GeoResources, Inc., (NASDAQ:GEOI), today provided an operations update as well as guidance on 2011 and 2012 capital expenditure and production levels.

EAGLE FORD

The Company recently successfully completed drilling its fourth Eagle Ford well, the Peebles #1H (39.8% W.I.) in its operated project area in Fayette County, Texas. This well was drilled to a measured depth of 15,100 feet, with a 5,000 foot lateral in 27 days at a cost of approximately $3.0 million. Through the application of optimal practices, GeoResources was able to significantly reduce the drilling time and cost of this well. The Company believes it can continue to realize improved drilling, completion and operational efficiencies which will positively impact costs in this area.

The Company is currently drilling the Arnim “A” #1H well (50.0% W.I.) with a second dedicated rig expected to begin drilling the Ring “A” 1H well (45.7% W.I.) within a couple of weeks, both of which are located in Fayette County, Texas. After drilling the Arnim “A” #1H, the rig will spud the Arnim “A” #2H (50.0% W.I.), which will be the second well in the Arnim “A” unit drilled from a common pad. These three wells will be completed along with the Peebles #1H well late in the fourth quarter with one frac crew working continuously to complete these wells in succession. After the Arnim “A” #2H, we expect to spud an additional one or two wells in our Eagle Ford project area by year end, which will bring our total 2011 Eagle Ford wells spud to eight or nine gross wells (3.8 to 4.3 net wells).

GeoResources currently plans to add two additional rigs to the Eagle Ford project area during 2012. Based on a three to four rig schedule the Company expects to spud between 21 and 24 gross wells in its Eagle Ford project area in 2012 (8.7 to 9.6 net wells).

The table below provides an update on the production results to date from the Company’s first three Eagle Ford wells.

Eagle Ford - Wells Summary   Lateral   # of     Average Daily Production (Boe/d)(1) Length Frac GEOI 30   60   90 (feet) Stages W.I. Days Days Days Flatonia E Unit 1H 3,200 10 50.0% 391 288 247 Flatonia E Unit 2H 4,800 14 50.0% 465 414 359 Black Jack Springs #1H 5,900 16 43.5% 369 302 -  

(1) Based on GEOI internal production data and excludes non-producing days and initial "flowback" days when well was cleaning up and producing frac fluid.

 

GeoResources has continued to add leases to its Eagle Ford project area throughout 2011 and its current net acreage totals approximately 25,000.

In addition to the Eagle Ford, we believe our acreage in Gonzales and Fayette counties has Austin Chalk potential, which lies immediately above the Eagle Ford. A re-entry, located within the boundaries of our southern Fayette County acreage block, was completed in February 2011 by a third party operator. That well, the Cherry Oil Unit 1H, averaged 402 boe/d in the first full month of production after the re-entry and has cumulative production of over 46,000 BO and 41,000 Mcf. We are currently participating with that same operator in a Chalk well, located about three miles to the southwest, being the Tilicek #1H well, where we have a 14.1% W.I. The Tilicek well reached total measured depth of 13,529 on September 19, 2011 and should be on production very soon. This well had considerable oil shows during drilling and also had a 30’ gas flare. We currently have one additional Austin Chalk well planned for Fayette County in 2012; however, we may accelerate our Chalk drilling in and around our Eagle Ford acreage block with continued good drilling results.

BAKKEN SHALE OPERATED

GeoResources has drilled and completed six gross Middle Bakken wells in its Williams County, North Dakota and eastern Montana project areas to date. In Williams County, the Company’s most recent producer, the Rasmussen 1-21-16H (30.9% W.I.), was completed in late September. This well experienced a 24 hour initial production rate of 816 bo/d, 113 mcf/d (835 boe/d) with 1,740 bw/d on a 34/64” choke with 445 psi of flowing tubing pressure, while still recovering frac significant fluid. One other recently completed well in Williams County, the Rasmussen 1-25-36H (43.9% W.I.) is currently flowing back after being frac’d. The Olson 1-21-16H well (31.4% W.I.) in eastern Montana and two additional Williams County wells, the State 1-36-25H (35.8% W.I.) and the Peterson Trust 1-5-8H (38.5% W.I.), have been drilled and are currently scheduled to be frac’d in October and November.

As previously announced, the Company added a second drilling rig to this area in July. The Company is currently drilling the Doris 1-28-33H (39.2% W.I) and the Poeckes 1-32-29H (40.0% W.I.). Including the two wells currently drilling, GeoResources plans to spud four or five additional gross wells by year end with its two drilling rigs which will bring its total wells spud within its operated Bakken project area to 10 or 11 in 2011.

