ENDEAVOUR LAUNCHES CONSTRUCTION OF ITY CIL
PROJECT BASED ON OPTIMIZATION STUDY
View News Release in PDF Format
View Presentation in PDF Format
HIGHLIGHTS
- Optimization Study significantly improves the previous
Feasibility Study results (published in November 2016) and
positions the Ity CIL Project as Endeavour's next long-life
low-cost flagship asset
- Long 14-year mine life based on current reserves which
increased by 1.0Moz to 2.9Moz
- Average annual production over the first 5 years increased by
42% to 235koz and AISC decreased by 3% to $494/oz
- Average annual production over the first 10 years increased by
51% to 204koz and AISC decreased by 2% to $549/oz
- Robust economics with after-tax NPV5% of $710m, a 73% increase,
based on a gold price of $1,250/oz
- Ity CIL Project has entered the construction phase following
Board approval
- Endeavour's in-house construction team has begun to transition
from Houndé to Ity and has commenced mobilisation to site
- $412 million initial capex, fully funded from existing sources
of capital with the recent Revolving Credit Facility upsize
- 20-month construction duration with the first gold pour
expected for mid-2019
Abidjan, September 20, 2017 - Endeavour
Mining Corporation ("Endeavour") (the "Company) (TSX:EDV)
(OTCQX:EDVMF) is pleased to announce that its Board of Directors
has approved the construction decision for its Ity CIL project at
its mine in Cote d'Ivoire following the robust results obtained
from its Optimization Study.
The Ity CIL Project Feasibility and Optimization
studies have been conducted to analyze the economic viability of
constructing a straight forward gravity circuit/Carbon-In-Leach
("CIL") plant as an alternate processing route to the current heap
leach process. Following the publication of the November 2016
Feasibility Study ("FS"), an Optimization Study ("OS") was prepared
to better capture the value created from the recent exploration
success which has led to increasing the plant name-plate design
from 3.0Mtpa to 4.0Mtpa. In addition, several changes have been
made to leverage construction and operating synergies between Ity,
Agbaou and Houndé.
The production profile and economics have
significantly improved, as summarized in Table 1 below:
Table 1: Summary of 2016 CIL
Feasibility Study vs. 2017 Optimization Study
(On a 100% basis) |
2017 OPTIMIZATION STUDY |
2016 FEASIBILITY STUDY |
VARIANCE (OS VS. FS) |
M&I Resources
(inclusive of Reserves) |
3.8Moz |
2.3Moz |
+65% |
P&P Reserves |
2.9Moz |
1.9Moz |
+53% |
Average production
(first 5 years) |
235koz |
165koz |
+42% |
Average AISC (first 5
years) |
$494/oz |
$507/oz |
(3%) |
After-tax NPV5%
based on $1,250/oz |
$710m |
$411m |
+73% |
After-tax IRR based on
$1,250/oz |
40.3% |
35.9% |
+12% |
After-tax
IRR based on $1,000/oz |
23.2% |
19.5% |
+19% |
Sébastien de Montessus, President & CEO,
stated: "Today's study clearly positions Ity as our next
flagship asset with robust project economics, a strong long-life
production profile, and significant exploration upside. Its average
annual production in the first five years of 235koz with AISC below
$500/oz and an after-tax IRR of +20% even at a low gold price
of $1,000 per ounce are proof of the compelling economics of the
project.
With the upcoming first gold pour at Houndé and
Ity CIL construction expected to be completed within 20-months, we
remain on track to achieve our strategic milestones of becoming a
+800,000 ounce per year gold producer with group AISC below $800
per ounce and mine lives above 10 years by 2019."
Jeremy Langford, COO, added: "We have optimized
the Ity CIL project by maximizing the construction and operational
synergies between Agbaou, Houndé and Ity, and by leveraging the
same designs, components, equipment and spare parts where possible
from one project to the other, along with incorporating our
extensive construction expertise. The construction team is excited
to transition from Houndé to Ity and to continue to build on its
construction track-record."
