Project Remains Fully Funded, Within Guidance
for Initial Capital Expenditure, and on Schedule
VANCOUVER, BC, Oct. 24,
2023 /CNW/ - Artemis Gold Inc. (TSXV: ARTG) ("Artemis
Gold" or the "Company") provides an update on Q3 construction
progress at the Blackwater Mine in central British Columbia. The project remains fully
funded, within the guidance for initial capital expenditure, and on
schedule for first gold pour in H2 2024.
At September 30, 2023, overall
construction was 45% complete, and approximately C$280 million of the guided initial capital
expenditure of C$730 to C$750 million had been spent. The lag between the
spend and percentage of completion is as planned and consistent
with a typical project S-curve.
Artemis Gold Chairman and CEO Steven
Dean commented: "Our workforce and construction activity at
Blackwater returned to 100% following the wildfire events in early
Q3. We remain focused on a disciplined approach to development and
remain on track for the first gold pour in H2 2024."
Construction Update
Earthworks continued in priority infrastructure areas, with
approximately 505 hectares logged and cleared. Over 90% of access
roads needed for Phase 1 construction are now operable.
Construction of the site water management facilities, including the
water management pond and Davidson
Creek diversion, is well advanced.
Total major works man-hours worked up to September 30, 2023, were more than 440,000
man-hours with a zero LTIFR1 and an AIFR2 of
138.97.
Plant Site
Process plant construction progressed well on a number of
fronts, including the mill building foundation preparation,
reagents building, ball mill pedestals, carbon in leach (CIL)
tanks, and the primary, secondary, and tertiary crushers
structures, as well as the reclaim tunnel civil works. Hydro
testing of the first CIL tank has been completed.
Construction of the run-of-mine (ROM) wall surpassed 75%
complete at the end of September 2023
and is scheduled to be completed by the end of October 2023, with the ROM dump slab civil works
scheduled to begin shortly thereafter.
Heavy Equipment
The construction fleet has been expanded to include 60- and
100-tonne rigid frame haul trucks and 150-tonne excavators,
providing more material movement capability to key areas. Initial
deliveries of the owner mining fleet are well advanced, including
400-tonne hydraulic backhoe excavators and three 240-tonne rigid
frame haul trucks which have arrived and are in various stages of
assembly. Fleet assembly is expected to be sufficiently advanced by
year end in preparation for pre-stripping and earthworks support in
2024. The remainder of the fleet to support operations will arrive
predominately in the first half of 2024.
Engineering and Procurement
At the end of September 2023, the
Sedgman EPC contract works passed 61% complete overall, with
engineering and design over 95% complete. Procurement is 96%
complete and progressing toward the conclusion of package awards.
Key mechanical equipment packages are in various stages of
delivery, including the primary, secondary and tertiary crushers
and associated dry screens, while the wet plant vibrating screens,
ADR plant, gravity concentrator(s) and intensive leach reactor are
all on site. The major ball mill components, including the shell
and head segments, are in transit and expected to arrive in
October. The electrical machinery control centre fabrication is
complete and will undergo factory testing in early Q4 2023.
Contracts are being finalized for explosives supply, mine fleet
tire supply and the assay laboratory, while proposals for the
oxygen plant and water treatment plants are in the final stages of
being evaluated. Right-of-way clearing and construction of the
135km 225kV transmission line is scheduled to begin in Q4 2023.
Personnel
The Company's staffing numbers at the Blackwater Mine surpassed
250 employees in Q3 2023, with approximately 20% female and 30%
identifying as Indigenous. Over 50% of the development team is from
the local region and over 80% are B.C. residents. The total
workforce at the Blackwater Mine, including staff and contractors,
was more than 500 at the end of September.
Funding
At September 30, 2023, Artemis
Gold had estimated remaining Phase 1 capital expenditures of
$450 to $470
million. At the same date, the committed sources of funding
totalled C$560 million,
comprising:
- cash and cash equivalents of C$73
million;
- remaining drawdowns from streaming agreements of US$45.2 million (approximately C$62 million);
- a project loan facility of C$385
million (including up to C$25
million of capitalized interest), and
- a cost overrun facility of C$40
million.
Hedging
Artemis Gold has continued to execute a modest hedging program
to secure the returns on capital invested in the early years of
operations and further de-risk servicing of the Company's project
loan facility during the pay-back period. To date, the Company has
entered into gold forward sales agreements to deliver 190,000
ounces of gold bullion between March
2025 and December 2027 at a
weighted average sales price of C$2,851 per gold ounce, which is more than 40%
higher than the gold price assumption in the September 2021 Feasibility Study.
Engineering Study
With Phase 1 fully funded and 45% complete at the end of
September 2023, a study to evaluate
the benefits of advancing the Phase 2 expansion earlier than
contemplated in the September 2021
Feasibility Study is progressing well. The results of this study
are expected to be released in early 2024.
Artemis Gold President and COO Jeremy
Langford commented: "The return and ramp-up to full
construction activities following the B.C wildfire event in Q3 2023
was a testimony to our disciplined and coordinated workforce and
collaborative partners. Q3 2023 saw positive gains in efficiencies
and productivity, with momentum building throughout the latter
stages of the period. To date, the project remains within our
guidance for initial capital expenditure and on track for first
gold in H2 2024 as planned."
