Americas Silver Corporation (TSX: USA) (NYSE American: USAS)
(“Americas Silver” or the “Company”), a growing North American
precious metals producer, announces Q2, 2019 production and
operating cost results on a consolidated and individual basis for
its Cosalá Operations and Galena Complex and a construction update
on the Relief Canyon gold mine. All figures are in U.S.
dollars.
Second Quarter
Highlights
- Consolidated silver production of approximately 1.7 million
silver equivalenti ounces and 345,695 silver ounces, representing
an increase of 15% year-over-year to both silver and silver
equivalent.
- Consolidated cash costsii were approximately $8.28 per silver
ounce and consolidated all-in sustaining costs (“AISC”) were
approximately $16.15 per silver ounce, both representing an
increase year-over-year and from the prior quarter. These increased
costs were primarily the result of lower realized prices for zinc
and lead and lower production at the Galena Complex.
- For the first half of 2019, consolidated silver production of
approximately 3.4 million silver equivalent ounces and 740,000
silver ounces with consolidated cash costs of approximately $3.60
per silver ounce and consolidated AISC of approximately $10.50 per
silver ounce.
- Guidance for 2019 remains unchanged at 1.6 – 2.0 million silver
ounces and 6.6 – 7.0 million silver equivalent ounces at cash costs
of $4.00 to $6.00 per silver ounce and AISC of $10.00 to $12.00 per
silver ounce. The Company expects to release its second quarter
financial results on or before August 14, 2019.
- Construction is proceeding as expected at the Relief Canyon
Mine with leach pad activities progressing, mobilization of the
mining contractor expected later this week and all fabrication work
on the crusher and conveyors progressing to meet scheduled delivery
in the third quarter. First gold pour is expected in late Q4,
2019.
- Milled tonnage at the Cosalá Operations increased by 13%
year-over-year, with the San Rafael mine sustaining an average
milling rate of approximately 1,750 tonnes per operating day during
the quarter, resulting in production of approximately 1.3 million
silver equivalent ounces, including approximately 145,000 silver
ounces. Cash costs were approximately negative ($18.27) per silver
ounce and AISC were approximately negative ($11.66) per silver
ounce, representing increases of 70% and 72%, respectively, when
compared to prior year, largely due to lower zinc and lead prices
and higher treatment and refining charges.
- The Galena Complex produced approximately 383,000 silver
equivalent ounces, including approximately 200,000 silver ounces,
representing decreases of 3% and 9%, respectively, when compared to
Q2, 2018. Cash costs were approximately $27.55 per silver ounce and
AISC were approximately $36.35 per silver ounce, representing
increases of 50% and 36%, respectively, when compared to the same
period. These increases were largely due to a focus on development
over production given low metals prices during the quarter.
“The Company remains on target to achieve its full year
production and cost guidance despite the expected lower production
from the Galena Complex and lower realized metal prices in the
quarter,” said Americas Silver President and CEO Darren Blasutti.
“The second half of 2019 will be a very exciting period for our
Company as we expect not only higher silver production, but most
importantly, first gold pour from the Relief Canyon Mine.”
Consolidated Second Quarter Production
Details
Consolidated silver production for the second quarter of 2019
was 345,695 ounces and silver equivalent production was
approximately 1.7 million ounces, an increase of 15% year-over-year
for both metrics. Consolidated cash costs increased 235% to $8.28
per silver ounce year-over-year and AISC increased 199% to $16.15
per silver ounce compared year-over-year. Consolidated zinc
production increased by 27% year-over-year, while consolidated lead
production increased by 16% year-over-year.
Table 1
Consolidated Production
Highlights
Q2 2019
Q2 2018
Change
Q1 2019
Change
Processed Ore (tonnes milled)
186,310
164,313
13%
182,029
2%
Silver Production (ounces)
345,695
301,711
15%
393,824
-12%
Silver Equivalent Production (ounces)
1,683,358
1,462,170
15%
1,754,839
-4%
Silver Grade (grams per tonne)
76
77
-1%
87
-13%
Cost of Sales ($ per equiv. ounce
silver)
$8.75
$8.20
7%
$7.11
23%
Cash Costs ($ per ounce silver)
$8.28
($6.15)
>100%
($0.50)
>100%
All-in Sustaining Costs ($ per ounce
silver)
$16.15
$5.40
>100%
$5.54
>100%
Zinc Production (pounds)
11,150,174
8,756,201
27%
11,263,623
-1%
Lead Production (pounds)
7,237,607
6,216,592
16%
8,211,429
-12%
Cosalá Operations Production
Details
The Cosalá Operations produced 145,410 ounces of silver during
the second quarter of 2019 and 1.3 million ounces of silver
equivalent during the same period at cash costs of negative
($18.27) per silver ounce and AISC of negative ($11.66) per silver
ounce. Silver production increased by 54% while silver equivalent
production increased by 25% over the prior year, respectively. Cash
costs and AISC increased by 70% and 72%, respectively, compared to
Q2, 2018, despite significant increases in zinc and lead
production.
