Endeavour Silver Provides 2018 Production and
Cost Guidance,
Targeting 20% Increase in
Production to 5.8-6.4 Million oz Silver and
58-64,000 oz Gold for
10.2-11.2 Million oz Silver Equivalent
___________________________________________________________________________
Vancouver, Canada -- January 25, 2018 -- InvestorsHub
NewsWire -- Endeavour Silver
Corp. (TSX:
EDR,
NYSE: EXK) issued today the 2018 production and cost
guidance for its three operating mines and one development project
in Mexico: the Guanaceví mine in Durango state, the Bolañitos and
El Cubo mines in Guanajuato state, and the El Compas mine, now
under development in Zacatecas state.
In 2018, silver equivalent production is expected to increase by
20% compared to 2017. Endeavour forecasts higher silver and
gold production at all three existing mines as well as initial
production from the new fourth mine at El Compas by the end of
March, with commercial production scheduled for the end of
July.
With the higher forecast production, cash costs and all-in
sustaining costs are expected to decline in 2018 compared to
2017. The 2018 capital budget will increase from 2017 due to
the development of the new El Compas mine, and two new high grade
orebodies at Guanacevi, whereas the exploration budget will
decrease as the focus shifts towards more development activities
this year.
2018 Production
Guidance
Silver production is anticipated to be in the range of 5.8-6.4
million ounces (oz) and gold production is expected be in the
58,000-64,000 oz range. Silver equivalent production is forecast to
be 10.2-11.2 million oz using a 75:1 silver:gold ratio , as shown
in the table below.
Mine |
Ag
(M oz) |
Au
(K oz) |
Ag
Eq (M oz) |
Tonnes/Day (tpd) |
Guanacevi |
2.2-2.5 |
5.0-5.5 |
2.6-2.9 |
900-1,050 |
Bolanitos |
1.0-1.1 |
23.5-25.5 |
2.8-3.0 |
1,100-1,250 |
El
Cubo |
2.5-2.7 |
22.5-24.5 |
4.2-4.5 |
1,300-1,450 |
El
Compas |
0.1-0.1 |
7.0-8.5 |
0.6-0.8 |
0-250(1) |
Total |
5.8-6.4 |
58.0-64.0 |
10.2-11.2 |
3,300-4,000 |
- El Compas is scheduled to achieve
commercial production by the end of July 2018
Bradford Cooke, Endeavour CEO, commented, “We are looking forward
to a much better year, with higher production and lower costs in
2018, owing to improved operating performance at each of the three
existing mines and the development of our fourth mine into
commercial production.
“Guanacevi should continue to improve this year as the mine
completes its recovery from the operating issues that held it back
last year. Bolanitos and El Cubo should both see higher
production from steady throughput, higher silver grades and
improving metal recoveries.
“We look forward to bringing Endeavour’s fourth mine into
commercial production in the third quarter as the El Compas
construction program nears completion. Over the next few months, we
anticipate a number of potential material developments to catalyze
our future growth, including:
- Update of the El Compas project construction and optimized mine
plan and economics
- Completion of construction and commissioning of production at
El Compas
- Release of an optimized pre-feasibility study for
Terronera
- Receipt of the final government environmental permits for
Terronera
- Continued exploration results from Parral and other
projects
- Additional acquisitions to expand our development project
pipeline
“All in all, 2018 should be a rewarding year for Endeavour Silver
shareholders, outlining our commitment to ensure both the
sustainability of our current operations while investing in our
development pipeline to fuel future growth.”
Operating Mines
At Guanaceví, mine performance should continue to improve over the
course of 2018. After resolving several operating issues in 2017,
management recently launched a seven month mine-site training
program aimed at significantly improving workforce productivity and
cutting costs. Plant throughput should rise from the 900 tpd in Q4,
2017 to 1,050 tpd in Q4, 2018 and average 1,000 tpd in 2018. Two
new orebodies at Milache and SCS are being developed to commence
production before year-end in order to reduce the onus on Porvenir
Norte and Santa Cruz and increase operational flexibility.
At Bolañitos, steady mine production and plant throughput are
forecast at 1,200 tpd similar to 2017, primarily from the
LL-Asunción and Plateros vein orebodies plus some historic mine
fill. Silver grades are expected to be higher than 2017 but gold
grades will be lower. An improvement in metal recoveries is
expected due to modifications in the flotation circuit implemented
late last year.
