Golden Dawn Provides Company Update
26 Março 2018 - 4:05AM
Wolf Wiese CEO of Golden Dawn Minerals Inc., (TSX-V:GOM)
(FRANKFURT:3G8A) (OTC:GDMRF) (the “
Company” or
“Golden Dawn”) provides the following activities
to be completed in 2018 to bring the Lexington Mine and Greenwood
Processing Plant on-stream, subject to meeting all conditions of
our existing permits and further funding. A short video of the
current activities is embedded in the following link:
http://iresourcenetwork.com/lexington-mine-update/
Q1 Activities
- The Lexington Mine has been
successfully dewatered and mostly cleaned out. Current activities
include geological and geotechnical assessments of the mine
workings. The geological work is aimed at improved understanding of
the geometry of the mineralized zones and major geological
structures. The geotechnical work is required to determine
appropriate ground control (rock bolting, screening etc.) and the
optimum sizes of mine openings and pillar sizes.
- The Lexington resource block model
has also been reviewed and improved and has been turned over to the
mine planning engineers. A first pass mine plan is expected
by mid April. This mine plan will be developed in conjunction
with the recent geotechnical work. This geotechnical input will be
invaluable to the mine plan to enable maximum extraction of the
resource in a safe manner.
- The mine ventilation plan will be
updated, and the necessary infrastructure will be placed in the
mine (surface and underground) to allow us to properly ventilate
operations of 200 tonnes per day (“tpd”). Additionally, the
ventilation plan will show us where the bottlenecks are for
increasing ventilation air to support a higher production
rate.
- Management continues to prepare all the necessary management
plans as required by the permits to operate the mine in a safe
manner.
Q2 Activities
- Staffing will be increased as
required for the activities scheduled through the pre-production
period.
- Mine activities will comprise the
following:
-
- Complete the repair of the West
Portal;
-
- Complete wiring and insulating the
Lexington maintenance shop;
-
- Continue repairs to the underground
equipment fleet (mobile and stationary) to ready for
operations;
-
- Repair of underground explosives
and detonator magazines, remobilization and stocking of surface
explosives/detonator magazines, refurbishing and stocking the
refuge station and excavating permanent mine sumps. A
sedimentation pond for mine discharge water will be built at the
east portal;
-
- Underground diamond drilling may be
initiated during this time to better define the mineralized zones
planned to be mined; and
-
- Extensive surface drilling on the
Golden Crown Mine Property is underway to increase current
resources. 38 diamond drill holes have ben drilled on this property
to date.
Q3 Activities
- Underground mine development will
be carried out beginning in July and mining of sufficient material
will be stockpiled and ready for the Zip mill to begin processing
in August.
- August: Mine operations will
ramp up to 6,000 tonnes per month by the end of August.
- September: The mine will be
operated at 200 tpd capacity.
- Prospecting on the entire Greenwood
Precious Metals property and further surface diamond drilling will
take place on the Golden Crown and other selected high priority
targets. The Company will follow up on potential intrusive
mineralization targets.
Q4 Activities
- October through December: It
is expected that 18,000 tonnes of ore will be mined and trucked to
the processing plant.
- In addition to providing mill feed
in September, the mine will also produce a bulk sample of material
that will be crushed at the Zip mill. A portion of this
material will be shipped to Kentucky for further testing of
pre-concentration sorting.
Zip Mill
- Q1-Q2: Mill offices, first
aid room and dry facility will all be purchased in the coming
months so that the site is fully equipped for refurbishing during
July.
- Staffing plans have been made and
will be implemented according to the activities scheduled through
the March to July pre-production period. A mill supervisor
will be hired on a consulting basis in Q2 to initiate and monitor
refurbishment and commissioning of the plant.
- Q3: The Zip mill will be
refurbished in July; production in August will average 100 tpd
(3,000 tonnes total) due to the usual challenges of starting a
plant and bringing it to full capacity of 6,000 tonnes per month by
September.
- The Company is working on
completing all the required conditions for permits, for the
operation of the Zip mill and Greenwood tailings impoundment
facility for the beginning of August. The Company is also working
with its consultants to fulfil environmental permitting
requirements for the Greenwood processing plant.
- Q4: The mill will be on-stream and
processing all of the Lexington Mine feed from September through
2018 year-end, a possible total of 24,000 tonnes.
- Note: The Lexington Mine has in
excess of 4000 meters of underground workings and ore development
completed, by our predecessors. One meter of 5x5 meters of
tunnelling costs between $4000-$6000.
Management is very satisfied with the progress
made towards commencing production at the Lexington Mine and
Greenwood Mill. It has been 18 months since the Company took
possession of the Lexington and Golden Crown Mines, and the 200/400
tpd mill. Permits have been obtained, the Lexington Mines has been
dewatered (which took longer than anticipated due to greater water
volume), the mill has been organized and readied to be operational
within a month’s notice, underground equipment has been repaired,
and the shop and offices at the portals of the Lexington Mine have
been rebuilt. The exploration program also continued, with 38 holes
drilled to date on the Golden Crown property to infill and extend
the current resource, plus transport and reorganization of about
30,000 metres of drill core from the three mines into one core
storage facility. The Company expects to meet all the
environmental and safety standards as required by the existing
permits, and looks forward to a promising start of its production
of gold and other metals in Q3.
The Company would like to clarify that its
decision to proceed to extract mineralized material from the Golden
Crown and Lexington deposits for processing at its facility located
at the Greenwood Precious Metals Project is not based on a
feasibility study. The Company cautions that, in such cases, there
is increased uncertainty and higher economic and technical risks of
failure.
Technical disclosure in this news release has
been approved by Dr. Mathew Ball, P.Geo., a Qualified Person as
defined by National Instrument 43-101, and Chief Operating Officer
of the Company.
On behalf of the Board of Directors:
GOLDEN DAWN MINERALS INC.Wolf
Wiese, President & CEO
For further information, please
contact:Corporate
Communications604-221-8936allinfo@goldendawnminerals.com
Neither the TSX Venture Exchange nor its
Regulation Services Provider (as that term is defined in the
policies of the TSX Venture Exchange) accepts responsibility for
the adequacy or accuracy of this news release.
Cautionary Note Regarding Forward
Looking Statements: Certain disclosure in this
release constitutes forward-looking statements. In making the
forward-looking statements in this release, the Company has applied
certain factors and assumptions that are based on the Company's
current beliefs as well as assumptions made by and information
currently available to the Company, including that the Company is
able to procure personnel, equipment and supplies required for its
exploration activities in sufficient quantities and on a timely
basis and that actual results of exploration activities are
consistent with management's expectations. Although the Company
considers these assumptions to be reasonable based on information
currently available to it, they may prove to be incorrect, and the
forward-looking statements in this release are subject to numerous
risks, uncertainties and other factors that may cause future
results to differ materially from those expressed or implied in
such forward-looking statements. Such risk factors include, among
others, that actual results of the Company's exploration activities
will be different than those expected by management and that the
Company will be unable to obtain financing or will experience
delays in obtaining any required government approvals or be unable
to procure required equipment and supplies in sufficient quantities
and on a timely basis. Readers are cautioned not to place undue
reliance on forward-looking statements. The Company does not
intend, and expressly disclaims any intention or obligation to,
update or revise any forward-looking statements whether as a result
of new information, future events or otherwise, except as required
by law. We seek safe harbor.
Golden Dawn Minerals (TSXV:GOM)
Gráfico Histórico do Ativo
De Nov 2024 até Dez 2024
Golden Dawn Minerals (TSXV:GOM)
Gráfico Histórico do Ativo
De Dez 2023 até Dez 2024