company said March 26. 
                              The entire plant had been 
                              off-line since March 14. 
 
Marathon Catlettsburg 226.0   Turnaround maintenance at un-     n/a 
         KY                   specified units starts March 
                              10. No restart estimate. 
ROCKY MOUNTAIN 
 
Western  Bloomfield,   16.8   Co. announced plans Nov. 9 
         NM                   to idle plant and shift 
                              production to Gallup plant. 
 
Suncor   Commerce      93.0   No. 1 Crude unit will shut for    Mar 22 
         City, CO             planned maintenance on Mar 6; 
                              restart Mar 22. 
                              Cryo Unit will shut for planned   Apr 4 
                              maintnenance Mar 20; restart 
                              April 4. 
                              Planned work at reformer unit     Fall 
                              deferred to Fall 2010 from Feb    2010 
                              28 start date. 
 
Tesoro   Salt Lake     58.0   Major turnaround work will 
         City, Utah           begin in 1Q 2010, the Co. said 
                              on Feb 3. 
 
Tesoro   Mandan, N.D.  60.0   Planned turnaround will           2Q 
                              begin 2Q 2010, the Co. said 
                              on Feb 3. 
 
WEST COAST 
 
Exxon    Torrance, CA 150.0   FCCU, alkylation unit shut        Apr 10 
                              March 20-21 as part of turn- 
                              around maintenance that be- 
                              gan March 1 at several units. 
                              The work is expected to last 
                              for 40 days, trade sources said 
                              on Feb. 11. 
 
BP      Carson, CA    265.0   Planned flaring activity  on 
                              March 29-April 20 and, Co. reported 
                              in filings. 
 
                      Planned flaring activity reported 
                              for April 4-9, an April 1 filing said. 
 
 
 
Tesoro   Golden Eagle 166.0   Turnaround work began in early    n/a 
         Martinez,            Dec at FCCU and alkylation 
         CA                   unit, the Co. said on Feb 3. 
                              Restart timing unclear. 
                              Other major turnaround mainte-    2011 
                              nance deferred to 2011 from 
                              late 2009, the Co. said Feb 3. 
 
Tesoro   Wilmington   100.0   Company reports planned           March 
                              flaring to start March 27         31 
                              and ending March 31. 
 
 
Tesoro   Oahu, HI      94.0   Planned turnaround work will 
         Kapolei              begin 3Q, 2010, the Co. said 
                              on Feb 3. 
 
                              nance deferred to 2011 from 
                              late 2009, the Co. said Feb 3. 
 
Tesoro   Wilmington   100.0   Company reports planned           March 
                              flaring to start March 27         31 
                              and ending March 31. 
 
 
Tesoro   Oahu, HI      94.0   Planned turnaround work will 
         Kapolei              begin 3Q, 2010, the Co. said 
                              on Feb 3. 
 
 
Harvest Energy (NYSE:HTE)
Gráfico Histórico do Ativo
De Mai 2024 até Jun 2024 Click aqui para mais gráficos Harvest Energy.
Harvest Energy (NYSE:HTE)
Gráfico Histórico do Ativo
De Jun 2023 até Jun 2024 Click aqui para mais gráficos Harvest Energy.