Sabina Gold & Silver Corp (SBB.T/SGSVF.OTCQX), (“Sabina” or the
“Company”) is pleased to report on the status of the Updated
Feasibility Study (“UFS”) on the proposed Goose Mine at its
100%-owned Back River Gold Project (“Back River” or the “Project”)
in Nunavut, Canada.
“Work continues to advance the updated Back
River resource estimate and Goose Project UFS for delivery in Q1,
2021,” said Bruce McLeod, President & CEO. “The
significant exploration success we have delivered since the
September 2015 feasibility study has been incorporated into the
resource estimate and mine plan, along with many other improvements
to the Project. This work continues to showcase the
Goose Mine as a very compelling project: the first of many
opportunities on Sabina’s 80km long Back River belt.
Work continues at site, and we expect to complete our
objectives for civil works to enable collaring our exploration
decline in the spring of next year. We anticipate mobilizing
out of camp in mid December.”
UPDATED FEASIBILITY STUDY
Introduction:
The September 2015 feasibility study (“2015 FS”)
envisioned a 3,000 tonne per day (“TPD”) mine producing
approximately 200,000 ounces a year over an 11.8-year mine life
from a series of three open pits and one underground at the Goose
site. Since that time, material discoveries and significant
resource extensions have been made at the Project, including the
two separate high-grade underground zones at Umwelt. Internal
studies were undertaken to determine what potential improvement
these areas might have to meaningfully increase the production
profile and/or mine life, with a similar or marginally increased
throughput, through a combination of open pit and underground mines
at the Goose site. The Company is well advanced on the UFS
which is expected in early Q1, 2021. The goal for the UFS is
to increase gold production on an annual and total life of mine
basis, which is expected to improve the overall financial metrics
of the Project over the already positive economics demonstrated in
the 2015 FS
Resource:
Since the last Back River resource statement was
completed, Sabina has drilled over 50,000 meters at the Goose
site. This drilling has resulted in several discoveries as
well as expansion of the known mineralized horizons at the Project.
In 2020, exploration and infill drilling focused on areas
that could positively impact the mine plan. Due to COVID,
drilling to enable conversion to reserves was not achievable in
2020 for all of the new deposit areas. However, the new
resource estimates will include updates to: Umwelt; Goose Main;
Echo; and new inferred resources from the Nuvuyak and Llama
Extension deposits. The George open pit resources will also
be updated to reflect current metal price assumptions.
Reserve, Mining methods and Market
Studies:
This Exploration success since the 2015 FS has
enabled Sabina to re-envision the mine plan in the UFS. With
early access to the high grade V2 Zone located below the Umwelt
open pit, Sabina will add high-grade underground feed to the
process plant early in the mine life and recover more higher-grade
reserves earlier than envisioned in the 2015 FS. The mine
plan will incorporate cut and fill mining methods plus cemented
rock in select areas of the interface between the open pit and
underground deposits, enabling production from areas previously
excluded. The mining sequence in the UFS mine plan compared
to the 2015 FS is outlined below.
Table 1: UFS re-envisioned mine plan relative to
the 2015 Feasibility Study
Mine Production Plan Sequencing |
2015 Feasibility Study |
2021 UFS |
Umwelt Open Pit |
Echo Pit |
Llama Open Pit |
Umwelt Underground |
Goose Open Pit |
Umwelt Open Pit |
Umwelt Underground |
Llama Open Pit |
|
Llama Underground |
|
Goose Main Open Pit |
|
Goose Main Underground |
A photo accompanying this announcement is
available at
https://www.globenewswire.com/NewsRoom/AttachmentNg/444079fb-dfed-4046-a372-6458768b5b80
Processing, Test Work and
Recoveries:
Since the 2015 FS, Sabina has undertaken
additional metallurgical test work programs which have provided
better certainty to the process plant design. These programs
included: secondary grinding; leach vs flotation; detox; gravity
recovery; and tailings and water quality test work. Results
have confirmed the process plant operating parameters as well
modest improvements to our baseline recoveries for most
deposits. The process plant is designed as a traditional
3,000 TPD, primary/secondary/tertiary crushing, primary/secondary
grinding, gravity separation, carbon-in-pulp, leach and detox
plant. The plant has a design head grade between 6 and 12gpt
with the capability to increase through-put in later years.