Video
Watch here for a Q3 project update video:
https://youtu.be/yR45JS3GQto
Photos
About Artemis Gold
Artemis Gold is a well-financed, growth-oriented gold
development company with a strong financial capacity aimed at
creating shareholder value through the identification, acquisition,
and development of gold properties in mining-friendly
jurisdictions. The company's current focus is the construction of
the Blackwater Mine project in central British Columbia approximately 160km southwest
of Prince George and 450km
northeast of Vancouver. The
project is one of the largest capital investments in the
Bulkley-Nechako, Fraser-Fort George
and Cariboo regions of B.C. in the last decade. The first pour of
gold and silver from Blackwater Mine is expected in H2 2024 and the
mine is expected to be in production for a minimum of 22 years.
Artemis Gold trades on the TSX-V under the symbol ARTG. For more
information visit www.artemisgoldinc.com.
Qualified Person
Jeremy Langford, FAUSIMM, a
Qualified Person as defined by National Instrument 43-101, has
reviewed and approved the scientific and technical information in
this press release.
On behalf of the Board of Directors
Steven Dean
Chairman and Chief Executive Officer
+1 604 558 1107
Neither the TSX Venture Exchange nor its Regulation Services
Provider (as that term is defined in the policies of the TSX
Venture Exchange) accepts responsibility for the adequacy or
accuracy of this news release.
Cautionary Note Regarding Forward-looking Information
This press release contains certain forward-looking
statements and forward-looking information as defined under
applicable Canadian and U.S. securities laws. Statements contained
in this press release that are not historical facts are
forward-looking statements that involve known and unknown risks and
uncertainties. Any statements that refer to expectations,
projections or other characterizations of future events or
circumstances contain forward-looking statements. In certain cases,
forward-looking statements and information can be identified using
forward-looking terminology such as "may", "will", "expect",
"intend", "estimate", "anticipate", "believe", "continue", "plans",
"potential" or similar terminology. Forward-looking statements and
information are made as of the date of this press release, and
include, but are not limited to, statements regarding the potential
of the Blackwater mine project; the jobs to be created in
connection with the project; the contribution of the project to the
economy; opinions of the Province of British Columbia regarding the project and the
region; agreements and relationships with Indigenous partners; the
future of mining in British
Columbia; the plans of the Company with respect to the
project, including construction, site preparation, clearing,
consultation with indigenous groups, and other plans and
expectations of the Company with respect to the project.
These forward-looking statements represent management's
current beliefs, expectations, estimates and projections regarding
future events and operating performance, which are based on
information currently available to management, management's
historical experience, perception of trends and current business
conditions, expected future developments and other factors which
management considers appropriate. Such forward-looking statements
involve numerous risks and uncertainties, and actual results may
vary. Important risks and other factors that may cause actual
results to vary include, without limitation: risks related to the
ability of the Company to accomplish its plans and objectives with
respect to the development of the project within the expected
timing or at all, the timing and receipt of certain required
approvals, changes in commodity prices, changes in interest and
currency exchange rates, risks inherent in exploration estimates
and results, risks inherent in exploration and development
activities, changes in development or mining plans due to changes
in logistical, technical or other factors, unanticipated
operational difficulties (including failure of plant, equipment or
processes to operate in accordance with specifications, cost
escalation, unavailability of materials, equipment or third party
contractors, delays in the receipt of government approvals,
industrial disturbances, job action, and unanticipated events
related to heath, safety and environmental matters), changes in
governmental regulation of mining operations, political risk,
social unrest, changes in general economic conditions or conditions
in the financial markets, and other risks related to the ability of
the Company to proceed with its plans for the project and other
risks set out in the Company's most recent MD&A, which is
available on the Company's website at
www.artemisgoldinc.com and on SEDAR at
www.sedar.com.
In making the forward-looking statements in this press
release, the Company has applied several material assumptions,
including without limitation, the assumptions that: (1) market
fundamentals will result in sustained mineral demand and prices;
(2) any necessary approvals and consents in connection with the
development of the project will be obtained; (3) financing for the
development, construction and continued operation of the project
will continue to be available on terms suitable to the Company; (4)
sustained commodity prices will continue to make the project
economically viable; and (5) there will not be any unfavourable
changes to the economic, political, permitting and legal climate in
which the Company operates. Although the Company has attempted to
identify important factors that could affect the Company and may
cause actual actions, events, or results to differ materially from
those described in forward-looking statements, there may be other
factors that cause the actual results or performance by the Company
to differ materially from those expressed in or implied by any
forward-looking statements. Accordingly, no assurances can be given
that any of the events anticipated by the forward-looking
statements will transpire or occur, or if any of them do so, what
impact they will have on the results of operations or the financial
condition of the Company. Investors should therefore not place
undue reliance on forward-looking statements. The Company is under
no obligation and expressly disclaims any obligation, to update,
alter or otherwise revise any forward-looking statement, whether
written or oral, that may be made from time to time, whether
because of new information, future events or otherwise, except as
may be required under applicable securities laws.
___________________________________
|
1 LTIFR
or Lost Time Injury Frequency Rate refers to the number of lost
time injuries occurring per million man-hours worked, divided by
total man-hours worked
|
2 AIFR
or All Injury Frequency Rate refers to the total number of
recordable incidents occurring per million man-hours worked,
divided by total man-hours worked
|
SOURCE Artemis Gold Inc.