Highland Copper Company Inc. (TSXV: HI; OTCQB: HDRSF)
(“
Highland” or the “
Company”) is
pleased to announce the results of the Preliminary Economic
Assessment (“
PEA”) and mineral resource estimate
for the White Pine North project (“
White Pine
North”) in Michigan, USA. The PEA demonstrates the robust
economic strength of this long-lived project.
Simultaneously, Highland is pleased to introduce
Kinterra Copper USA LLC (“Kinterra”) as a joint
venture (“JV”) partner on the project. Kinterra
will bring additional financial and technical strength required to
progress the project through to development. Kinterra has made a
cash payment of $30 million to Highland for a 66% stake in the
White Pine North project. Additionally, the joint venture has
agreed to spend a further $30 million to advance the project
through permitting, infill drilling and feasibility study.
Highland continues to make great progress in
2023. Combined, these announcements markedly improve Highland’s
prospects of advancing its larger White Pine North project while
focusing on moving its Copperwood project to construction and
operation. Highland believes this is positive for all stakeholders,
particularly the State of Michigan where Highland’s project
development is aligned with the State vision of electrification and
regional support for local communities.
Key highlights of the PEA and joint
venture transaction include (all figures in $USD):
-
Robust PEA Results Set Path for White Pine North
Advancement: With a significant increase in resource base,
an after-tax net present value (“NPV”) 8% of $821 million and an
after-tax internal rate of return (“IRR”) of 20.8%, the project
provides strong cash flow and leverage to copper price.
-
Kinterra Invests $30 Million for 66% of White Pine North,
Funds Available for Copperwood: The initial $30 million
proceeds from the joint venture arrangement allow Highland to
initiate early site works at the fully-permitted Copperwood
project, where Highland is focused on advancing to development and
production.
-
Additional $30 Million Commitment to Advance White Pine
North Permitting and Feasibility Study: Kinterra and
Highland, as JV partners, have agreed on a further $30 million
investment in the project to be funded by Kinterra. This consists
of $20 million representing Kinterra’s 66% pro rata expenditure, as
well as a $10 million unsecured loan to fund Highland’s pro rata
expenditure.
-
Highland Set to Advance Key Michigan Assets: With
key assets 100% owned Copperwood, 34% owned White Pine North, a
consolidated multi-billion pound resource base, and an additional
$30 million in liquidity, Highland looks forward to contributing to
critically needed US domestic copper supply through production
growth with these advanced-stage projects.
“Today’s announcements are transformational for
Highland Copper. While we continue to maintain our focus on the
fully-permitted Copperwood project, we have a viable path to
simultaneously advance the White Pine North project, keeping our
focus on near-term value creation by creating a new US copper
producer. As significant capital is required to develop both
projects, the joint venture arrangement allows us to move forward
without having to issue any shares, and unlocks tremendous value
for our shareholders. Kinterra recognizes the quality of our asset
base and is committed to working with Highland to advance White
Pine North. We look forward to working with Kinterra as partners to
progress this great asset.
We are pleased that all stakeholders, including
the various Michigan communities and our shareholders, will benefit
as we surface the significant asset value at both projects. We look
forward to updating the market as we advance.” stated Denis
Miville-Deschênes, President and CEO of Highland Copper.