SUMMARY OF KEY CHANGES FROM PREVIOUS
FEASIBILITY STUDYThe Ity CIL Project Optimization Study has
been managed by Endeavour's in house development team and
independently prepared by Lycopodium Minerals Pty Ltd
("Lycopodium") with the support of six globally recognized
engineering firms, with the key operational and financial results
summarized in the table below:
Table 2: Detailed Summary of
2016 CIL Feasibility Study vs. 2017 Optimization Study
|
2017 OPTIMIZATION STUDY |
2016 FEASIBILITY STUDY |
VARIANCE (OS VS. FS) |
LIFE OF MINE
PRODUCTION |
|
|
|
Strip
ratio, w:o |
1.9 |
2.1 |
(10%) |
Tonnes
of ore processed, Mt |
57.0Mt |
41.0Mt |
+39% |
Grade
processed, Au g/t |
1.57 g/t |
1.42 g/t |
+10% |
Gold
content processed, Moz |
2.87 Moz |
1.88 Moz |
+53% |
LOM
Average Gold recovery, % |
86% |
83% |
+3% |
Gold
production, Moz |
2.47 Moz |
1.56 Moz |
+58% |
Mine
life, years |
14.3 years |
13.7 years |
+4% |
Average annual gold production, koz |
173 Koz |
114 Koz |
+52% |
Cash
costs, $/oz |
$554 |
$528 |
+5% |
AISC,
$/oz |
$580 |
$603 |
(4%) |
AVERAGE FOR YEARS 1 TO
5: |
|
|
|
Gold
production, kozpa |
235 koz |
165 koz |
+42% |
Cash
costs, $/oz |
$472/oz |
$446/oz |
+6% |
AISC,
$/oz |
$494/oz |
$507/oz |
(3%) |
AVERAGE FOR YEARS 1 TO
10: |
|
|
|
Gold
production, kozpa |
204 koz |
135 koz |
+51% |
Cash
costs, $/oz |
$523/oz |
$488/oz |
+7% |
AISC,
$/oz |
$549/oz |
$559/oz |
(2%) |
CAPITAL COST |
|
|
|
Initial capital cost, $m |
$412m |
$307m |
+34% |
- of which equipment lease, $m |
$61m |
$25m |
+160% |
Upfront capital cost, $m |
$351m |
$282m |
+24% |
ECONOMICS (BASED ON $1,250/OZ) |
|
|
|
After-tax IRR |
40% |
36% |
+12% |
After-tax NPV ( 0% discount rate) |
$990m |
$607m |
+63% |
After-tax NPV ( 5% discount rate) |
$710m |
$411m |
+73% |
Payback period |
1.8 years |
2.1 years |
(17%) |
The key changes made in the Optimization Study
include:
- CIL process plant increased from 3Mtpa to 4Mtpa to better
capture the value created from the recent exploration success which
has discovered the Bakatouo deposit and increased resources at
notably Daapleu and Mont/Ity Flat.
- Simplified and optimized the process plant design to maximize
the replication of the Houndé design, where applicable, to capture
working capital inventory synergies.
- Improved recoveries based on additional metallurgical testwork,
namely on the Daapleau primary material.
- Addition of a diverter/flop-gate system which allows the Ball
Mill to run independently during periods when the SAG mill is shut
down. This operability allows the plant to maximize utilization and
effectively ensure process milling all year round.
- Addition of a 26MW full back up power station, identical to
that installed at the Houndé project.
- Optimized upfront capital cost and sequenced overall build time
with a higher percentage of "Self-Perform" works.
- Optimized the site layout, which allows the current heap leach
operation to run independently of the CIL project. As such, the
construction of the CIL project is not expected to impact the heap
leach operation.
RESERVES INCREASED BY 1.0Moz, UP 53%
The updated Mineral Reserve estimates were
undertaken by Snowden Mining industry Consultants (Snowden).
Changes from the previously reported Mineral Reserves are largely
due to revised and updated Mineral Resource estimates on the
Daapleu, Ity and Bakatouo deposits and revised operating costs
largely associated with revised processing capabilities from a 3
Mtpa facility to a 4 Mtpa treatment facility.
Compared to the 2016 Feasibility Study
reserves, a total of 1.0Moz were added, with the main increases
coming from the discovery of Bakatouo (+532koz), and additional
resource to reserve conversion at Mont Ity/Ity Flat (+211koz),
Teckraie/Verse Ouest (+187koz), and at Daapleu (+79koz) following
additional drilling, as shown in the table below. The Colline Sud
deposit is expected to be mined during the heap leach phase and
therefore has been excluded from CIL Mineral
Reserves.
