaarat Gold Holdings Ltd                             Tel:  +44 (0) 20 7499 2612
Dekel Golan  - Dekel@chaarat.com
Terry Cross   -  terry@caserve.co.uk

Canaccord Adams Limited                               Tel:  +44 (0) 20 7050 6500
Mike Jones
Robin Birchall



END








                      This information is provided by RNS
            The company news service from the London Stock Exchange
END

DRLGUUUGGUPRPUC

Chaarat Gold (LSE:CGH)
Gráfico Histórico do Ativo
De Jun 2024 até Jul 2024 Click aqui para mais gráficos Chaarat Gold.
Chaarat Gold (LSE:CGH)
Gráfico Histórico do Ativo
De Jul 2023 até Jul 2024 Click aqui para mais gráficos Chaarat Gold.