Key Preliminary Economic Assessment
Highlights1,2
The PEA provides a base case assessment of
mining the mineral resources of the White Pine North Project. The
PEA considers White Pine North as a stand-alone project, where
potential synergies with Copperwood are not considered. The Project
is the extension of the historical White Pine mine which operated
from 1953 to 1995. The results of the White Pine North PEA
demonstrate the long-lived nature of the project with strong
economics and cash flows. Key highlights include the following,
with all figures being shown for 100% of the asset:
-
Strong Economic Returns with Leverage to Copper Price
Changes
- After-tax NPV8%
of $821 million (at $4.00/pound copper price)3
- 20.8% after-tax
IRR
- At $4.50/pound
copper price, after tax NPV8% of $1.2 billion and IRR of 25.4%
-
Improved NPV to Initial Capital Expenditure Ratio
- Initial capital
expenditures of $615 million, net of pre-production revenue of $265
million
- NPV to initial
capital expenditure ratio of 1.33
-
Significantly Increased Resource Base
- Indicated
mineral resource containing 3.5 billion pounds of copper (150.7
million tonnes at 1.05% Cu) and 65.5 million ounces of silver (13.5
g/t Ag)
- Inferred mineral
resource containing 2.2 billion pounds of copper (96.4 million
tonnes at 1.03% Cu) and 27.8 million ounces of silver (9.0 g/t
Ag)
- From the above
resource, mineralized material included in the mine plan of 115.8
million tonnes at 0.97% Cu and 11.09 g/t Ag, containing 2.47
billion pounds of copper and 41.3 million ounces of silver
-
Long-lived Asset with Strong Cash Flows
- Mine life of
21.8 years, including 21 months of ramp-up, with average annual LOM
payable copper production of 93.5 million pounds and 1.2 million
ounces of silver
- Life-of-mine
(“LOM”) average C1 cash costs of $1.58/lb, net of
by-product
- Undiscounted
average annual operating cash flow of approximately $210 million
and annual free cash flow of approximately $160 million (excluding
initial capital)
“The White Pine North project was able to
operate successfully for 50 years until the mid-1990s. The results
of the PEA indicate that the project could have another 22 or more
years of mining in the Upper Peninsula. We look forward to
continuing our work with the state of Michigan, making Copperwood
and White Pine North key economic contributors in the region,
becoming an important part of domestic copper supply and aiding in
the on-going goals of electrification in Michigan and the US” said
Denis Miville-Deschênes, President and CEO of Highland Copper.
1) The reader is
advised that a PEA is preliminary in nature and is intended to
provide only an initial, high-level review of the Project potential
and design options. The PEA mine plan and economic model include
numerous assumptions and the use of Inferred resources. Inferred
resources are too speculative geologically to have the economic
considerations applied to them that would enable them to be
categorized as mineral reserves and to be used in an economic
analysis except as allowed for in PEA studies. There is no
guarantee that Inferred resources can be converted to Indicated or
Measured resources, and as such, there is no guarantee the Project
economics described herein will be achieved.2) Readers are
cautioned that the PEA is an economic analysis of mineral
resources. Mineral resources are not mineral reserves and do not
have demonstrated economic viability.3) White Pine North NPV
includes revenue related to 88% of the unexercised Osisko Gold
Royalties Ltd (“Osisko”) silver option. Osisko has
the right to pay an additional $23 million in order to secure the
rights to the balance 88% of the silver stream. If this option was
exercised, the adjusted NPV8% of White Pine North would be $634
million.4) Included within mineralized material within the
conceptual mine plan area are approximately 7 million tonnes of
mineralized material on lands that White Pine Copper LLC’s mineral
title has not been confirmed.
Key Joint Venture Agreement
Highlights
The joint operating agreement among Kinterra
Copper USA LLC and, Highland’s wholly owned subsidiary Upper
Peninsula Copper Holdings Inc. (“UPCH”) provides financial capacity
to proactively advance both key Michigan projects. The following
are the key terms of the investment by Kinterra and the joint
operating agreement:
-
Initial Investment of $30 million for 66% of White Pine
North Project: The initial investment reflects Kinterra’s
endorsement of the underlying asset value of White Pine North. The
cash is unrestricted and can be used at Highland’s discretion.
Highland intends on assigning a portion of the proceeds to
advancing the fully-permitted Copperwood project to a construction
decision in 2024. The purchase and sale of the interest in White
Pine Copper LLC has been completed and is fully funded.
-
Budget of Additional $30 million to Advance White Pine
North: In addition to its $30 million initial investment,
Kinterra has agreed to fund, subject to certain conditions, a
further $30 million in expenditures to advance the White Pine North
project. The commitment will consist of $20 million representing
Kinterra’s 66% pro rata expenditure, as well as a $10 million
unsecured loan to fund Highland’s pro rata expenditure. This loan
will be available to Highland to satisfy cash calls. The investment
will allow the joint venture project to progress quickly into
permitting, infill drilling and a feasibility study.