GeoResources has recently entered into oil and gas gathering arrangements in its Williams County project with a third party gathering and processing company. This infrastructure should be completed by the end of the second quarter of 2012 and will allow for improved operational efficiencies as well as additional market outlets for the Company’s oil and gas production from its operated Bakken project.

The Company currently expects to add two rigs in 2012. Based on a three to four rig schedule the Company expects to spud between 23 and 26 gross wells in 2012 in our Bakken operated project areas of Williams County and eastern Montana (7.7 to 8.2 net wells).

The table below provides an overview of production results to date from the wells that have been on production for 30 days or more in our operated Bakken shale project.

Bakken Operated - Well Summary   Spacing   # of     Average Daily Production (Boe/d)(1) Units Frac GEOI 30   60   90 (Acres) Stages W.I. Days Days Days Carlson 1-11H 640 18 47.5% 235 236 224 Siirtola 1-28-33H 1,280 30 41.4% 341 266 254 Anderson 1-24-14H 1,280 29 35.0% 363 302 279 Muller 1-21-16H 1,280 38 31.1% 250 - -  

(1) Based on GEOI internal production data and excludes non-producing days and initial "flowback" days when well was cleaning up and producing frac fluid.

 

The Company’s Muller 1-21-16H well has been online for 53 days and on rod pump for the last 31 days at an average rate of 253 boe/d.

GeoResources currently has approximately 25,000 net acres in Williams County, North Dakota in its operated Bakken Shale project area and 10,000 net acres in eastern Montana.

BAKKEN SHALE NON-OPERATED

In its non-operated program located in Mountrail and adjacent counties in North Dakota, GeoResources has participated in over 100 wells to date with Slawson Exploration Company, Inc. (“Slawson”), with a 100% success rate. In addition, the Company owns minor working interests in numerous other wells operated by other industry partners within the Bakken/Three Forks play primarily in Mountrail, Williams and McKenzie counties. Slawson continues to operate four to five drilling rigs within the Company’s area of mutual interest and the Company continues to seek to acquire additional acreage and well interests in this project area.

GeoResources has also participated in five non-operated Bakken wells to date in eastern Montana. One of these wells, the Swindle 16-9 #1H (9.3% W.I.) is operated by Brigham Exploration while the other four wells are operated by Slawson in the Rip Rap prospect. The Swindle well and two of the Slawson wells, being the Renegade #1-10H (24.1% W.I.) and the Battalion #1-3H (25.0% W.I.), are currently on production while the Squadron 1-14-15H (15.6% W.I.) is waiting on completion and the Citadel #1-11-2H (23.6% W.I.) is currently being drilled.

The following table updates prior operations releases regarding GeoResources’ non-operated activities in the area. Generally, the Company reports only the wells operated by Slawson, but may include others where the wells or the Company’s interests are meaningful. GeoResources does not report many of its wells in which they have very small working interests. The table below lists activity during the indicated quarters for such wells, with subsequent production data, where available. This table includes oil production only.

                          WELL NAME  

SPACINGUNIT(ACRES)

 

WORKINGINTEREST

 

IP (BOPD)(1) (24-HRRATE)

 

1st 30 DAYAVG(BOPD)

 

1st 60 DAYAVG(BOPD)

 

CURRENTSTATUS

           

4th Qtr. 2010

Prowler #2-16H 640 5.86% 725 452 408 Producing Bandit #2-29H 640 7.35% 959 449 382 Producing Payara #2-21H 640 6.28% 1,069 452 434 Producing Genesis #2-13H 640 8.51% 1,297 738 602 Producing Loon Federal #1-24-25H 1,280 4.84% 1,402 958 1058 Producing Mamba #2-20H 640 8.38% 815 481 417 Producing Mustang #1-22H 640 4.75% 738 479 401 Producing Nightcrawler #2-17H 640 6.67% 1,068 890 678 Producing Hunter #2-8-17H 1,280 6.08% Completing  

1st Qtr. 2011

Alamo #2-19-18H 1,280 8.59% 1,286 1,037 930 Producing Ambush #1-31-30H 1,280 12.66% Completing Diamondback #2-21H 640 2.79% 1,032 665 556 Producing Jughead Federal #2-26H 640 8.88% 1,184 730 644 Producing Orca Federal #1-23-26H 1,280 4.84% 812 583 Producing Cruiser #2-16-9H 1,280 10.80% 1,115 793 710 Producing Dagger #1-10H 640 12.52% Completing Wizard #2-35H 640 14.40% 867 651 578 Producing  

