Wolf Wiese CEO of Golden Dawn Minerals Inc., (TSX-V:GOM)
(FRANKFURT:3G8B) (OTC:GDMRF) (the “
Company” or
“Golden Dawn”) provides the following update on
activities being completed to bring the Lexington Mine and
Greenwood Processing Plant on-stream. The Company is aiming
to initiate trial mining in August of 2018, then from October
through December, mining and processing of 18,000 tonnes of
material.
The Company is working diligently to meet all
conditions of existing permits to proceed to production. New
conditions were recently added by the Ministry of Mines and
Ministry of Environment, requiring new consultants and additional
staffing for GOM. Many new regulations have been put in place
since the mines and plant were constructed in 2008 to improve
environmental and safety standards and upgrades are required to
some of the infrastructure. BC has one of the highest safety
and environmental standards in the world.
Work Completed at the Lexington Mine:
- De-watering
The Lexington mine was successfully de-watered
in early January. Once the de-watering phase was completed
the mine contractor was released and the Company hired its own
mining crew to save costs. Operational pumping is now
underway and is being maintained by Company employees. For
the past two weeks the mine area has been in the middle of the
spring thaw, with snow melting and groundwater inflow to the mine
peaking. The mine crew is on duty to maintain the pumps.
- Mine Services
Work is progressing on building a new entrance
for the West Portal. The old portal entrance that had
collapsed was removed and the surface area cleaned of loose
material. Overburden was stripped back and stockpiled for
later reclamation. New mine timbers were received, and timber
sets were constructed for installation outside the portal.
The existing vent raise was retimbered and new ladders
installed.
A new roof was built for the mine mechanic shop
and a temporary power generator was installed. A mine
mechanic was hired and started work on rebuilding the underground
equipment fleet. Mine personnel carriers were refurbished, and fire
suppression systems were installed on the equipment. Most of
the fleet is in relatively good condition and can be refurbished
with minimal effort. New engines are required to comply with
new standards for underground mines. Other services, including a
portable generator, compressor, mine office, mine dry and toilet
facilities were installed at the East Portal to facilitate
de-watering.
- Technical
The main effort currently is on-going technical
work including geological mapping and sampling, geotechnical
assessment, and mine engineering.
Geological mapping is underway in the previously
mined areas that are still accessible. This work involves
washing the workings and detailed recording of rock types,
mineralized zones and fault structures. To date, 14 stope
areas have been mapped out of a total of 17 that are
accessible. Chip sampling has been conducted in the areas
mapped, with the first batch of samples dispatched to the assay
laboratory in April. The results of this work will be to
understand the controls on the mineralization, to aid grade control
efforts when mining, and to provide data for refinement of the
resource model.
At the same time, all the results from past
mining and exploration of the property are being reviewed.
Exploration targets for diamond drilling have been identified and
permit applications for exploration have been submitted for the
Lexington, Golden Crown, JD and Phoenix areas.
A geotechnical consultant was engaged to prepare
a Ground Control Management Plan. Testing of rock bolts and
geotechnical mapping was done in the mine. Initial parameters
were supplied to the mine engineering consultant for input into the
mining plan.
A geotechnical engineer was also engaged to
prepare a waste rock management plan. This will determine how
mine waste is classified and stored at surface.
A mine engineering consultancy was engaged to
prepare an initial mine plan based on the resource model.
This is a more detailed review than the PEA study, which considers
more accurate mining costs, application of different mining methods
in separate areas, and mining dilution based on individual stope
blocks. The output will be a tentative schedule for mine
development and production.
Work Planned at the Lexington mine:
The next tasks remaining to be completed before
mining at Lexington can proceed include the following:
- Rock bolting in existing drifts to secure ground support;
- Complete the West Portal refurbishment;
- Install mine ventilation and electrics;
- Re-establish the underground rescue station;
- Move power and compressed air to West Portal;
- Install new office trailer for technical staff;
- Install or refurbish larger mine dry;
- Complete wiring and insulating the mine maintenance shop;
- Acquire sufficient mine rescue equipment for full mining
crew;
- Repair of underground explosives and detonator magazines,
remobilization and stocking of surface explosives/detonator
magazines;
- Complete updates to permit (Environmental Management System,
Mine Plan, Ground Control, Waste Dump, etc);
Work is also being done to ready the Greenwood
process plant for start-up, including:
- Installation of new offices and washroom trailers;
- Health and safety audits and programs;
- Updates to permit for Environmental Management, mine plan,
closure plan and new installations;
- Review and approval of existing electrical and mechanical
installations;
- Geotechnical design for permitting an upgrade of the facility
to 400 TPD;
- Staffing;
In addition to providing mill feed in September,
the mine will also produce a bulk sample of material that will be
crushed at the Zip mill. A portion of this material will be
shipped to Kentucky for further testing of pre-concentration
sorting.
Technical disclosure in this news release has
been approved by Dr. Mathew Ball, P.Geo., a Qualified Person as
defined by National Instrument 43-101, and Chief Operating Officer
of the Company.
On behalf of the Board of Directors:
GOLDEN DAWN MINERALS INC.Wolf
Wiese, President & CEO
For further information, please
contact:Corporate
Communications604-221-8936allinfo@goldendawnminerals.com
Neither the TSX Venture Exchange nor its
Regulation Services Provider (as that term is defined in the
policies of the TSX Venture Exchange) accepts responsibility for
the adequacy or accuracy of this news release.
Cautionary Note Regarding Forward
Looking Statements: Certain disclosure in this
release constitutes forward-looking statements. In making the
forward-looking statements in this release, the Company has applied
certain factors and assumptions that are based on the Company's
current beliefs as well as assumptions made by and information
currently available to the Company, including that the Company is
able to procure personnel, equipment and supplies required for its
exploration activities in sufficient quantities and on a timely
basis and that actual results of exploration activities are
consistent with management's expectations. Although the Company
considers these assumptions to be reasonable based on information
currently available to it, they may prove to be incorrect, and the
forward-looking statements in this release are subject to numerous
risks, uncertainties and other factors that may cause future
results to differ materially from those expressed or implied in
such forward-looking statements. Such risk factors include, among
others, that actual results of the Company's exploration activities
will be different than those expected by management and that the
Company will be unable to obtain financing or will experience
delays in obtaining any required government approvals or be unable
to procure required equipment and supplies in sufficient quantities
and on a timely basis. Readers are cautioned not to place undue
reliance on forward-looking statements. The Company does not
intend, and expressly disclaims any intention or obligation to,
update or revise any forward-looking statements whether as a result
of new information, future events or otherwise, except as required
by law. We seek safe harbor.
Golden Dawn Minerals (TSXV:GOM)
Gráfico Histórico do Ativo
De Nov 2024 até Dez 2024
Golden Dawn Minerals (TSXV:GOM)
Gráfico Histórico do Ativo
De Dez 2023 até Dez 2024