Table 3: CIL Project Reserves
Comparison
Deposits on a 100% basis |
Optimization Study Reserves, as at September 1,
2017 |
|
Feasibility Study Reserves, as at October 1,
2016 |
|
Variance (koz) |
Tonnage (Mt) |
Grade (Au g/t) |
Content (Au koz) |
|
Tonnage (Mt) |
Grade (Au g/t) |
Content (Au koz) |
|
Open Pits |
|
|
|
|
|
|
|
|
|
Bakatouo |
6.9 |
2.40 |
532 |
|
- |
- |
- |
|
+532 |
Colline Sud |
- |
- |
- |
|
- |
- |
- |
|
- |
Daapleu |
18.4 |
1.72 |
1,015 |
|
19.3 |
1.51 |
936 |
|
+79 |
Mont Ity / Ity Flat |
7.4 |
2.03 |
479 |
|
3.8 |
2.19 |
268 |
|
+211 |
Gbeitouo |
2.5 |
1.37 |
111 |
|
2.6 |
1.35 |
112 |
|
(1) |
Walter |
1.2 |
1.07 |
41 |
|
1.9 |
1.22 |
73 |
|
(32) |
Zia NE |
6.2 |
1.06 |
210 |
|
4.8 |
1.24 |
192 |
|
+18 |
Sub-total |
42.5 |
1.75 |
2,390 |
|
32.4 |
1.52 |
1,580 |
|
+810 |
Existing
Stockpiles |
|
|
|
|
|
|
|
|
|
Aires |
5.8 |
1.09 |
202 |
|
5.8 |
1.09 |
202 |
|
- |
Teckraie/ Verse Ouest |
8.7 |
1.02 |
284 |
|
2.8 |
1.07 |
97 |
|
+187 |
Sub-total |
14.5 |
1.05 |
486 |
|
8.6 |
1.08 |
300 |
|
+186 |
Total |
57.0 |
1.57 |
2,876 |
|
41.0 |
1.42 |
1,880 |
|
+996 |
Mineral Reserve estimates follow the Canadian
Institute of Mining, Metallurgy and Petroleum ("CIM") definitions
standards for mineral resources and reserves and have been
completed in accordance with the Standards of Disclosure for
Mineral Projects as defined by National Instrument 43-101. Notes
are provided in Section "About the Mineral Reserve and Resources"
of this Press Release, with effective date September 1, 2017. Full
details on the 2016 Feasibility Study Reserves are available in the
Company's published press release dated November 10, 2016.
INDICATED RESOURCE INCREASED BY
1.5Moz
The updated Indicated and Inferred Mineral
Resource estimates were undertaken by Cube Consulting (Cube), and
incorporate all validated RC, DC and AC drilling completed at the
Ity CIL Project up to May 1, 2017.
There is a total of 10 deposit areas included
in the updated Mineral Resource for the Ity CIL Project including
four in situ gold deposits that have been or are currently in
production, comprising Mont Ity, Ity Flat, ZiaNE and Walter, plus
three near-mine in situ deposits comprising Gbeitouo, Daapleu,
Colline Sud and Bakatouo, and two rock waste dumps at Teckraie and
Verse Ouest and a discontinued heap leach pad Aires.
Compared to the resource inventory used to
build the 2016 Feasibility Study, a total of 1.5Moz of Indicated
Resources were added, with the main increases coming from the
discovery of Bakatouo (+704koz), and additional Indicated resources
outlined at Daapleu (+384koz), Mont Ity / Ity Flat (+189koz), and
Verse Ouest (+187koz), as shown in the table below.
Table 4: Resource
Comparison
|
2017 OPTIMIZATION STUDY INVENTORY |
|
2016 FEASIBILITY STUDY INVENTORY |
Deposits on a 100% basis |
Indicated Resources |
|
Inferred Resources |
|
Indicated Resources |
|
Inferred Resources |
Tonnage (Mt) |
Grade (Au g/t) |
Content (Au koz) |
|
Tonnage (Mt) |
Grade (Au g/t) |
Content (Au koz) |
|
Tonnage (Mt) |
Grade (Au g/t) |
Content (Au koz) |
|
Tonnage (Mt) |
Grade (Au g/t) |
Content (Au koz) |
Open Pits |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Daapleu |
28.1 |
1.50 |
1,349 |
|
0.7 |
0.92 |
22 |
|
19.9 |
1.51 |
965 |
|
4.3 |
1.15 |
160 |
Mont Ity /
Flat |
10.1 |
2.20 |
716 |
|
9.7 |
1.40 |
436 |
|
7.5 |
2.19 |
527 |
|
11.1 |
1.92 |
684 |
Gbeitouo |
2.9 |
1.35 |
124 |
|
0.3 |
1.48 |
13 |
|
2.9 |
1.35 |
124 |
|
0.3 |
1.48 |
13 |
Walter |
1.6 |
1.23 |
65 |
|
0.6 |
1.35 |
26 |
|
2.1 |
1.21 |
81 |
|
0.7 |
1.32 |
28 |
Zia NE |
6.7 |
1.28 |
274 |
|
4.0 |
1.40 |
178 |
|
7.7 |
1.31 |
325 |
|
4.0 |
1.39 |
179 |
Bakatouo |
10.2 |
2.14 |
704 |
|
0.6 |
2.27 |
44 |
|
- |
- |
- |
|
- |
- |
- |
Colline Sud |
1.0 |
2.14 |
66 |
|
0.4 |
2.11 |
28 |
|
- |
- |
- |
|
- |
- |
- |
Sub-total |
60.6 |
1.69 |
3,298 |
|
16.3 |
1.43 |
747 |
|
40.1 |
1.57 |
2,022 |
|
20.4 |
1.62 |
1,064 |
Existing
Stockpiles |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Aires |
5.8 |
1.09 |
202 |
|
0.2 |
0.78 |
6 |
|
5.8 |
1.09 |
202 |
|
0.2 |
0.78 |
6 |
Teckraie |
2.8 |
1.07 |
97 |
|
0.1 |
0.55 |
2 |
|
2.8 |
1.07 |
97 |
|
0.1 |
0.55 |
2 |
Verse Ouest |
5.9 |
0.99 |
187 |
|
2.3 |
0.50 |
37 |
|
- |
- |
- |
|
8.4 |
0.85 |
230 |
Sub-total |
14.5 |
1.04 |
486 |
|
2.6 |
0.54 |
45 |
|
8.6 |
1.08 |
300 |
|
8.7 |
0.85 |
238 |
Total |
75.1 |
1.57 |
3,784 |
|
18.9 |
1.30 |
792 |
|
48.7 |
1.48 |
2,322 |
|
29.1 |
1.39 |
1,302 |
Resource estimated to the Indicated status,
as such no Measured Resources available. Mineral Resource
estimates follow the Canadian Institute of Mining, Metallurgy and
Petroleum ("CIM") definitions standards for mineral resources and
reserves and have been completed in accordance with the Standards
of Disclosure for Mineral Projects as defined by National
Instrument 43-101. Notes are provided in Section "About the Mineral
Reserve and Resources" of this Press Release, with effective date
September 1, 2017. Full details on the 2016 Feasibility Study
Inventory are available in the Company's published press release
dated November 10, 2016.