-
Unsecured $10 million Loan from Kinterra: The $10
million unsecured loan to cover cash calls will be available to
Highland Copper at coupon of 10% and will mature in July 2026. A
second unsecured loan (on the same terms) will become available to
Highland after this $30 million has been spent on White Pine North,
assuming any initial loan has been repaid. The second loan will
have a maturity of July 2028.
The joint operating agreement contemplates that
White Pine LLC will be governed by a management committee, which
will consist of three representatives appointed by Kinterra, and
two by Highland. Highland expects to continue to be involved in the
development of the White Pine North project. The management
committee will propose programs and budgets for future
expenditures. Highland will have the option to elect to participate
in future work programs.
In a challenging capital markets environment,
Highland is pleased to have secured funding, without issuing any
shares, to support our strategic goals at both Copperwood and White
Pine North.
“The structure of the funding package, in
addition to the strength of Kinterra’s balance sheet, provides
critical financial flexibility to advance Highland’s projects. The
initial investment allows Highland to progress to early site works
at Copperwood and move towards construction in 2024. The additional
capital of $30 million at White Pine North ensures no contributions
will be required by Highland in the near-term expenditure period.
Looking forward, the White Pine North project will benefit from
Kinterra’s financial strength, particularly through funding 66% of
the initial capital, should we jointly elect to construct White
Pine North in the future,” said Barry O’Shea, CFO of Highland
Copper.
Highland Copper Strategic Next
Steps
Highland will continue towards its goal of
becoming a US domestic copper producer in the near-term with the
development of the Copperwood project. Highland will then look to
production and cash flow growth from White Pine North through its
joint venture partnership with Kinterra.
-
Advance Copperwood towards Construction in 2024:
Key steps as the Highland progresses to development include:
-
Early works at site: With the available liquidity,
Highland will initiate early works at Copperwood for required site
impacts and environmental mitigations. The majority of the early
works are considered in the initial capital as outlined in the
recently published Copperwood Feasibility Study. Importantly, this
expenditure will net against initial capital.
-
Feasibility Study Optimizations: Through the
period leading up to a construction decision, Highland will
consider additional value creation opportunities relative to the
Copperwood Feasibility Study, particularly infill drilling and
potential life of mine extensions. A significant opportunity exists
to convert inferred resources into measured and indicated
resources.
-
Advance White Pine North to Permitting and Feasibility
Study: With the committed additional investment from
Kinterra, the joint venture partnership will proactively work
toward permitting and Feasibility Study, also advancing the White
Pine North project toward development. Highland’s 34% stake in the
White Pine North project remains highly significant to Highland’s
overall asset value:
-
After-tax NPV8% of $279 million1
for Highland’s 34% interest in the project, ensuring it remains a
valuable component of Highland’s asset value under the joint
venture partnership.
-
Copper resource of 1.2 billion pounds indicated and 0.7
billion pounds inferred for Highland’s 34% interest
(indicated 51.2 million tonnes at 1.05% Cu) (inferred 32.8 million
tonnes at 1.03% Cu)
-
Continue to Develop Relationship with Key Stakeholder in
State of Michigan: Highland looks forward to being a key
contributor to the economy of the State of Michigan. This requires
us to work collaboratively with all key community, government,
corporate and other stakeholders. Highland understands a mutually
beneficial relationship with all stakeholders is critical to
success.
We look forward to updating the market as we
advance towards our key strategic goals and surface the
considerable underlying asset value of Copperwood and White Pine
North.
1) NPV excludes the potential impact of Osisko
exercising its silver option.
Advisors
With respect to the Kinterra joint venture
transaction, the Company’s financial advisor is BMO Capital Markets
and the Company’s legal counsel is McMillan LLP.
Kinterra’s legal counsel with respect to the
joint venture transaction is Bennett Jones LLP.
Preliminary Economic Assessment
Detail
All amounts in this news release are in US
dollars, unless otherwise indicated. Due to rounding, numbers
presented throughout this release may not add up precisely to the
totals provided. Readers are cautioned that the PEA is an economic
analysis of mineral resources. Mineral resources are not mineral
reserves and do not have demonstrated economic viability.
The PEA and mineral resource estimate have been
prepared by G Mining Services Inc. (“GMSI”).
