Centamin is pleased to announce preliminary production results
from its Sukari Gold Mine ("Sukari") in Egypt for the quarter ended
31 March 2014. Total gold production for the quarter was
74,241 ounces, a 14% decrease on the corresponding quarter in 2013
and 19% lower than Q4 2013. Although gold production was affected
by a temporary reduction in the underground average grade, the
first quarter demonstrated record levels of material movement from
the underground mine and process plant throughput and all areas of
the operation have provided a solid foundation for the year
ahead. Production guidance for 2014 remains unchanged at
420,000 ounces gold.
Open pit total material movement continued well from the
previous quarter with a small increase of 1% to 9,749kt. A
decrease in open pit ore production of 26% on Q4 2013 to 2,325kt
reflected a focus on waste stripping activities in line with the
mine plan. The run of mine ore stockpile balance decreased by 216kt
to 1,540kt at the end of the period.
Record quarterly throughput at the process plant was 1,486kt, a
6% increase on the prior year period and a 6% increase on Q4 2013,
exceeding the nameplate annualised rate of 5 million tonnes for the
fifth successive quarter with continued high levels of productivity
and availability. The Stage 4 commissioning process will
progressively lift overall plant throughput and hence gold
production levels through the remainder of the year.
The primary challenge faced during the quarter was from poor
mining fleet availability within the high grade stoping areas of
the underground mine. Whilst the operation delivered a record 206kt
of ore, up 18% on Q4 2013, this limited ability to remotely mine
the high-grade stopes reduced the average mined grade to below
planned levels and thus restricted the contribution to overall
production. These problems with equipment availability were
rectified late in the quarter.
|
|
|
|
|
Q1 2014 (estimate) |
Q4 2013 |
Q1 2013 |
Total Material Movement - Open Pit (kt) |
9,749 |
9,642 |
10,550 |
Open Pit Ore Production (kt) |
2,325 |
3,161 |
2,133 |
Underground Ore Production (kt) |
206 |
174 |
119 |
Process Plant Throughput (kt) |
1,486 |
1,400 |
1,402 |
Process Plant Productivity (tph) |
745 |
698 |
689 |
Gold Produced (oz) |
74,241 |
91,546 |
87,016 |
Josef El-Raghy, Chairman of Centamin, commented:
"Consistently high levels of productivity have again been
achieved with the process plant at Sukari, with minimal impact from
the Stage 4 commissioning activities. Although underground
performance has impacted Q1 we are pleased to confirm commissioning
of Stage 4 is proceeding as planned, with Sukari achieving a major
milestone towards the end of Q1 as first ore was fed through the
new circuit. We expect plant throughput, and hence quarterly
production rates, to increase through the rest of the year as
commissioning continues. Our forecast 2014 production and the
continued ramp up towards Sukari's long-term target of
450,000-500,000 ounces per annum remain on track."
For more information please contact: Centamin plc Josef
El-Raghy, Chairman Andy Davidson, Head of Business Development and
Investor Relations (andy.davidson@centamin.je) +44 (0) 1534 828708
Buchanan Bobby Morse Gordon Poole Gabriella Clinkard + 44 (0) 20
7466 5000
Centamin (TSX:CEE)
Gráfico Histórico do Ativo
De Fev 2025 até Mar 2025
Centamin (TSX:CEE)
Gráfico Histórico do Ativo
De Mar 2024 até Mar 2025