At El Cubo, mine production and plant throughput will also continue
steady at 1,400 tpd from the V-Asunción, Dolores, and San Nicolas
veins. Ore grades should increase considerably as a higher grade
area of the V-Asuncion orebody is scheduled for mining this year.
Metal recoveries should rise incrementally after modifying the
flotation circuit late last year.
Operating Costs
Cash costs, net of gold by-product credits, are expected to be
$6.00-$7.00 per oz of silver produced in 2018. Consolidated cash
costs on a co-product basis are anticipated to be $10.00-$11.00 per
oz silver and $750-$800 per oz gold.
All-in sustaining costs (AISC), net of gold by-product credits, in
accordance with the World Gold Council standard, are estimated to
be $15.00-$16.00 per oz of silver produced in 2018 reflecting new
investments in exploration and development programs. When non-cash
items such as stock-based compensation are excluded, AISC are
forecast to be in the $14.50-$15.50 range. Excluding the investment
to develop the SCS and Milache ore bodies into production at
Guanacevi, AISC would decrease by $2.00 per oz to $13.00-$14.00 per
oz.
On a co-product basis, AISC are anticipated to be $15.50-$16.00 per
oz silver and $1,150-$1,200 per oz gold. Direct operating costs are
estimated to be in the range of $80-$85 per tonne.
Management has assumed a $17 per oz silver price, $1,275 per oz
gold price, and 19:1 Mexican peso per US dollar exchange rate for
its 2018 cost forecasts.
2018 Capital Budget
In 2018, Endeavour plans to invest $48.4 million on capital
projects including $41.1 million in sustaining capital at the four
operating mines and $7.3 million in growth capital at the two
development projects. At current metal prices, the sustaining
capital investments will be covered by operating cash flow.
Growth capital of $7.2 million is budgeted to complete the
construction of the El Compas project to commercial production.
At Guanacevi, a capital budget of $25.9 million is planned for
2018, including sustaining capital of $10.3 million to develop 9.2
kilometres (km) of mine access at the North Porvenir and Santa Cruz
mines. A total of $13.3 million is budgeted to development
the new ore bodies. An additional $2.3 million will be invested on
site infrastructure, including plant and office equipment and
building improvements.
At Bolañitos, a capital budget of $2.6 million is planned for 2018,
including $0.5 million on mine development to access resources in
LL-Asunción and Plateros veins, plus mineralized fill from historic
stopes not included in resources. An additional $2.1 million is
planned for supporting site infrastructure, including mobile
equipment, plant equipment, office equipment and building
improvements.
At El Cubo, a capital budget of $12.6 million is planned for 2018,
including 5.9 km of mine development for $7.6 million, $2.0 million
for refurbishment of underground mobile equipment, $1.8 million to
increase the capacity of the tailings facility and an additional
$1.2 million for site infrastructure, including vehicles, plant
equipment, office equipment and building improvements.
In 2017, Endeavour received government environmental permits to
build the Terronera mine and plant but the Company still awaits
receipt of the dumps and tailings permits. Upon receipt of
these final permits, and assuming a positive production decision
and appropriate debt financing, the 2018 growth capital budget will
be amended accordingly.
Mine |
Mine Development |
Other Capital |
Sustaining Capital |
Growth Capital |
Total
Capital |
Guanaceví |
$23.6
million |
$2.3
million |
$25.9
million |
- |
$25.9
million |
Bolañitos |
$0.5
million |
$2.1
million |
$ 2.6
million |
- |
$2.6
million |
El
Cubo |
$7.6
million |
$5.0
million |
$12.6
million |
- |
$12.6
million |
El
Compas |
- |
- |
- |
$7.2
million |
$7.2
million |
Corporate |
- |
- |
- |
$0.1
million |
$0.1
million |
Total |
$29.0
million |
$6.6
million |
$41.1
million |
$7.3
million |
$48.4
million |
Exploration Budget
In 2018, the Company plans to drill 44,000 metres (m) and spend
$11.1 million on brownfields and greenfields exploration,
development engineering, and land payments across its portfolio of
properties. At the three existing mines, 17,000 m of core drilling
are planned at a cost of $2.8 million. At the exploration and
development projects, expenditures of $8.3 million are planned to
drill 27,300 m, to advance engineering studies and meet property
holding obligations.