White Pine North Project
Geology
The White Pine deposit is located in the
Ontonagon County, Michigan State. The base of the Nonesuch
Formation hosts the bulk of the copper mineralization at White
Pine, which consists of cupriferous siltstone, black shale and
fine-grained sandstone beds, and low-grade siltstone, sandstone and
red shale beds.
The copper mineralization in the area of the
former White Pine mine occurs in the bottom 6 m (20 ft) of the
Nonesuch Formation at the contact with the Copper Harbor
conglomerate. Beds within the lower 21 m (70 ft) of the Nonesuch
Formation are laterally persistent and can be correlated across the
mine. The shale and siltstone in the lower part of the Nonesuch
Formation are divided into two sedimentary sequences, the lower
“Parting Shale” and the upper “Upper Shale”, separated by the Upper
Sandstone.
Copper mineralization at the White Pine deposit
occurs as two distinct styles -- very fine-grained sulfide
(chalcocite) and as native copper. Sulfide mineralization is
estimated to account for 85-90% of the copper in the deposit, but
both modes of copper are intimately associated throughout the
deposit.
Mineral Resources
GMSI prepared a Mineral Resource estimate for
the White Pine Project based on data provided up to and including
September 28, 2022. The resource estimate was prepared in
accordance with CIM Standards on Mineral Resources and Reserves
(adopted May 10, 2014) and is reported in accordance with
National Instrument 43-101 (“NI 43-101”)
Standards of Disclosure for Mineral Projects. Classification, or
assigning a level of confidence to Mineral Resources, has been
undertaken with strict adherence to CIM Standards on Mineral
Resources and Reserves. In the opinion of GMSI, the resource
evaluation reported herein is a reasonable representation of the
global Mineral Resources found at the White Pine Project at the
current level and spacing of sampling.
The mineral estimate was prepared under the
supervision of Réjean Sirois, P. Eng. consultant for GMSI, and
Christian Beaulieu, P. Geo. consultant for GMSI, both independent
“qualified persons” as defined in NI 43-101. Geovia GEMS™ and
Leapfrog Geo™ software were used to facilitate the resource
estimation process.
The modelling of the copper mineralization
horizons was based on the footwall and hanging wall of the three
selected “columns” (sedimentary sequences), namely the Parting
Shale, and the Full Column. The Parting Shale was modelled with a
minimum thickness of 2 m and the Full Column with a minimum
thickness of 3 m. In instances where the Parting Shale column
was less than 2 m, dilution was applied in the footwall to
ensure that the 2 m thickness was honored. The Mineral
Resources are reported within the Full Column or the Parting Shale,
based on mine engineering considerations.
Copper and silver assays were composited to the
full thickness of the column. Grade distributions were reviewed and
assay capping was not deemed necessary. Grade estimation was
undertaken using Ordinary Kriging (OK) for copper grades and
Inverse Distance Squared (ID2) for silver grades into a percentage
block model based on the wireframes of the two columns. A
three-pass estimation approach was adopted, with increasing search
ellipses and relaxed estimation parameters. A 300 m buffer
zone around existing workings was excised from the Mineral
Resources.
The block model was validated both visually and
statistically and was found to be a good representation of the
composites. Mineral Resource classification was based primarily on
estimation passes, and other considerations such as drill spacing,
quality of historical data and confidence in grade continuity.
The White Pine North deposit’s total Indicated
Mineral Resources are reported at 150.7 Mt grading an average
1.05% Cu and 13.5 g/t Ag containing 3.50 Blbs Cu and
65.5 Moz Ag using a lower cut-off grade of 0.90% Cu for the
Parting Shale and Full Column combined. Inferred Mineral Resources
are reported at 96.4 Mt grading an average 1.03% Cu and
9.0 g/t Ag containing 2.18 Blbs Cu and 27.8 Moz Ag using
a lower cut-off grade of 0.90% Cu (Parting Shale only).