Table 2
Cosalá Operations
Highlights
Q2 2019
Q2 2018
Change
Q1 2019
Change
Processed Ore (tonnes milled)
156,998
138,708
13%
152,605
3%
Silver Production (ounces)
145,410
94,231
54%
173,169
-16%
Silver Equivalent Production (ounces)
1,300,009
1,041,246
25%
1,322,045
-2%
Silver Grade (grams per tonne)
49
42
17%
57
-14%
Cost of Sales ($ per equiv. ounce
silver)
$5.51
$5.36
3%
$4.34
27%
Cash Costs ($ per ounce silver)
($18.27)
($60.13)
-70%
($30.48)
-40%
All-in Sustaining Costs ($ per ounce
silver)
($11.66)
($41.66)
-72%
($25.85)
-55%
Zinc Production (pounds)
11,150,174
8,756,201
27%
11,263,623
-1%
Lead Production (pounds)
4,052,559
2,982,316
36%
4,626,233
-12%
Strong results were driven by sustained improvements in grade,
mill throughput and metal recovery as mining and milling operations
generally expanded at San Rafael in Q2, 2019 compared to Q2, 2018.
Ore production from the Main Zone benefited from additional working
headings providing greater operational flexibility.
Silver and lead head grades in Q2, 2019 were lower compared to
Q1, 2019 with steady zinc grades consistent with the Mining Plan
though expected to be slightly lower in the second half of 2019.
Any potential reduction in head grades over the remainder of the
year are expected to be largely offset by further gains in mill
throughput and metal recovery as additional flotation capacity was
installed during the second quarter with increased recoveries.
The increase in cash costs and AISC were largely the result of
higher treatment and refining charges and lower market prices for
both zinc and lead during the quarter. Operating costs and capital
expenditures remain in line with management expectations.
Development of the incline ramp toward the Upper Zone continues
to advance with the expectation of accessing the area prior to the
end of the year.
Galena Complex Production
Details
As previously noted in Q1, 2019, two high-tonnage stopes were
impacted by separate ground falls in late Q1, 2019 with follow-on
impact in Q2, 2019. The remaining active stopes were unable to
replace the tonnage loss associated with the impacted areas. Due to
these issues, the Galena Complex produced 200,285 ounces of silver
during Q2 2019 and 383,349 ounces of silver equivalent at cash
costs of $27.55 per silver ounce and AISC of $36.35 per silver
ounce. Silver and silver equivalent production decreased by 9% and
11%, respectively, compared to the prior quarter, and 3% and 9%,
respectively, year-over-year. Both cash costs and AISC represented
an increase of 20% due to the noted lower production and lower lead
prices during the quarter.
In order to improve mining flexibility, the Galena team
prioritized underground development and gained over 1,600 feet of
advance during the quarter. New production areas were established
on the 2400 and 3200 levels. In addition, ongoing exploration
activities continue to yield encouraging results which could
benefit production in the near term. Specifically, drilling on the
4900 level has identified new zones of mineralization (129 and 130
Veins) near existing infrastructure and further extended the strike
and vertical extent of known resources (137, 146, 167, 168 and
168HW Veins).
Table 3
Galena Complex
Highlights
Q2 2019
Q2 2018
Change
Q1 2019
Change
Processed Ore (tonnes milled)
29,312
25,605
14%
29,424
0%
Silver Production (ounces)
200,285
207,480
-3%
220,655
-9%
Silver Equivalent Production (ounces)
383,349
420,924
-9%
432,794
-11%
Silver Grade (grams per tonne)
220
263
-16%
242
-9%
Cost of Sales ($ per equiv. ounce
silver)
$19.75
$15.24
30%
$15.55
27%
Cash Costs ($ per ounce silver)
$27.55
$18.36
50%
$23.03
20%
All-in Sustaining Costs ($ per ounce
silver)
$36.35
$26.77
36%
$30.17
20%
Lead Production (pounds)
3,185,048
3,234,276
-2%
3,585,196
-11%
Relief Canyon Update
Construction is advancing well at the fully funded Relief Canyon
Mine. Preparation of the leach pad is approximately 80% complete
and installation of the liner has started. Mobilization of the
mining contractor is expected later this week. Work at the existing
processing plant has started where upgrades will be made to the
refinery and emissions controls.