Infrastructure:
Sabina has made extensive improvements on all
aspects of the Project scope. A brief outline of the
significant improvements are as follows:
- Inaugural winter ice road and sealifts completed, gaining
logistical, operational and cost experience which will be
incorporated into the UFS;
- Significant reduction in earthworks for water management
structures, (particularly earthworks scheduled for winter
construction in the 2015 FS), thus reducing overall Project
execution and schedule risk;
- Larger accommodation complex for an increased work force which
enables underground and surface mining operations to run
concurrently with construction;
- Enclosed power plant with larger and fewer power units
generating heat recovery providing additional reliability for the
power supply during operations;
- Shorter tailings lines which will reduce operational risk;
- A Sabina owned, on site oxygen plant and laboratory versus the
previous model contemplated; and
- Three years of on-site seasonal construction experience
providing improved understanding of operating in our northern
environment which will be applied to estimated costs.
Environmental, Permitting and
Social:
The Company is now in receipt of all major
authorizations for construction and operations. More recent
significant advances in permitting include: the final Project
Certificate, received on December 19, 2017; the Type A Water
License, received on November 14, 2018; and the listing to enable
deposition of tailings on Schedule 2 of the Metals and Diamond
Mining Effluent Regulations, received on June 25, 2020. All
project modifications were contemplated when the Company submitted
its 2020 permit modification package to the regulatory
authorities. Sabina continues to support the local
communities within the region during COVID and continues to receive
local support for the project.
CAPEX, OPEX and Financial:
Sabina is maintaining an initial nameplate
throughput of 3,000 TPD in the UFS but the study will include an
expansion to 4,000 TPD from sustaining capital in years four to
five. As per the UFS guidelines, the team is achieving an
AACE class III CAPEX estimate with the intention of converting to a
class IV estimate for the process plant and selected aspects of
remaining project scope after issuing the UFS. This will
enable Sabina to obtain a fixed price proposal for construction
execution. Completing the UFS while concurrently completing
detail engineering will ensure details typically unrealized during
a traditional feasibility study will be accurately represented and
contribute to the overall accuracy of the study. The CAPEX
and OPEX are being built up from first principles to reflect an
updated execution strategy of a modified EPCM with Sabina
self-managing as the Company has over the last three years.
The inclusion of early underground mining activity along with price
escalation and inflation, is expected to increase the overall CAPEX
and OPEX when compared to the 2015 FS. The impact of an
increased gold price and higher recovered ounces on an annual and
life of mine basis are expected to improve the project economics
when compared to the 2015 FS.
Timeline:
Sacré-Davey Engineering Inc., currently heading
detail engineering, will be the overall author with the following
companies contributing to the UFS.
Firm |
Area of responsibility |
AMC Consultants |
Resource Estimate |
Knight Piésold Consulting |
Geo-mechanical & Site water management Studies |
Caneco |
Process Plant and Metallurgy |
SRK Consulting |
Water management Structures |
Mining Plus |
Mining updates |
DT Engineers |
Balance of Plant Engineering |
CGT Industrial Ltd |
Construction estimates |
ALS & BaseMet lab |
Environmental and mineral processing lab works |
Sabina is working with Sacré-Davey Engineering
Inc. and the other QP’s for delivery of the UFS in early Q1 2021
and detailed engineering to 90% by the end of Q1 2021.
Sabina Gold & Silver
Corp.
Sabina Gold & Silver Corp. is well-financed
and is an emerging precious metals company with district scale,
advanced, high grade gold assets in one of the world’s newest,
politically stable mining jurisdictions: Nunavut, Canada.