Mineral Resource Estimate - White Pine
Project - 0.9% Cu cut-off Grade – June 12, 2023
Ore Column |
ResourceCategory |
Tonnage(Mt) |
CopperGrade(%) |
SilverGrade(g/t) |
CopperContained(M
lbs) |
SilverContained(M
oz) |
Full Column (3 m) |
Indicated |
37.8 |
1.03 |
10.1 |
857 |
12.3 |
Inferred |
0 |
- |
- |
0 |
0 |
Parting Shale (2 m) |
Indicated |
112.8 |
1.06 |
14.6 |
2,640 |
53.1 |
Inferred |
96.4 |
1.03 |
9.0 |
2,183 |
27.8 |
White Pine North (Total) |
Indicated |
150.7 |
1.05 |
13.5 |
3,497 |
65.5 |
Inferred |
96.4 |
1.03 |
9.0 |
2,183 |
27.8 |
Notes on Mineral Resources:
1) Mineral Resources
are reported using a copper price of US$4.00/lb and a silver price
of US$25/oz.2) A payable rate of 96.5% for copper and 90% for
silver was assumed.3) Metallurgical recoveries of 88% for copper
and 73.4% for silver were assumed.4) A cut-off grade of 0.90%
copper was used, based on an underground “room and pillar” mining
scenario.5) Mineral Resources are reported within the most probable
extraction scenario of Full Column or Parting Shale based on mine
engineering.6) Operating costs are based on a processing plant
located at the White Pine site.7) A flat NSR royalty rate of
$0.10/lb Cu payable was applied, which incorporates three royalties
on the project (Osisko Silver royalties, Osisko Copper royalties,
and Longyear Royalty).8) Minimum mining thicknesses of 2 m and
3 m were applied to the Parting Shale and the Full Column
respectively.9) No mining dilution and mining loss were considered
for the Mineral Resources.10) Mineralized rock bulk densities is
assumed at 2.74 g/cc.11) Classification of Mineral Resources
conforms to CIM definitions.12) The qualified persons for the
estimate are Mr. Réjean Sirois, P.Eng., consultant for GMSI and Mr.
Christian Beaulieu, P.Geo., consultant for GMSI. The estimate has
an effective date of June 12, 2023.13) Mineral Resources that are
not mineral reserves do not have demonstrated economic viability.
The estimate of Mineral Resources may be materially affected by
environmental, permitting, legal, title, taxation, sociopolitical,
marketing, or other relevant issues.14) Parting Shale: interval
defined from the base of the Lower Transition unit to the top of
the Tiger unit.15) Full Column: interval defined from the base of
the Lower Transition unit to the top of the Thinly unit.16) The
quantity and grade of reported Inferred Resources in this
estimation are uncertain in nature and there has been insufficient
exploration to define these Inferred Resources as Indicated or
Measured Mineral Resources.
Mining Plan
The PEA envisions that the deposit will be mined
with a mix of conventional highly mechanized, drill and blast and
continuous mining room-and-pillar mining method. The method
consists of the extraction of a series of entries and cross-cuts in
the mineralization, leaving pillars in place to support the back.
The entries, cross cuts and pillars have been sized using
geotechnical analysis and experience from historical mining at
White Pine.
The mine will comprise three sectors; the
Eastern, Center and Western parts. The mine will be accessed
via a new covered box-cut to establish a portal at the mine
entrance from the surface, located at the western side of the
deposit. The pre-production period requires 18,193 m of development
to establish the main entry panel requiring four to six drifts
according to the ventilation requirements. Ground conditions are
expected to be good to excellent, similar to the historical White
Pine mine. The ground support consists a 1.8 m rebar bolts on a 1.2
m by 1.2 m pattern. At room intersection rebar bolt length is
increased to 2.4 m.
The production schedule is based on mining a
fixed target of 5.475 M tonnes/year. To achieve this annual
production, seven to fourteen production panels must be in
production simultaneously. The number of required panels depends on
the tonnage from the development as well as the height of the rooms
of each panel. The mining of the room will be done using a
single-pass approach. In the first pass, larger pillars are left in
place. The mining recovery is approximately 57%.
Life-of-Mine (LOM) Metal
Production
The LOM production for the White Pine Project is
shown below. Payable copper production is estimated at 922,803
tonnes (2,034 million pounds) with an annual average of 42,428
tonnes (93.5 million pounds) over the 23.4-year mine life which
includes a 21-month commissioning and ramp-up period. The average
copper payable rate is 96.5%. Payable silver production over the
LOM is 26.2 million ounces with an annual average of 1,203 thousand
ounces of silver.
