THIS
ANNOUNCEMENT CONTAINS INSIDE INFORMATION
Pensana
Plc ("Pensana" or the "Company")
Technical
Due Diligence Report on Longonjo
Pensana
(LSE:PRE) is pleased to advise that the technical due diligence
report on the Longonjo rare earth project in Angola (the Project or Longonjo) has been
reported by The Mineral Corporation (TMC) to ABSA Capital (ABSA) as
the Mandated Lead Arranger for potential debt funding of the
Project.
A
summary of TMC's key findings:
The
Project is located approximately 320km east of the Port of Lobito
and envisages the open pit mining and processing of near surface
Rare Earth Elements (REE) bearing carbonatite ores to produce a
mixed REE carbonate (MREC) concentrate which will then be marketed
commercially.
The holder
of the Mineral and Mining Rights over the Longonjo mining licence
area is the Angolan registered company Ozango Minerais S.A.
(Ozango), which is 84% owned by Portugal domiciled subsidiaries of Pensana.
The balance of Ozango is held by the Angolan Sovereign Wealth Fund
and two Angolan partners.
Longonjo
will comprise an open pit mine to recover near surface REE, which
will then be processed via concentration and downstream refining to
produce a commercially saleable Mixed Rare Earth Carbonate (MREC)
concentrate for export via the Port of Lobito to third-party
offtakers for the purpose of ultimately producing
Neodymium/Praseodymium (NdPr) feed into the renewable energy and
electric vehicle markets.
A nominal
plant feed of 0.8Mtpa has been specified at a TREO feed grade of
4.12% and an NdPrO feed grade of 0.9%. The stockpiling and blending
strategy critical to achieving stable and consistent concentrator
performance and product has been identified and included in the
mining and processing flowsheets. The plant design is nominally
based on a dry concentrate feed of approximately 59ktpa, to produce
a nominal MREC dry product of 19.6ktpa (15ktpa normal operating
conditions).
Whilst TMC
is of the opinion that ramp-up to achieve design recoveries will be
challenging, and the ongoing operational control of the processing
plants will be critical to maintaining product quality and
recovery, TMC notes no fatal flaws in terms of the revised bankable
feasibility study (BFS) review and no material technical
divergences from the level of study required for bank funding
approval.
TMC noted
the capital estimate provided is extremely detailed and based on
bills of quantities and tendered prices with a capital base date of
Q4 2023. An accuracy assessment was also carried out, which
confirms the level of accuracy complies with that required by a BFS
standard. TMC is of the opinion that sustaining capital may be
slightly understated however this does not present a material risk
to the Project.
Capital
Cost Breakdown
Concentrator
Plant
|
US$37 766
993
|
Plant
Common Areas
|
US$14 687
930
|
TSF
|
US$7 157
201
|
Recovery
Plant
|
US$75 472
541
|
Plant
Infrastructure
|
US$15 568
988
|
Project
Infrastructure
|
US$123
386
|
Mine
Infrastructure
|
US$9 707
348
|
Environmental
|
US$4 538
590
|
Security
|
US$1 767
680
|
Site
Infrastructure
|
US$7 001
150
|
Indirect
Costs
|
US$22 640
254
|
Contingency
|
US$20 100
933
|
Total
Project Capital Expenditure
|
US$216 532
994
|
The
capital estimate was derived from the various currencies relating
to the goods and services costs in the country of origin and
adjusted for the relevant exchange rates: US$ South African Rand
ZAR 18.5, European Euro EUR 0.9, Australian Dollar AUD 1.5 and Angolan
Kwanza AOA 830.
TMC notes
the level of detail provided in the detailed capital estimate
consisting of in excess of 18,000 line items, the methodology
undertaken to produce the capital estimate and the basis of
estimate being predominantly based on bills of quantity, tendered
rates and budget quotations.
Operating
Cost Estimates have been updated based on the revised Project scope
and also brought to a consistent cost base date of Q4 2023. TMC has
reviewed all of the operating cost centre data and concurs that the
operating cost estimates as provided meet the accuracy levels
associated with a BFS, however it is noted that the retender for
the mining contract scheduled for late 2024 will impact on overall
Project economics and in all likelihood trigger the requirement for
a revision of the mining optimisation plan.
TMC notes
that the financial model as received is detailed in all modelled
inputs and results in free cash flow levels which would be likely
to support a funding decision. TMC reiterates the sensitivity of
the Project economics to the forecast rare earth oxide prices and
recommends that the imminent offtake agreements and pricing
structures should be included in any funding agreement as
Conditions Precedent. Once these are available the Project
financial model should be updated, and the economics revised. The
Project economics are most sensitive to projected market dynamics
and the resulting product pricing projections, which in turn
present the most material risk to Project economics.