Sabina released a Feasibility Study on its 100%
owned Back River Gold Project which presents a project that has
been designed on a fit-for purpose basis, with the potential to
produce ~200,000 ounces a year for ~11 years with a rapid payback
of 2.9 years (see “Technical Report for the Initial Project
Feasibility Study on the Back River Gold Property, Nunavut, Canada”
dated October 28, 2015).
The Project received its final Project
Certificate on December 19, 2017. The Project received
its Type A Water License on November 14, 2018 and its listing to
enable deposition of tailings on Schedule 2 of the Metals and
Diamond Mining Effluent Regulations on June 25, 2020. The
Company is now in receipt of all major authorizations for
construction and operations.
In addition to Back River, Sabina also owns a
significant silver royalty on Glencore’s Hackett River
Project. The silver royalty on Hackett River’s silver
production is comprised of 22.5% of the first 190 million ounces
produced and 12.5% of all silver produced thereafter.
For further information please contact:
Nicole Hoeller, Vice-President, Communications:
1 888 648-4218
nhoeller@sabinagoldsilver.com
Forward Looking InformationThis
news release contains “forward-looking information” within the
meaning of applicable securities laws (the “forward-looking
statements”), including our belief as to the extent, results and
timing of and various studies relating to engineering studies,
infrastructure improvement activities, exploration results and
permitting and licensing outcomes. These forward-looking statements
are made as of the date of this news release. Readers are cautioned
not to place undue reliance on forward-looking statements, as there
can be no assurance that the future circumstances, outcomes or
results anticipated in or implied by such forward-looking
statements will occur or that plans, intentions or expectations
upon which the forward-looking statements are based will occur.
While we have based these forward-looking statements on our
expectations about future events as at the date that such
statements were prepared, the statements are not a guarantee that
such future events will occur and are subject to risks,
uncertainties, assumptions and other factors which could cause
events or outcomes to differ materially from those expressed or
implied by such forward-looking statements. Such factors and
assumptions include, among others, the effects of general economic
conditions, commodity prices, changing foreign exchange rates and
actions by government and regulatory authorities and misjudgments
in the course of preparing forward-looking statements. In addition,
there are known and unknown risk factors which could cause our
actual results, performance or achievements to differ materially
from any future results, performance or achievements expressed or
implied by the forward-looking statements. Known risk factors
include risks associated with exploration and project development;
the need for additional financing; the calculation of mineral
resources and reserves; operational risks associated with mining
and mineral processing; fluctuations in metal prices; title
matters; government regulation; obtaining and renewing necessary
licenses and permits; environmental liability and insurance;
reliance on key personnel; the potential for conflicts of interest
among certain of our officers or directors; the absence of
dividends; currency fluctuations; labour disputes; competition;
dilution; the volatility of the our common share price and volume;
future sales of shares by existing shareholders; and other risks
and uncertainties, including those relating to the Back River
Project and general risks associated with the mineral exploration
and development industry described in our Annual Information Form,
financial statements and MD&A for the fiscal period ended
December 31, 2019 filed with the Canadian Securities Administrators
and available at www.sedar.com. Although we have attempted to
identify important factors that could cause actual actions, events
or results to differ materially from those described in
forward-looking statements, there may be other factors that cause
actions, events or results not to be as anticipated, estimated or
intended. There can be no assurance that forward-looking statements
will prove to be accurate, as actual results and future events
could differ materially from those anticipated in such statements.
Accordingly, readers should not place undue reliance on
forward-looking statements. We are under no obligation to update or
alter any forward-looking statements except as required under
applicable securities laws. This news release has been authorized
by the undersigned on behalf of Sabina Gold & Silver Corp.
Bruce McLeod, President & CEOSuite 1800 – Two
Bentall Centre555 Burrard StreetVancouver, BC V7X 1M7Tel 604
998-4175 Fax 604
998-1051http://www.sabinagoldsilver.com
Sabina Gold and Silver (TSX:SBB)
Gráfico Histórico do Ativo
De Dez 2024 até Jan 2025
Sabina Gold and Silver (TSX:SBB)
Gráfico Histórico do Ativo
De Jan 2024 até Jan 2025