MINING OPERATIONS, PROCESSING, AND
METALLURGYMINING AND PROCESSING STRATEGY
A number of schedules were completed to test
the impact of limiting stockpile size and it was found that there
was limited benefit to allowing for large stockpiles. As such, the
mining sequence and stockpile management has improved in the
Optimized Study compared to the Feasibility Study. Whereas
previously the mining period was 9 years followed by the processing
of stockpiled low-grade ore for another 5 years, the current mine
plan is based on 12 years of mining followed by the processing of
stockpiled low-grade ore for another 2 years.
A combination of strategic pit staging and
stockpiling allows gold production to be brought forward, with
about 1.2 Moz mined in the first 5 years from commissioning and 1.5
Moz in the last 10 years. The overall grade profile declines
gradually over the life of mine as higher grade deposits such as
Bakatouo, Daapleu and Mont Ity / Flat are mined upfront.
Mining OperationsThe mine planning,
resource and cost estimation for the Feasibility Study is based on
an owner-operated mining operation using 90-tonne haul trucks and a
maximum mining movement of 16Mt per year with a vertical advance of
approximately 40 metres per year. The Company sees these figures as
conservative in nature due to the annual rainfall at the Ity
project. Mining is scheduled to commence three months before
the start of the processing plant to pre-strip the pits and
stockpile ore. The mining fleet contract has been awarded to
Komatsu to benefit from synergies relating to minimizing spare
parts inventory and maintenance costs, as both Houndé and Karma
have a similar fleet.
Table 5: Mine Plan
|
Total |
Y-1 |
Y-2 |
Y-3 |
Y-4 |
Y-5 |
Y-6 |
Y-7 |
Y-8 |
Y-9 |
Y-10 |
Y-11 |
Y-12 |
Total material moved,
Mt |
167 |
15.6 |
16.0 |
16.0 |
16.0 |
16.0 |
16.0 |
13.8 |
12.7 |
15.9 |
13.6 |
10.1 |
5.1 |
Total ore mined,
Mt |
57 |
4.6 |
5.8 |
5.9 |
4.7 |
4.8 |
5.1 |
4.3 |
3.8 |
5.4 |
5.9 |
4.9 |
1.9 |
Stripping ratio,
w:o |
1.9 |
2.4 |
1.8 |
1.7 |
2.4 |
2.3 |
2.1 |
2.2 |
2.3 |
1.9 |
1.3 |
1.1 |
1.7 |
Grade mined, g/t
Au |
1.57 |
1.70 |
2.05 |
1.78 |
1.87 |
1.65 |
1.88 |
1.20 |
1.37 |
1.38 |
1.30 |
1.12 |
1.08 |
Contained gold mined, koz |
2,883 |
250 |
380 |
340 |
284 |
256 |
310 |
166 |
168 |
241 |
246 |
176 |
66 |
Processing Operations
Following updated resource and reserve
estimates, the key change to the design basis is an increase in
throughput from 3 Mtpa feed to 4 Mtpa feed based on a blend of
primary and oxide ore with a conventional primary crushing followed
by SAG and Ball milling circuit (SABC) with recycle pebble
crusher, gravity circuit and conventional CIL
(Carbon-In-Leach) plant. Soluble copper from the Bakatouo asset is
blended with the low copper Daapleu ore into the plant process
schedule until depletion of Bakatouo. A maximum process plant feed
limit of 200ppm cyanide soluble copper constraint has been set, to
manage cyanide consumption within the CIL plant and detoxification
circuit.
