Sabina Gold & Silver Corp. (“Sabina”) or (the “Company”) (SBB –
TSX/ SGSVF - OTCQX) announces optimization to the plan for its
Goose Mine at the Company’s 100% owned Back River District in
Nunavut, Canada.
The Updated Feasibility Study (“UFS”) announced
in February 2021 contemplated a mill producing 3,000 tonnes per day
(“tpd”) for the first two years, increasing to 4,000 tpd in year
two with a sustaining capital cost for the expansion of ~C$17m.
As part of the UFS, an initial 4,000 tpd mill
was considered. However, at the time of the UFS work the settled
tailings density was based on the previous pre-leach thickener test
work. This work resulted in a lower Echo open pit tailings capacity
and a decision to delay the mill expansion timeline.
Since the UFS, completion of detailed
geotechnical test work on the tailings samples and the
inclusion of a high-capacity tailings thickener, the tailings
storage capacity of the Echo open pit has increased sufficiently to
enable the decision to construct the mill at a 4,000 tpd capacity
at the outset. This, in addition to optimized equipment selection
and detailed engineering has reduced the cost of the expansion from
C$17m to C$10m when compared to the UFS.
The current mine plan includes the complete
mining of the Echo open pit and seven quarters of mining from the
Umwelt open pit during the construction phase of the project. As
per the UFS, this provides 2.2 million tonnes (“Mt”) of stockpiled
ore containing 373,000 ounces of gold, including 936,000 high grade
tonnes at 8.4 g/t gold prior to commissioning of the mill. In
addition, the current mine plan includes an additional 3.5 Mt mined
in the first 3 years of operations, enabling 4,000 tpd of mill
capacity without the need to increase the mining rate or modify the
existing mine plan.
The Back River permitting was completed based on
a maximum 6,000 tpd mill capacity and thus no additional permitting
or authorizations are required for this modification.
“We are pleased that additional test work has
resulted in this conclusion,” said Bruce McLeod, President &
CEO “it is the option that makes sense from an operational and cost
perspective and has the potential to improve payback by delivering
increased gold production in the earlier stages of the mine life.
We look forward to providing additional project updates through the
year.”
Qualified Persons Statement
Mr. Vincy Benjamin, P. Eng, PMP, and Director of
Engineering for Sabina Gold & Silver Corp. is a Qualified
Person within the meaning of NI 43-101 and has reviewed the
technical content of this news release and has approved its
dissemination.
About Sabina
Sabina Gold & Silver Corp. is an emerging
gold mining that 100% owns the district scale, advanced, high grade
Back River Gold District in Nunavut, Canada.
Sabina recently filed an Updated Feasibility
Study (the “UFS”) on its first mine on the
district, the Goose Mine, which presents a project that will
produce ~223,000 ounces of gold a year (first five years average of
287,000 ounces a year with peak production of 312,000 ounces in
year three) for ~15 years with a rapid payback of 2.3 years, with a
post-tax IRR of ~28% and NPV5% of C$1.1B. See “National Instrument
(NI) 43-101 Technical Report – 2021 Updated Feasibility Study for
the Goose Project at the Back River Gold District, Nunavut, Canada”
dated March 3, 2021.
The Project received its final major
authorization on June 25, 2020 and is now in receipt of all major
permits and authorizations for construction and operations.
The Company is also very committed to its Inuit
stakeholders, with Inuit employment and opportunities a focus. The
Company has signed a 20-year renewable land use agreement with the
Kitikmeot Inuit Association and has committed to various
sustainability initiatives under the agreement.
In February 2022, the Company announced it had
completed a comprehensive project financing package for US$520
million comprised of:
- A US$225 million senior secured
debt facility with Orion Mine Finance;
- A US$75 million gold prepay
facility with Orion Mine Finance;
- A US$125 million gold stream
arrangement with Wheaton Precious Metals; and
- A US$95 million private placement
of Sabina Common shares subscribed to by both Orion and Wheaton
Precious Metals.
