Sabina Gold & Silver Corp. (“Sabina”) or (the “Company”) (SBB –
TSX/ SGSVF - OTCQX) provides an update on advancements of the Goose
Mine development at the Company’s 100% owned Back River Gold
District in Nunavut, Canada. The Goose Mine is the Company’s first
mine on the 80 km long Back River Gold District, a
multi-generational mining district already with a high-grade world
class gold endowment.
The first quarter of 2022 culminated in one of
the most important milestones for the Company to date. Debt,
streaming and equity financings were completed with a total of over
C$800 million arranged, well in excess of the requirements of the
2021 Updated Feasibility Study (“UFS”).
More importantly, with financing in hand,
pre-construction, logistical and procurement activities have
accelerated. In anticipation of the financing, Sabina had prepared
tender documents and purchase orders which enabled the Company to
quickly procure critical components necessary for this year’s
sealift.
The UFS CAPEX estimate was C$610 million. Of
that, approximately C$218 million was identified as direct
equipment and materials purchases. Since last year, Sabina
has procured, or has committed agreements to procure, just over 70%
of all direct purchases identified in the UFS. Reconciliation
on purchases have seen an average overall inflationary escalation
of 14% since March of 2021, with a 20% escalation on the purchases
made in 2022. Efforts now focus on securing the remaining 30%
(C$62 million) of materials and equipment.
Earthworks at the plant site are ~67% complete,
which reflects an overall Project civil works completion rate of
~40%. To date, the Project is trending an ~10% quantity reduction
from UFS estimates.
“Inflation and global supply chain issues have
impacted all new capital investment projects and Sabina continues
to monitor these potential impacts as we develop the Goose Mine,”
said Bruce McLeod, President & CEO. “We are fortunate that our
strategy of pre-planning and accelerating procurement efforts has
reduced our exposure to inflationary impacts.”
Advancement Highlights and Schedule and
Cost De-risking Events
Engineering
- FLSmidth (“FLS”) has been chosen to supply the key equipment
for the Goose Mine processing flowsheet. The equipment package is
valued at approximately US$39 million and is due to be delivered by
mid-2023, for implementation ahead of the mine start-up date of Q1,
2025;
- CGT Industrial (“CGT”) has provided Sabina with a fixed priced
proposal of C$130 million, with an agreed rise and fall mechanism,
for materials and consumables for the process plant. These
components make up approximately 85% of the direct works on site.
The proposal is comparable to within 5% of the feasibility study
estimate;
- The team is preparing to move on to the design concept for the
Echo open pit, which is intended to be pre-mined to enable initial
tailings storage. The advanced mining of the Echo and Umwelt pits
will also result in approximately two years of stock-piled feed for
the mill prior to commencement of operations; and
- Detail engineering is reaching 85% complete project wide with
remaining engineering activities focused on vendor data updates as
procurement activity progresses.
Procurement
Approximately C$157 million of C$218 million (72%)
of materials and equipment required for the project (per UFS) has
already been procured.
Purchased or committed items include:
- 90% of mining fleet;
- Entire process plant equipment at 4000 TPD;
- Permanent accommodation complex (500 units) with kitchen and
recreation center;
- 95% of building envelope steel (by weight) and cladding;
- 100% of project explosives required for construction;
- Cranes and major construction support equipment;
- 95% project cement & rebar – with concrete batch plant
available on site;
- 80% of secondary structural steel for the process plant and
process piping;
- 100% of all tailing, reclaim and freshwater piping for the
project (~11.5Km of piping);
- All conveyor galleries and arctic corridors;
- Electrical E-houses complete with MCC and VFD (5 of 6 will be
on 2022 sealift);
- Electrical switch gear for the Powerhouse;
- Water, sewer and waste systems;
- HVAC unit and Dust collections systems;
- Fuel dispensing and offloading system for Goose & Port
sites;
- All equipment for double heading winter ice road construction
on site;
- Fully functional aggregate crusher and washer unit on
site;
- 24 MW (N+2 configuration) Power plant cogeneration system with
boilers and ancillary equipment from Toromont;
- One ten-million and one five-million liter fuel storage tanks
at each of Goose and Port sites, respectively; and
- Liner requirements for all water management structures
procured.