The process plant will notably be composed of
a single stage primary crushing to produce a crushed product size
of 80% passing (P80 of 166 mm) and a two stage SAG (with pebble
crusher recycle)/ Ball milling in closed circuit with hydrocyclones
to produce a P80 grind size of 75 micrometers. A gravity
concentrator and Intensive Leach Reactor (ILR) have been included
in the design as per the FS. The CIL circuit comprises eight CIL
tanks (up from six in the FS) containing carbon for gold and silver
adsorption with oxygen sparged from two 25 tonne PSA Oxygen
plants and a 18 tonne split Anglo (AARL) elution circuit.
Electrowinning and induction furnace smelting completes the gold
doré production process. A cyanide detoxification and arsenic
removal circuit is included in the process facility design, for
treatment of process residue before discharge to the fully lined
57Mt Tailings Storage Facility (TSF), located adjacent to the
processing facility. Feed water for the processing facility will
come from various sources such as pit dewatering bores, the Cavally
River for (make-up) and decant return from the TSF.
Table 6: Processing
Schedule
|
Total |
Y-1 |
Y-2 |
Y-3 |
Y-4 |
Y-5 |
Y-6 |
Y-7 |
Y-8 |
Y-9 |
Y-10 |
Y-11 |
Y-12 |
Y-13 |
Y-14 |
Ore processed, Mt |
57.2 |
4.0 |
4.0 |
4.0 |
4.0 |
4.0 |
4.0 |
4.0 |
4.0 |
4.0 |
4.0 |
4.0 |
4.0 |
4.0 |
4.0 |
Grade processed, g/t
Au |
1.57 |
2.26 |
2.32 |
2.21 |
1.87 |
1.99 |
1.80 |
1.37 |
1.57 |
1.84 |
1.32 |
1.45 |
0.98 |
0.72 |
0.53 |
Recovery rate, % |
86% |
86% |
84% |
84% |
88% |
87% |
87% |
85% |
80% |
80% |
93% |
90% |
90% |
84% |
86% |
Recovered gold, koz |
2,467 |
250 |
250 |
238 |
212 |
223 |
201 |
151 |
161 |
189 |
159 |
167 |
113 |
77 |
59 |
Metallurgy
The overall life of mine recovery rate
increased from 83% in the Feasibility Study to 86% in the Optimized
Study due to the addition of high-recovery Bakatouo oxide and fresh
ore, Mont Ity ore and better recovery on Daapleu Sulphides
following additional testwork.
Table 7: Gold Recovery Rate by
Deposit
|
Bakatouo Oxides/Fresh |
Bakatouo Transition |
Daapleu Sulphides |
Daapleu Oxides |
Gbeitouo |
Mont Ity/Flat |
Walter |
Zia NE |
Stockpiles |
Total |
LOM Tonnage, Mt |
6.07 |
0.8 |
7.8 |
10.6 |
2.5 |
7.4 |
1.2 |
6.2 |
14.5 |
57.0 |
% of LOM Tonnage |
11% |
1% |
14% |
19% |
4% |
13% |
2% |
11% |
25% |
100% |
Gold Grade, g/t Au |
2.28 |
3.29 |
2.41 |
1.21 |
1.37 |
2.03 |
1.08 |
1.06 |
1.04 |
1.57 |
Gold
Recovery rate, % |
95/97% |
84% |
66% |
85% |
88% |
89% |
96% |
97% |
92% |
86% |
For the economic model, payable silver in the
doré ingots has been estimated on a conservative ratio of 2 to 1. A
detailed investigation of the metallurgical response of the
Bakatouo deposit was undertaken. Most samples showed high gold
extractions but soluble copper levels were also high, particularly
in the transition ore. As such, Endeavour has elected to blend in
the soluble copper ore constraining it to 200ppm per feed blend.
The Daapleu Primary ore can be considered refractory, with elevated
Arsenic levels in the fresh ore, however it has negligible copper.
Further detailed testwork has shown improvements, allowing the
reported recovery for the higher Arsenic fresh material to increase
to from 60% in the Feasibility Study to 66% in the Optimization
Study.
Low Operating Costs
The operating cost estimates have been re-scoped
based on most recent available cost information and based on a
4mtpa processing operation.
Table 8: Life of Mine Operating
Costs in US$, estimated at ± 15% accuracy
|
2017 OPTIMIZATION STUDY |
2016FEASIBILITY STUDY |
VARIANCE (OS VS. FS) |
Open
Pit Mining and Rehandling, $/tonne moved |
$2.89/t |
$2.45/t |
+18% |
Processing, $/t
milled |
$11.96/t |
$10.56/t |
+13% |
G&A
costs, $/t milled |
$2.23/t |
$2.79/t |
(20%) |
Operating Cost, $/t milled |
$22.90/t |
$20.56/t |
+11% |
Operating costs have been based on a delivered
diesel price of $1.00/L and are in line with current local pricing.
Following the connection to the grid, electricity costs have been
estimated based on $0.1243/kWh.