Production Physicals |
Pre-production |
Production |
Total |
Concentrate (k of dmt) |
102.8 |
3,129 |
3,232 |
Cu con. Grade (% Cu) |
30.5% |
30.5% |
30.5% |
Cu metal production (M lbs) |
69.3 |
2,108 |
2,177 |
Ag metal production (k oz) |
965.9 |
2,9323 |
30,290 |
Cu payable metal (M lbs) |
66.8 |
2,034 |
2,101 |
Ag payable metal (k oz) |
865.5 |
26,165 |
27,031 |
Processing and Metallurgy
The PEA envisions a process plant design for the
Project that is based on the historical metallurgical flowsheet to
produce copper concentrate with a nominal throughput of 15,000 tpd
and a planned availability of 92%. The flowsheet consists of a
standard grinding circuit with SAG and Ball Mill in closed circuit
with cyclone targeting a primary grind of 105 microns. The cyclone
overflow feeds the primary flotation cells following by a desliming
cyclone and secondary flotations cells. The concentrate from the
primary and secondary flotation cells will be sent to a regrind
mill in close circuit with cyclone targeting a grind of 20 microns.
The regrind cyclone overflow feeds two stages of concentrate
cleaning cells before thickening, filtration concentrate and
tailings disposal.
The copper recovery is estimated at 88% with a
concentrate grade of 30.5% Cu. Silver recovery is estimated at
73.4%.
Power and Surface
Infrastructure
The Company envisions using the available power
from the grid in conjunction with a natural gas fired power
generation plant to be built on site. The combined power capacity
is estimated at 38 MW. The existing tailings disposal facility will
be utilized to deposit tailings from the White Pine North project,
which will require dam raises over the life-of-mine. Water supply
is available from an existing Lake Superior pump station.
Capital and Operating Costs
The initial capital costs, including all direct
and indirect costs, are estimated at $880.4 million, including
a contingency of $140.4 million. It is anticipated that
pre-production revenue of $265.2 million will reduce the
capital expenditures to $615.2 million.
Initial Capital Expenditure
Summary
Initial CAPEX1 |
($M) |
General |
0.6 |
Infrastructure |
44.4 |
Power & Electrical |
76.1 |
Water & TDF Mgmt. |
97.3 |
Mobile Equipment |
93.2 |
Mine Infrastructure |
93.1 |
Process Plant |
148.9 |
Construction Indirects |
71.5 |
General Services & Owner's Costs |
42.7 |
Pre-Production, Commissioning |
72.3 |
Sub-Total Before Contingency |
740.0 |
Contingency (18.8%) |
140.4 |
Total Incl. Contingency |
880.4 |
Less: Pre-Production Revenue |
(265.3) |
Total Incl. Contingency & Pre-Prod.
Revenue |
615.2 |
Sustaining Capital Expenditure
Summary
The total LOM sustaining capital is estimated at
$657.8 million. The sustaining capital includes the extension
of the conveyor system for extracting ore to surface and
replacement of equipment which typically has a useful life of
50,000 hours.
Sustaining Capital |
LOM |
($M) |
Tailings disposal facility expansion |
88.0 |
Water treatment plant |
15.0 |
Mine equipment purchases |
319.3 |
Mine development expenditures |
99.0 |
Mine Infrastructure expenditures |
136.6 |
Total Sustaining Capital |
657.8 |
Operating Costs Summary
Operating costs include mining, processing,
G&A services, concentrate transportation and concentrate
treatment and refining charges. The concentrate transportation,
treatment charges and refining are deducted from gross revenues to
calculate the net smelter return (“NSR”). The NSR for the Project
during operations is estimated at $8.1 billion, excluding
$265 million of NSR generated during pre-production and
presented as a reduction of initial capital expenditures. The
average NSR over the LOM is $3.97 per pound of payable copper. The
average operating cost over the LOM is $29.90 per tonne of ore or
$1.64 per pound of payable copper with mining representing 58% of
the total operating costs, or $17.39 per tonne of ore.