Earthworks
and civils contractors established site in November 2022. Servitude bush clearing and pylon
installations to the borehole pumps, contractors camp, main camp
and water treatment plant were in progress at the time of the site
visit at the end of February 2023.
Overall, the level of detail design of the infrastructure is
commensurate with the requirements of the BFS and TMC is of the
opinion that the infrastructure design is appropriate and fit for
purpose to support the mining and processing operations.
TMC is of
the opinion that the level of work undertaken for the project
schedule and plan of execution is commensurate with the
requirements of a BFS and the work undertaken is comprehensive and
will be the basis for a potential successful project
execution.
Extensive
work has been undertaken in the areas of social and community
engagement. TMC supports the programmes and costs which have been
allocated to the various social initiatives, however notes that the
Relocation Action Plan still requires careful monitoring and
management to ensure successful implementation, minimising
community grievances. Ozango's engagements and initiatives now
comply with the expectations associated with a BFS level of study
and in some instances exceed expected levels.
TMC notes
that all legislative aspects of Human Resources management have
been addressed adequately, however it does recommend that
remuneration levels are reviewed prior to the commencement of
recruitment, as the budgeted levels may mitigate against the
procurement of top level individuals, particularly in the senior
technical expatriate roles. The BFS meets expected levels of detail
in terms of all HR, operational readiness and occupational health
and safety aspects. It is noted that specific operational readiness
planning is only expected at the next stage of the
Project.
Tim George CEO commented:
"We
are very grateful to Russel Heins
and the team at The Mineral Corporation team for the diligent and
extremely thorough review of all aspects of the Longonjo project
undertaken in their role as lead Technical Advisor to ABSA as the
Mandated Lead Arranger and we are pleased with the positive
recommendations.
The
review was based on the re-engineered, reduced capital cost of the
project for financing purposes following our review in
Q2
of
2023. A huge amount of work has gone into the capital cost estimate
which as noted by Russell and the team is based on very detailed
estimates and we are pleased that despite the current inflationary
and cost pressures the estimate has been confirmed around
US$217 million, which includes
US$20 million in
contingency.
As
previously announced, once the Longonjo operations are operational
and fully commissioned it is our intention to expand production to
around 40,000 tonnes of MREC per annum which will require an
additional capital cost of around US$100
million which is expected to be incurred around year three
of the initial operations.
Whilst
this technical review has been underway, we have been working
closely with our financiers ABSA, FSDEA and others and we expect to
be in a position to announce the financing arrangements
shortly."
About
The Mineral Corporation
The
Mineral Corporation (TMC) was established in Johannesburg, South Africa in 1997 and is home
to a well-informed, globally-focused corporate and technical
advisory team of mining sector professionals. TMC have expertise in
mineral exploration, geology, mining engineering and development,
mineral processing, mining infrastructure, ESG, statutory
compliance, mineral asset valuation and techno-economic
modelling.
TMC
understand that exploration and mining can be high risk industries
and are confident that their skills can be applied to identify,
resolve and minimise their clients exposure to such risk, thereby
creating or preserving value.
TMC cover
all minerals, including precious metals, base metals, noble and
refractory metals, energy minerals (coal and uranium), mineral
sands, precious and semi-precious stones, rare earth elements and
industrial minerals.
Since
inception, TMC has created or preserved many billions in various
currencies (including rand, dollar, pounds) on behalf of clients.
Their business model is founded on the qualification and
quantification of mineral investment opportunities. TMC assemble
teams of expert multi-disciplinary consultants who collectively
craft an integrated business model to evaluate clients'
enterprises. TMC's group of professionals offers knowledge from six
continents but enjoys a particular passion for Africa. In many circumstances, TMC's
imaginative, but always realistic, examination of mineral projects
offers distinctive solutions to the complex alternatives that
challenge investors.
TMC also
provide bespoke institutional research on the mining
industry.
The
information contained within this announcement is considered by the
Company to constitute inside information as stipulated under the
Market Abuse Regulations (EU) No.596/2014. Upon the publication of
this announcement via a Regulatory Information Service, this inside
information will be considered to be in the public domain. The
person responsible for arranging for the release of this
announcement on behalf of the Company is
Paul Atherley,
Chairman.
-
ENDS -
For
further information, please contact:
Shareholder/analyst
enquiries:
Pensana
Plc
Paul Atherley, Chairman IR@pensana.co.uk
Tim George, Chief Executive Officer
Rob Kaplan, Chief Financial Officer