Further information on the Relief Canyon development will be
made available periodically on the Company’s website as
construction progresses at www.americassilvercorp.com.
About Americas Silver Corporation
Americas Silver is a precious metal mining company focused on
growth from its existing asset base and execution of targeted
accretive acquisitions. It owns and operates the Cosalá Operations
in Sinaloa, Mexico and the Galena Complex in Idaho, USA. The
Company expects to begin producing gold in the fourth quarter of
2019 at its fully funded Relief Canyon Mine in Nevada, USA which is
currently in construction. The Company also holds an option on the
San Felipe development project in Sonora, Mexico.
Daren Dell, Chief Operating Officer and a Qualified Person under
Canadian Securities Administrators guidelines, has approved the
applicable contents of this news release. For further information
please see SEDAR or americassilvercorp.com.
Cautionary Statement on Forward-Looking Information:
This news release contains “forward-looking information” within
the meaning of applicable securities laws. Forward-looking
information includes, but is not limited to, Americas Silver’s
expectations, intentions, plans, assumptions and beliefs with
respect to, among other things, Americas Silver’s financing
efforts; production and cost performance at the Cosalá Operations
and the Galena Complex; construction, production, development plans
and performance expectations at the Relief Canyon Project and the
impact on Americas Silver’s financial performance; Often, but not
always, forward-looking information can be identified by
forward-looking words such as “anticipate”, “believe”, “expect”,
“goal”, “plan”, “intend”, “potential’, “estimate”, “may”, “assume”
and “will” or similar words suggesting future outcomes, or other
expectations, beliefs, plans, objectives, assumptions, intentions,
or statements about future events or performance. Forward-looking
information is based on the opinions and estimates of Americas
Silver as of the date such information is provided and is subject
to known and unknown risks, uncertainties, and other factors that
may cause the actual results, level of activity, performance, or
achievements of Americas Silver to be materially different from
those expressed or implied by such forward-looking information.
With respect to the business of Americas Silver, these risks and
uncertainties include interpretations or reinterpretations of
geologic information; unfavorable exploration results; inability to
obtain permits required for future exploration, development or
production; general economic conditions and conditions affecting
the industries in which the Company operates; the uncertainty of
regulatory requirements and approvals; fluctuating mineral and
commodity prices; the ability to obtain necessary future financing
on acceptable terms or at all; the ability to develop, complete
construction and operate the Relief Canyon Project; and risks
associated with the mining industry such as economic factors
(including future commodity prices, currency fluctuations and
energy prices), ground conditions and other factors limiting mine
access, failure of plant, equipment, processes and transportation
services to operate as anticipated, environmental risks, government
regulation, actual results of current exploration and production
activities, possible variations in ore grade or recovery rates,
permitting timelines, capital and construction expenditures,
reclamation activities, labor relations, social and political
developments and other risks of the mining industry. Although the
Company has attempted to identify important factors that could
cause actual results to differ materially from those contained in
forward-looking information, there may be other factors that cause
results not to be as anticipated, estimated, or intended. Readers
are cautioned not to place undue reliance on such information.
Additional information regarding the factors that may cause actual
results to differ materially from this forward‐looking information
is available in Americas Silver’s filings with the Canadian
Securities Administrators on SEDAR and with the SEC. Americas
Silver does not undertake any obligation to update publicly or
otherwise revise any forward-looking information whether as a
result of new information, future events or other such factors
which affect this information, except as required by law. Americas
Silver does not give any assurance (1) that Americas Silver will
achieve its expectations, or (2) concerning the result or timing
thereof. All subsequent written and oral forward‐looking
information concerning Americas Silver are expressly qualified in
their entirety by the cautionary statements above.
i Silver equivalent production throughout this press release was
calculated based on silver, zinc, and lead realized prices during
each respective period.
ii Cash cost per ounce and all-in sustaining cost per ounce are
non-IFRS performance measures with no standardized definition. For
further information and detailed reconciliations, please refer to
the Company’s 2018 year-end and quarterly MD&A. The performance
measures for the quarter ended June 30, 2019 are preliminary
throughout this press release subject to refinement from the
Company’s second quarter financial results to be released on or
before August 14, 2019.
View source
version on businesswire.com: https://www.businesswire.com/news/home/20190730005359/en/
For more information: Darren Blasutti President and CEO
Americas Silver Corporation 416‐848‐9503
Americas Gold and Silver (TSX:USA)
Gráfico Histórico do Ativo
De Fev 2025 até Mar 2025
Americas Gold and Silver (TSX:USA)
Gráfico Histórico do Ativo
De Mar 2024 até Mar 2025