PROJECT CAPEX SUMMARYThe optimized and
fully scoped upfront capital cost has been re-estimated to reflect
the upgrade project scope at $412 million, inclusive of $49 million
for the owner-mining fleet and $34 million for contingencies, as
summarised in the table below. The upfront capital is expected to
be $351 million as a $61 million lease financing is expected to be
put in place for the mining fleet and power station.
Table 9: Initial Capital Cost
Estimate Summary (US$, ±15%)
|
2017 OPTIMIZATION STUDY |
2016FEASIBILITY STUDY |
Treatment Plant |
94 |
63 |
Reagents and
Services |
14 |
9 |
Infrastructure and
Tailings |
71 |
46 |
Mining (includes
pre-striping and $49m for equipment) |
84 |
59 |
Construction
Distributables |
26 |
24 |
Management Costs |
17 |
16 |
Owners Project
Costs |
66 |
59 |
Owners
Operations Costs |
5 |
4 |
Sub-Total |
378 |
282 |
Contingency |
34 |
26 |
Total |
412 |
307 |
Capital costs include the construction of a 58
km, 91kv overhead power line, which connects to the national grid
at Danane and terminates with a substation at Ity which will be
owned by Côte d'Ivoire Energie ("CIE"). A full 26MW full high speed
diesel back-up power station provides 100% redundancy. The
infrastructure in place will be improved with roads upgraded to an
all-weather and free draining carriageway to provide access for the
delivery of equipment, materials and services to the site. A new
camp will be built approximately 1 kilometer north-west of the
process plant and will provide accommodation for 200 employees, and
provisions have been made to construct a suitable airstrip.
A Cavally River diversion will be installed to
allow development of the Daapleu pit, with a second diversion
upstream of the Walter pit. Pit protection bunds will also be
installed and a bridge/culvert road structure from Daapleu over the
Cavally River will also be built.
The proposed approach to project implementation
is similar in nature to the current execution methodology of the
Endeavour Project Services In-House team in that Endeavour will
engage a suitably qualified Engineering, Procurement and
Construction Management (EPCM) Engineer for design and construction
management of the process plant and infrastructure, which will then
be handed over to an Owner's operating team. Endeavour will
self-perform the development of the mine infrastructure and
provision of ongoing drill and blast and mine operating services
under an Owner's mine technical team.
The schedule anticipates the project being
completed within 20 months from EPCM award.
PROJECT ECONOMICSThe results of the
financial model show robust results. Applying a long term gold
price of $1,250/oz on a flat line basis from the commencement of
production, the after-tax NPV5% is $710 million, IRR is 40.3% and
project payback period is 1.8 years.
Table 10: Gold Price
Sensitivity
Gold Price ($US/oz) |
After-tax NPV ($m) |
After-tax IRR |
0% |
5% |
10% |
$1,000/oz |
520 |
343 |
221 |
23.2% |
$1,050/oz |
613 |
416 |
280 |
26.7% |
$1,100/oz |
707 |
489 |
339 |
30.2% |
$1,150/oz |
801 |
563 |
399 |
33.6% |
$1,200/oz |
896 |
636 |
458 |
36.9% |
$1,250/oz |
990 |
710 |
518 |
40.3% |
$1,300/oz |
1,072 |
773 |
569 |
43.1% |
$1,350/oz |
1,166 |
847 |
629 |
46.4% |
$1,400/oz |
1,260 |
920 |
688 |
49.6% |
PROJECT IS FULLY FUNDED
As shown in Figure 1 below, the Ity CIL Project
is fully funded with significant headroom available based on
liquidity and funding sources available which include cash and
undrawn upsized Revolving Credit Facility ("RCF"), the future cash
generation from existing operating mines the upcoming proceeds from
the sale of the Nzema mine, potential Ity power station and
equipment financing, and the upcoming La Mancha anti-dilution
equity placement.
Figure 1: Funding Sources
As was successfully implemented during the
Houndé construction period, Endeavour will study the opportunity to
put in place a short-term Gold Revenue Protection Strategy,
consisting of Gold Option Contracts on only a portion of its
production, to mitigating risk and increase the certainty of its
upcoming free cash flow during its peak investment phase.
HEAP LEACH OPERATION
It is envisaged that the heap leach operation
will run during the construction period and that heap leach
activities will cease once the CIL plant is commissioned. Endeavour
will reassess the risk and opportunity of running both operations
in parallel once the CIL project has been developed.
COMMUNITY AND SOCIAL RESPONSIBILITY
ACTIONS
Endeavour recognizes that an active CSR program
is the foundation of long-term success and its social license to
operate. Baseline studies for the ESIA from 2013 to 2016 have been
completed and an ESIA report was published in March 2016 and a
Resettlement Action Plan ("RAP") has been completed.
Three environmental permits have been granted
covering the mining and process plant, Daapleu and Gbeitouo
exploitation and mining and surface infrastructure.