At El Compas, 6,600 m will be drilled for $1.0 m primarily on the
Calicanto concessions. The 2018 drilling will further test the new
zones of high grade mineralization within the Misie-Karla-Karla HW
and Calicanto veins discovered in 2017.
At Terronera, $1.7 million will be spent to complete an updated
pre-feasibility study and a 6,600 m drill program. The 2018
drilling will focus on extending mineralization in the Terronera
vein to the southeast of the current resource, plus testing other
veins.
At Parral, $2.2 million will be spent on drilling 12,000 m to
extend historic and new resource areas and complete a preliminary
economic assessment.
In Chile, the Company will conduct a 3,000 m drill program on one
property exploring for bulk tonnage silver-lead-zinc manto
mineralization.
Project |
2018
Activity |
|
Drill Metres |
Expenditures (millions) |
Guanaceví |
Drilling |
|
6,600 |
$0.8 |
Bolanitos |
Drilling |
|
5,400 |
$1.0 |
El
Cubo |
Drilling |
|
5,000 |
$1.0 |
El
Compas |
Drilling |
|
6,600 |
$1.0 |
Terronera |
Drilling/Update PFS |
|
5,400 |
$1.2 |
Parral |
Drilling/PEA |
|
12,000 |
$2.2 |
Guadalupe y Calvo |
Mapping |
|
- |
$0.2 |
Chile |
Drilling |
|
3,000 |
$1.3 |
Mexico |
Holding Costs/Land Payments |
|
- |
$2.4 |
Total |
|
|
44,000 |
$11.1 |
About Endeavour –
Endeavour
Silver Corp. is a mid-tier precious metals mining company with
three high-grade, underground, silvergold mines in Mexico. In 2018,
the Company is forecasting a 20% production increase to 10.2-11.2
million oz silver equivalent. Endeavour has a compelling pipeline
of silver-gold exploration and development projects and plans to
build new mines over the next three years to fuel its next stage of
organic growth. Our mission is to become a premier senior producer
in the silver mining sector.
Contact
Information - For more information, please contact:
Galina Meleger, Director Investor Relations
Toll free: (877) 685-9775
Tel: (604) 640-4804
Fax: (604) 685-9744
Email: gmeleger@edrsilver.com
Website: www.edrsilver.com
Cautionary Note Regarding Forward-Looking
Statements
This news release contains
“forward-looking statements” within the meaning of the United
States private securities litigation reform act of 1995 and
“forward-looking information” within the meaning of applicable
Canadian securities legislation. Such forwardlooking statements and
information herein include but are not limited to statements
regarding Endeavour’s anticipated performance in 2018 and the
timing and results of various future activities. The Company does
not intend to, and does not assume any obligation to update such
forward-looking statements or information, other than as required
by applicable law.
Forward-looking statements or
information involve known and unknown risks, uncertainties and
other factors that may cause the actual results, level of activity,
performance or achievements of Endeavour and its operations to be
materially different from those expressed or implied by such
statements. Such factors include, among others, changes in national
and local governments, legislation, taxation, controls, regulations
and political or economic developments in Canada and Mexico;
operating or technical difficulties in mineral exploration,
development and mining activities; risks and hazards of mineral
exploration, development and mining; the speculative nature of
mineral exploration and development, risks in obtaining necessary
licenses and permits, and challenges to the Company’s title to
properties; as well as those factors described in the section “risk
factors” contained in the Company’s most recent form 40F/Annual
Information Form filed with the S.E.C. and Canadian securities
regulatory authorities.
Forward-looking statements are
based on assumptions management believes to be reasonable,
including but not limited to: the continued operation of the
Company’s mining operations, no material adverse change in the
market price of commodities, mining operations will operate and the
mining products will be completed in accordance with management’s
expectations and achieve their stated production outcomes, and such
other assumptions and factors as set out herein. Although the
Company has attempted to identify important factors that could
cause actual results to differ materially from those contained in
forward-looking statements or information, there may be other
factors that cause results to be materially different from those
anticipated, described, estimated, assessed or intended. There can
be no assurance that any forward-looking statements or information
will prove to be accurate as actual results and future events could
differ materially from those anticipated in such statements or
information. Accordingly, readers should not place undue reliance
on forward-looking statements or information.
Endeavour Silver (TSX:EDR)
Gráfico Histórico do Ativo
De Nov 2024 até Dez 2024
Endeavour Silver (TSX:EDR)
Gráfico Histórico do Ativo
De Dez 2023 até Dez 2024