2nd Qtr. 2011

Cannonball Federal #2-27-34H 1,280 3.50% WOC Mooka #2-28-20H 1,280 9.94% Location Neptune #2-15H 640 5.68% 828 Producing Skybolt #2-24H 640 5.27% Location Athena #1-36H 640 8.00% Drilling Jaguar #2-32H 640 13.50% 1,318 871 697 Producing Muskrat Federal #2-28-33H 1,280 6.51% 890 Producing Sauger Federal #2-22H 640 5.65% Drilling  

3rd Qtr. 2011

Cannonball Federal #3-27-34H 1,280 3.50% Completing Zephyr Federal #2-36H 640 11.27% Location Sauger Federal #3-22H 640 5.65% Drilling Stallion #2-1-12H 1,280 11.70% WOC Probe #1-19-30HMB 1,280 3.64% Drilling Howitzer #2-25H 640 14.40% WOC Mustang #2-22H 640 4.71% WOC

(1) As used in the above table, “IP (BOPD) (24 hr. rate)” is defined as the peak oil volume produced on a daily basis through permanent production facilities that occur within the first few days of initial production from the well.

OTHER PROJECT AREAS

In the Giddings Field, GeoResources completed and began producing the West Cannon Unit #1H Austin Chalk well in late August (43.4% W.I.). This well has been a strong producer, averaging 696 bo/d and 2,036 mcf/d (1,035 boe/d) in its first 31 days of production. This well continues to produce at strong rates with good wellhead pressure as of the date of this release.

In its Quarantine Bay project area in Plaquemines Parish, Louisiana, the SL 195 QQ #365 well (22.0% W.I.) was brought online in mid-September and is currently producing approximately 1,009 bo/d and 1,211 mcf/d (1,211 boe/d) with a flowing tubing pressure of 5,600 psi. As previously announced this well has over 105’ of pay primarily from two separate sands. The well is producing from one of the two sands and therefore a future acceleration well may be added to deplete both reservoirs in a timely manner.

UPDATED CAPITAL BUDGET

GeoResources continues to refine its capital budget for the remainder of 2011 and 2012. The Company currently expects its 2011 capital budget to be approximately $120 million, which is modestly higher than the previously disclosed forecast of $114 million. The 2012 capital expenditure budget will depend on how quickly the Company expands to three or four rigs in both the Eagle Ford and the Bakken. The current expectation is for the 2012 capital budget to be between approximately $188 million and $223 million. The table below illustrates the components of the 2012 budget.

Estimated 2012 Capital Budget           ($ in millions)   Low(1)   High(2)   Notes Bakken Operated Projects (Williams County and Montana) $61 $73 23 to 26 gross wells (~31% W.I.) Bakken Non-Operated Project (Primarily Mountrail County) 23 23 42 gross wells with Slawson (8% W.I.); 12 with others (1% W.I.) Eagle Ford Project (Fayette and Gonzales Counties) 74 86 21 to 24 gross wells (~40% W.I.) Other Drilling 11 11 Williston Basin conventional, St. Martinville and Austin Chalk drilling Acreage and Seismic 15 25 Primarily Eagle Ford and Bakken Infrastructure and Other 4 6 Saltwater disposal and other infrastructure and equipment Total Expected 2012 Capital Expenditures $188 $223  

(1) Assumes GEOI grows to 3 drilling rigs in both the Bakken and Eagle Ford in 2012 with gross well costs of $8.0 million on GEOI operated Bakken wells and $8.5 million on GEOI operated Eagle Ford wells.

(2) Assumes GEOI grows to 4 drilling rigs in both the Bakken and Eagle Ford by late 2012 with gross well costs of $8.5 million on GEOI operated Bakken wells and $9.0 million on GEOI operated Eagle Ford wells.

NOTE: The data above is based on conservative well cost assumptions. The Compay's goal is to reduce well costsbelow the amounts indicated above. Management believes that Bakken well costs of $7.5 million and Eagle Ford well costs of $8.0 million are attainable under current conditions.

PRODUCTION GUIDANCE

GeoResources expects production for the full year ended December 31, 2011 to be between 5,000 and 5,500 boe/d, being 61% to 65% oil. Production for 2012 is expected to range from 6,500 to 7,500 boe/d, being 70% to 75% oil depending largely on the timing of new rig additions and the pace of drilling activity.