Full CSR team complement is now in place and
working on establishing CSR best practices and reporting.
EXPLORATION POTENTIAL
The Ity area has significant exploration
potential with several deposits located within 5 kilometers of one
another in addition to several exploration targets identified as
per the blue dashed area in the Figure below. This area represents
a small portion of the 80km corridor controlled by Endeavour.
Figure 2: Ity Mine Area and Surrounding
Exploration Targets
ABOUT THE MINERAL RESERVES AND
RESOURCES
The in situ Mineral Resources, which include
Daapleu, Mont Ity / Ity Flat, Bakatouo, Gbeitouo, Walter, Zia NE
and Colline Sud, have been reported inside optimised pit shells and
above a 0.5 g/t Au cut-off. Reporting within an optimised pit shell
satisfies the requirement for the Mineral Resource to have
reasonable prospects for future economic extraction. The pit
optimisation assumes a US$1,500/oz Au price.
The Mineral Resource for the rock dumps, which
include the Teckraie and Verse Ouest Mineral Resources and also the
Aires heap leach pad, have not been reported inside an optimised
pit shell. These deposits have been built up above the existing
topography and the associated shallow laterite located directly
below, therefore satisfying the requirement for the Mineral
Resource to have reasonable prospects for future economic
extraction. The Teckraie and Verse Ouest rock dump Mineral
Resources and Aires leach pad Mineral Resources have been reported
above 0.0 g/t Au because there is unlikely to be any grade
selectivity during mining. The underlying laterite Mineral
Resources for each of the deposits has been reported above 0.5 g/t
Au given the possibility for some mining selectivity. The Colline
Sud deposit is expected to be mined during the heap leach phase and
therefore has been excluded from CIL Mineral Reserves. All Mineral
Resources are current as at April 30, 2017. Mineral resources which
are not mineral reserves do not have demonstrated economic
viability.
Reported tonnage and grade figures have been
rounded from raw estimates to reflect the relative accuracy of the
estimate. Minor variations may occur during the addition of rounded
numbers.
The statistical analysis, geological modelling
and resource estimation for Colline Sud were prepared by Kevin
Harris, CPG. Mr. Harris is Endeavour Mining's Group Resource
Manager and is a "Qualified Person" as defined by National
Instrument 43-101 - Standards of Disclosure for Mineral Projects
("NI 43-101").
The statistical analysis, geological modelling
and resource estimation for Bakatouo, Mt Ity/Ity flat, Daapleu and
Verse Ouest were prepared by Mark Zammit, CPG. Mr. Zammit is a
principal consultant geologist with Cube Consulting Pty Ltd and is
a "Qualified Person" as defined by National Instrument 43-101 -
Standards of Disclosure for Mineral Projects ("NI 43-101").
The statistical analysis, geological modelling
and resource estimation for Bakatouo, Mt Ity/Ity flat, Daapleu,
Gbeitouo, Walter, Zia NE. Aires and Verse Ouest were prepared by
Mark Zammit, CPG. Mr. Zammit is a principal consultant geologist
with Cube Consulting Pty Ltd and is a "Qualified Person" as defined
by National Instrument 43-101 - Standards of Disclosure for Mineral
Projects ("NI 43-101").
The Qualified person for the Ity Mineral Reserve
estimation is Mr Allan Earl AWASM FAusIMM. Mr. Earl is an executive
consultant with Snowden Mining industry Consultants Pty Ltd and is
a "Qualified Person" as defined by National Instrument 43-101 -
Standards of Disclosure for Mineral Projects ("NI 43-101").
A gold price of US$1,250/oz was used in the pit
optimizations for Mineral Reserves. The estimation of break-even
cut-off grades are based on net revenue (gold price x process
recovery) and the throughput (ore related) costs.
QUALIFIED PERSONS
Jeremy Langford, Endeavour's Chief Operating
Officer - Fellow of the Australasian Institute of Mining and
Metallurgy - FAusIMM, is a Qualified Person under NI 43-101, and
has reviewed and approved the operational analysis, operating and
capital estimates, and other technical information in this news
release.
CONFERENCE CALL AND LIVE WEBCAST FOR ITY CIL
PROJECT
Management will host a conference call and live
webcast today at 9:30am Toronto time (EST) to discuss the results
of the Ity CIL Project Optimization Study.
The conference call and live webcast are scheduled
at:9:30am Toronto time 6:30am in Vancouver 9:30am in Toronto
and New York 2:30pm in London 9:30pm in Hong Kong and Perth
The live webcast can be accessed through the following
link: https://edge.media-server.com/m6/p/44r6ckra
Analysts and interested investors are also invited to
participate and ask questions using the dial-in numbers below:
International: +1646 254 3360North American toll-free: 1877 280
2342UK toll-free: 0800 279 4992
Confirmation code: 5815693
The conference call and webcast will be available for
playback on Endeavour's website.