In addition to Back River, Sabina also owns a
significant silver royalty on Glencore’s Hackett River Project. The
silver royalty on Hackett River’s silver production is comprised of
22.5% of the first 190 million ounces produced and 12.5% of all
silver produced thereafter.
For further information please contact:Nicole
Hoeller, Vice-President, Communications: 1 888
648-4218
nhoeller@sabinagoldsilver.com
Forward Looking Information
This news release contains “forward-looking
information” within the meaning of applicable securities laws (the
“forward-looking statements”), including, but not limited to, the
commencement of construction of the Project, the timing for
completion of construction, the creation of value for stakeholders,
the timing and completion of the second and third tranches of the
private placement and the projections and assumptions of the
results of the UFS. These forward-looking statements are made as of
the date of this news release. Readers are cautioned not to place
undue reliance on forward-looking statements, as there can be no
assurance that the future circumstances, outcomes or results
anticipated in or implied by such forward-looking statements will
occur or that plans, intentions or expectations upon which the
forward-looking statements are based will occur. While we have
based these forward-looking statements on our expectations about
future events as at the date that such statements were prepared,
the statements are not a guarantee that such future events will
occur and are subject to risks, uncertainties, assumptions and
other factors which could cause events or outcomes to differ
materially from those expressed or implied by such forward-looking
statements. Such factors and assumptions include, among others, the
availability of equity financing on reasonable terms, the approval
of the private placement to Orion and Wheaton by Sabina’s
shareholders, the uncertainty of construction, production,
development plans and costs estimates for the Back River Gold
Project; discrepancies between actual and estimated mineral
reserves and mineral resources, between actual and estimated
development and operating costs; the interpretation of drill,
metallurgical testing and other exploration results; the ability of
the Company to retain its key management employees and skilled and
experienced personnel; exploration, development and mining risks
and the inherently dangerous nature of the mining industry, and the
risk of inadequate insurance or inability to obtain insurance to
cover these risks and other risks and uncertainties; property and
mineral title risks including defective title to mineral claims or
property; the effects of general economic conditions, commodity
prices, changing foreign exchange rates and actions by government
and regulatory authorities; and misjudgments in the course of
preparing forward-looking statements. In addition, there are known
and unknown risk factors which could cause our actual results,
performance or achievements to differ materially from any future
results, performance or achievements expressed or implied by the
forward-looking statements. Known risk factors include risks
associated with exploration and project development; the need for
additional financing; the calculation of mineral resources and
reserves; operational risks associated with mining and mineral
processing; fluctuations in metal prices; title matters; government
regulation; obtaining and renewing necessary licenses and permits;
environmental liability and insurance; reliance on key personnel;
the potential for conflicts of interest among certain of our
officers or directors; the absence of dividends; currency
fluctuations; labour disputes; competition; dilution; the
volatility of the our common share price and volume; future sales
of shares by existing shareholders; and other risks and
uncertainties, including those relating to the Back River Project
and general risks associated with the mineral exploration and
development industry described in our Annual Information Form,
financial statements and MD&A for the fiscal period ended
December 31, 2020 filed with the Canadian Securities Administrators
and available at www.sedar.com. Although we have attempted to
identify important factors that could cause actual actions, events
or results to differ materially from those described in
forward-looking statements, there may be other factors that cause
actions, events or results not to be as anticipated, estimated or
intended. There can be no assurance that forward-looking statements
will prove to be accurate, as actual results and future events
could differ materially from those anticipated in such statements.
Accordingly, readers should not place undue reliance on
forward-looking statements. We are under no obligation to update or
alter any forward-looking statements except as required under
applicable securities laws.
Sabina Gold and Silver (TSX:SBB)
Gráfico Histórico do Ativo
De Dez 2024 até Jan 2025
Sabina Gold and Silver (TSX:SBB)
Gráfico Histórico do Ativo
De Jan 2024 até Jan 2025