Sabina has approximately C$62 million remaining
to be spent on procurement (based on the UFS) which will have
exposure to the current inflationary environment. These items
include:
- Platework, pumps and tanks insulation -materials for which
engineering is completed and quotes are being finalized;
- Electrical bulks and cable tray;
- Electrical miscellaneous equipment (process plant and
powerplant);
- PLC controls systems;
- Instrumentation for the project; and
- Communication systems.
Supply chain and Sealift
Supply chain resilience will continue to require
expertise, novel solutions and strong collaboration among Sabina
and its suppliers. Key strategies include diversification of
suppliers, monitoring production capabilities and transportation
processes, as well as finding alternative materials and
nontraditional partnerships. To this end, Sabina has implemented
the following:
- Ensuring dedicated internal resources, including specialized
expeditors, to monitor progress on fabrication of equipment
procured;
- Co-ordinating with CGT during the procurement phase of all
critical fabrication items to de-risk the construction schedule at
site;
- Reviewing fuel supply proposals for 2022 sealift;
- Securing sealift carriers at both East and West
transport/consolidation points for the 2022 sealift program;
and
- Completing the installation of a fully functional hard wall
camp at Port to support activities in 2022.
Although supply chain issues have impacted
delivery dates, through advance planning, all major equipment
required is anticipated to arrive in time for this year’s
sealift.
Civil Works & Logistics
Considerable pre-development activities have
already been completed at the Goose and Port sites. This work
includes:
- ~40% of overall project and ~67% of plant site civil
works;
- Construction of two 10 million-liter fuel tanks constructed
(Port and Goose);
- ~20km of all weather roads completed at Project;
- Pads complete for permanent camp, plant and fuel storage;
- Approx. 25,000m2 of additional laydown area created at the
Port;
- New hard wall camp at Port and forward camps established;
- Esker harvesting and placement for sub-base prep along winter
ice road route to improve future construction campaigns; and
- 700 meters of underground exploration ramp completed at
Umwelt.
With surface construction season commencing,
Sabina is preparing to mobilize crews to further advance civil
works on site. Budgeting and scheduling is nearing completion and
will be announced in the coming weeks.
Planning is well underway for the marshalling of
procured equipment and supplies, at both East and West transport
locations, for the 2022 sealift campaign in the late summer of this
year.
SABINA GOLD & SILVER
CORP
Sabina Gold & Silver Corp. is an emerging
gold mining company that owns 100% of the district scale, advanced,
high grade Back River Gold District in Nunavut, Canada.
Sabina filed an Updated Feasibility Study (the
“UFS”) on its first mine on the district, the Goose Mine, which
presents a project that will produce ~223,000 ounces of gold a year
(first five years average of 287,000 ounces a year with peak
production of 312,000 ounces in year three) for ~15 years with a
rapid payback of 2.3 years, with a post-tax IRR of ~28% and NPV5%
of C$1.1B at a gold price of $1,600 USD. See “National Instrument
(NI) 43-101 Technical Report – 2021 Updated Feasibility Study for
the Goose Project at the Back River Gold District, Nunavut, Canada”
dated March 3, 2021.
The Project has received all major permits and
authorizations for construction and operations.
The Company has arranged a comprehensive project
financing package comprised of:
- A US$425 million senior secured debt facility, gold prepay and
stream package with Orion Mine Finance and Wheaton Precious Metals
Corp.; and
- US$221 million in equity including Zhaojin’s
participation.
The Company is also very committed to its Inuit
stakeholders, with Inuit employment and opportunities a focus. The
Company has signed a 20-year renewable land use agreement with the
Kitikmeot Inuit Association and has committed to various
sustainability initiatives under the agreement.