MANAGEMENT COMMENTS

Frank A. Lodzinski, President and CEO of GeoResources, Inc. commented, “We are pleased with the early production rates of the first Rasmussen well which further demonstrates the economic viability of our Williams County acreage position. We continue to adjust our drilling and completion methods in the Bakken to drive down costs as commodity prices have softened in recent months while service costs have remained high. Accordingly, we expect our next several wells to be lower cost wells utilizing sliding sleeves and sand fracs as opposed to the more elaborate 38 stage plug and perf ceramic proppant wells just completed. We are focused on drilling economic wells, reducing drilling and completion days and rapidly converting our lease position to held by production status. It should be noted that our latest Bakken well, the State 1-36-25H, was drilled to total depth in just 20 days. We are also searching for a third drilling rig in the Bakken which we expect to move on location and begin drilling by the end of the first quarter of 2012. We are continuing our leasing efforts in addition to pursuing joint ventures and other activities in order to expand our acreage position in select areas of the Bakken.”

“In the Eagle Ford, the second drilling rig should be on location in a couple of weeks and we are beginning the development phase of this project. We are pleased with the reduced drilling time and cost we were able to achieve on our most recent well, the Peebles 1H, and we expect to continue to drive drilling and completion costs down as we add drilling rigs and refine our drilling and completion techniques. As we continue to establish drilling units and capture acreage, we will drill adjacent units and also transition to “pad drilling”, with the Arnim wells. We anticipate completing these wells in batches which should have a positive impact on overall well costs. In addition to Eagle Ford potential, we believe our acreage in Gonzales and Fayette counties has considerable oil-rich reserve and production potential from the Austin Chalk formation which lies immediately above the Eagle Ford. We have a great deal of Austin Chalk experience and with continued successful drilling results in this area the Chalk could evolve into a separate drilling project in 2012.”

“As for our other operating areas, we are pleased with the early production results of the West Cannon Austin Chalk well in Grimes County. This is an oily Austin Chalk well that is performing better than we anticipated. Over the first 31 days of production from this well, production has actually increased with continued strong wellhead pressures. We are also happy to report that the Quarantine Bay well is online and producing continuously. Based on comparable well histories, we expect this well to be a strong performer for several years. We plan to drill a handful of select wells outside of our core Eagle Ford and Bakken projects in 2012 and beyond, but our primary focus will continue to be on the Eagle Ford and Bakken.”

“Finally, our management and technical teams have a good historical track record of reducing well and operating costs. We are focused on driving costs down in this environment of reduced commodity prices and high service and equipment costs. Although we have no material near term lease expirations issues, due to our operating strengths and strong balance sheet and cash flows, we are continuing with our plans to add drilling rigs in our focus areas in 2012. However, we will continue evaluate our programs considering commodity prices, service costs and availability in addition to well economics as we proceed.”

ABOUT GEORESOURCES, INC.

GeoResources, Inc. is an independent oil and gas company engaged in the development and acquisition of oil and gas reserves through an active and diversified program that includes the acquisition, drilling and development of undeveloped leases, purchases of reserves and exploration activities, currently focused in the Southwest, Gulf Coast, and the Williston Basin. For more information, visit our website at www.georesourcesinc.com.

CAUTIONARY NOTE REGARDING FORWARD LOOKING STATEMENTS

This release includes forward-looking statements within the meaning of the Private Securities Litigation Reform Act of 1995, which are subject to risks and uncertainties. The forward-looking statements, which address GeoResources’ expected business and financial performance, among other matters, contain words such as “believe,” “expect,” “estimate,” “anticipate,” “optimistic,” “intend,” “plan,” “aim,” “will,” “may,” “should,” “could,” “would,” “likely,” “continue,” and similar expressions. Examples of forward-looking statements, include, but are not limited to: (i) changes in production volumes and prices and future production and development costs, (ii) projections of capital expenditures, revenues, income or loss, earnings or loss per share, capital structure, and other financial items, (iii) statements of our plans and objectives of our management or board of directors including those relating to planned development of our oil and gas properties, (iv) statements of future economic performance and (v) statements of assumptions underlying such statements. Readers are cautioned not to place undue reliance on these forward-looking statements, which speak only as of the date on which they are made. GeoResources undertakes no obligation to update or revise any forward-looking statements.

A further description of these uncertainties and other risks can be found in the GeoResources Annual Report on Form 10-K for the year ended December 31, 2010 and other reports filed by GeoResources with the U.S. Securities and Exchange Commission.

Georesources (NASDAQ:GEOI)
Gráfico Histórico do Ativo
De Jun 2024 até Jul 2024 Click aqui para mais gráficos Georesources.
Georesources (NASDAQ:GEOI)
Gráfico Histórico do Ativo
De Jul 2023 até Jul 2024 Click aqui para mais gráficos Georesources.