Click here to add Webcast reminder to
Outlook Calendar
CONTACT INFORMATION
Martino De Ciccio VP - Strategy & Investor Relations +44
203 640 8665 mdeciccio@endeavourmining.com |
DFH
Public Affairs in Toronto John Vincic, Senior Advisor (416)
206-0118 x.224 jvincic@dfhpublicaffairs.com Brunswick Group LLP
in London Carole Cable, Partner +44 7974 982 458
ccable@brunswickgroup.com |
ABOUT ENDEAVOUR MINING CORPORATION
Endeavour Mining is a TSX-listed intermediate
gold producer, focused on developing a portfolio of high quality
mines in the prolific West-African region, where it has established
a solid operational and construction track record.
Endeavour is ideally positioned as the major
pure West-African multi-operation gold mining company, operating 5
mines across Côte d'Ivoire (Agbaou and Ity), Burkina Faso (Karma),
Mali (Tabakoto), and Ghana (Nzema). In 2017, it expects to produce
between 500koz and 530koz at an AISC of US$855 to US$900/oz,
following the full-year deconsolidation of the discontinued Nzema
mine. Endeavour is currently building its Houndé project in Burkina
Faso, which is expected to commence production in Q4-2017 and to
become its flagship low-cost mine with an average annual production
of 190koz at an AISC of US$709/oz over an initial 10-year mine
life, based on reserves. The development of the Houndé and Ity CIL
projects are expected to lift Endeavour's group production to
+900kozpa and decrease its average AISC to circa $800/oz by 2019,
while exploration aims to extend all mine lives to +10 years.
Corporate Office: 5 Young St, Kensington,
London W8 5EH, UK
This news release contains "forward-looking
statements" including but not limited to, statements with respect
to Endeavour's plans and operating performance, the estimation of
mineral reserves and resources, the timing and amount of estimated
future production, costs of future production, future capital
expenditures, and the success of exploration activities. Generally,
these forward-looking statements can be identified by the use of
forward-looking terminology such as "expects", "expected",
"budgeted", "forecasts", and "anticipates". Forward-looking
statements, while based on management's best estimates and
assumptions, are subject to risks and uncertainties that may cause
actual results to be materially different from those expressed or
implied by such forward-looking statements, including but not
limited to: risks related to the successful integration of
acquisitions; risks related to international operations; risks
related to general economic conditions and credit availability,
actual results of current exploration activities, unanticipated
reclamation expenses; changes in project parameters as plans
continue to be refined; fluctuations in prices of metals including
gold; fluctuations in foreign currency exchange rates, increases in
market prices of mining consumables, possible variations in ore
reserves, grade or recovery rates; failure of plant, equipment or
processes to operate as anticipated; accidents, labour disputes,
title disputes, claims and limitations on insurance coverage and
other risks of the mining industry; delays in the completion of
development or construction activities, changes in national and
local government regulation of mining operations, tax rules and
regulations, and political and economic developments in countries
in which Endeavour operates. Although Endeavour has attempted to
identify important factors that could cause actual results to
differ materially from those contained in forward-looking
statements, there may be other factors that cause results not to be
as anticipated, estimated or intended. There can be no assurance
that such statements will prove to be accurate, as actual results
and future events could differ materially from those anticipated in
such statements. Accordingly, readers should not place undue
reliance on forward-looking statements. Please refer to Endeavour's
most recent Annual Information Form filed under its profile at
www.sedar.com for further information respecting the risks
affecting Endeavour and its business. AISC, all-in sustaining costs
at the mine level, cash costs, operating EBITDA, all-in sustaining
margin, free cash flow, net free cash flow, free cash flow per
share, net debt, and adjusted earnings are non-GAAP financial
performance measures with no standard meaning under IFRS, further
discussed in the section Non-GAAP Measures in the most recently
filed Management Discussion and Analysis.
MINE PLAN
Attachments:
A photo accompanying this announcement is available at
http://www.globenewswire.com/NewsRoom/AttachmentNg/0c0ed29a-8b66-421c-b03b-c2fd52ee3f53
Attachments:
http://www.globenewswire.com/NewsRoom/AttachmentNg/f9d8eac9-b368-4b0b-9053-9854d5c60557
Attachments:
http://www.globenewswire.com/NewsRoom/AttachmentNg/a7f62c74-3438-48c6-a236-7e814f97c283
Attachments:
A photo accompanying this announcement is available at
http://www.globenewswire.com/NewsRoom/AttachmentNg/6a159db6-5088-4fb1-a1df-d79121ef5aa7
Attachments:
http://www.globenewswire.com/NewsRoom/AttachmentNg/69188139-a721-4cab-85b4-e09f3d04e8b1
Endeavour Mining (TSX:EDV)
Gráfico Histórico do Ativo
De Jan 2025 até Fev 2025
Endeavour Mining (TSX:EDV)
Gráfico Histórico do Ativo
De Fev 2024 até Fev 2025