The Company continues to advance exploration and
project optimization, including advancing the planned plant
expansion to 4,000 tpd from Year two to initial startup.
All news releases and further information can be
found on the Company’s website at www.sabinagoldsilver.com or on
SEDAR at www.sedar.com. All technical reports have been filed on
www.sedar.com
For further information please contact:
Nicole Hoeller, Vice-President,
Communications: 1
888 648-4218
nhoeller@sabinagoldsilver.com
Forward Looking Information
This news release contains “forward-looking information” within the
meaning of applicable securities laws (the “forward-looking
statements”), including, but not limited to, statements
related to the expected use of proceeds of the Offering and the
projections and assumptions of the results of the UFS. These
forward-looking statements are made as of the date of this news
release. Readers are cautioned not to place undue reliance on
forward-looking statements, as there can be no assurance that the
future circumstances, outcomes or results anticipated in or implied
by such forward-looking statements will occur or that plans,
intentions or expectations upon which the forward-looking
statements are based will occur. While we have based these
forward-looking statements on our expectations about future events
as at the date that such statements were prepared, the statements
are not a guarantee that such future events will occur and are
subject to risks, uncertainties, assumptions and other factors
which could cause events or outcomes to differ materially from
those expressed or implied by such forward-looking statements. Such
factors and assumptions include, among others, the uncertainty of
production, development plans and costs estimates for the Back
River Gold Project; discrepancies between actual and estimated
mineral reserves and mineral resources, between actual and
estimated development and operating costs; the interpretation of
drill, metallurgical testing and other exploration results; the
ability of the Company to retain its key management employees and
skilled and experienced personnel; exploration, development and
mining risks and the inherently dangerous nature of the mining
industry, and the risk of inadequate insurance or inability to
obtain insurance to cover these risks and other risks and
uncertainties; property and mineral title risks including defective
title to mineral claims or property; the effects of general
economic conditions, commodity prices, changing foreign exchange
rates and actions by government and regulatory authorities; and
misjudgments in the course of preparing forward-looking statements.
In addition, there are known and unknown risk factors which could
cause our actual results, performance or achievements to differ
materially from any future results, performance or achievements
expressed or implied by the forward-looking statements. Known risk
factors include risks associated with exploration and project
development; the need for additional financing; the calculation of
mineral resources and reserves; operational risks associated with
mining and mineral processing; fluctuations in metal prices; title
matters; government regulation; obtaining and renewing necessary
licenses and permits; environmental liability and insurance;
reliance on key personnel; the potential for conflicts of interest
among certain of our officers or directors; the absence of
dividends; currency fluctuations; labour disputes; competition;
dilution; the volatility of the our common share price and volume;
future sales of shares by existing shareholders; and other risks
and uncertainties, including those relating to the Back River
Project and general risks associated with the mineral exploration
and development industry described in our Annual Information Form,
financial statements and MD&A for the fiscal period ended
December 31, 2021 filed with the Canadian Securities Administrators
and available at www.sedar.com. Although we have attempted to
identify important factors that could cause actual actions, events
or results to differ materially from those described in
forward-looking statements, there may be other factors that cause
actions, events or results not to be as anticipated, estimated or
intended. There can be no assurance that forward-looking statements
will prove to be accurate, as actual results and future events
could differ materially from those anticipated in such statements.
Accordingly, readers should not place undue reliance on
forward-looking statements. We are under no obligation to update or
alter any forward-looking statements except as required under
applicable securities laws.
Bruce McLeod, President & CEO 1800-555
Burrard Street, Two Bentall Centre Vancouver, BC V7X 1M9 Tel 604
998-4175 Fax 604 998-1051
http://www.sabinagoldsilver.com
Sabina Gold and Silver (TSX:SBB)
Gráfico Histórico do Ativo
De Dez 2024 até Jan 2025
Sabina Gold and Silver (TSX:SBB)
Gráfico Histórico do Ativo
De Jan 2024 até Jan 2025