Operating Cash Flow2 |
LOM |
$/t ore |
$/lb Cu Payable |
($M) |
Cu Revenue |
8,138 |
72.76 |
4.00 |
Ag Credits |
654 |
5.85 |
0.32 |
Revenue |
8,792 |
78.60 |
4.32 |
Concentrate Transportation Costs |
375 |
3.35 |
0.18 |
Treatment & Refining Charges |
349 |
3.12 |
0.17 |
Net Smelter Return |
8,068 |
72.14 |
3.97 |
Royalties |
205 |
1.83 |
0.10 |
Mining Costs |
1,945 |
17.39 |
0.96 |
Processing Costs |
711 |
6.36 |
0.35 |
G&A Costs |
483 |
4.31 |
0.24 |
Working capital adj in OPEX |
-33 |
-0.30 |
-0.02 |
Total OPEX (incl. royalties) |
3,311 |
29.6 |
1.63 |
Operating Cash Flow |
4,758 |
42.54 |
2.34 |
2) Excluding commissioning period.
Sensitivity Analysis
Variance |
After-Tax Results |
NPV0% (M$) |
NPV8% (M$) |
IRR (%) |
Payback (yrs) |
Copper Price Sensitivities |
3.50 $lb |
1,822 |
457 |
15.8% |
4.7 |
3.75 $lb |
2,273 |
639 |
18.4% |
4.0 |
4.00 $lb |
2,723 |
821 |
20.8% |
3.5 |
4.25$lb |
3,174 |
1,003 |
23.1% |
3.1 |
4.5 $lb |
3,624 |
1,184 |
25.4% |
2.7 |
Initial Capital Cost Sensitivities |
-20% |
2,881 |
971 |
26.5% |
2.5 |
-10% |
2,802 |
896 |
23.4% |
3.0 |
0% |
2,723 |
821 |
20.8% |
3.5 |
10% |
2,645 |
746 |
18.7% |
3.9 |
20% |
2,566 |
671 |
16.9% |
4.4 |
Operating Cost Sensitivities |
-20% |
3,287 |
1,034 |
23.2% |
3.1 |
-10% |
3,005 |
928 |
22.1% |
3.3 |
0% |
2,723 |
821 |
20.8% |
3.5 |
10% |
2,442 |
714 |
19.5% |
3.7 |
20% |
2,159 |
607 |
18.2% |
4.0 |
Estimated Timeline
The estimated timeline for the White Pine North
Project is shown below. Upon receipt of required permits and
necessary approvals a 39-month mine development, construction,
commissioning, and pre-production ramp-up period is foreseen
followed by 21.75 years of commercial production.
Project Timeline |
Total |
Construction and Mine development (months) |
18 |
Commissioning and pre-production (months) |
21 |
Commercial production (yrs) |
21.75 |
Closure (months) |
36 |
PEA Assumptions
Feasibility Study Assumptions |
Total |
Avg. Copper Price ($/lb) |
4.00 |
Avg. Silver Price ($/oz) |
25.00 |
Treatment Charge ($/t) |
65 |
Refining Charge (¢/lb) |
6.5 |
Avg. Copper Payable Rate (%) |
96.5% |
Avg. Silver Payable Rate (%) |
90% |
Summary Economics for White Pine
Project
Summary Economics for White Pine Project |
|
Pre‐tax NPV @8% ($M) |
1,023.6 |
Pre-tax IRR @8% |
23.1% |
After‐tax NPV@ 8% ($M) |
821 |
After-tax IRR @8% |
20.8% |
Undiscounted After‐Tax Cashflow (LOM) ($M) |
2,723.5 |
Payback Period from start of processing‐years |
3.5 |
Initial Capital expenditures ($M) |
615.2 |
LOM Sustaining Capital Expenditures ($M) |
657.8 |
LOM C‐1 Cash Costs $/lb (net of bi‐product) |
1.58 |
Nominal Process capacity mt/d |
15,000 |
Mine Life‐years |
21.75 |
|
|
Annual Payable Metal Production |
|
Copper (M lb) |
93.5 |
Silver (k oz) |
1,203 |
LOM Average Process Recovery |
|
Copper % |
88.0 |
Silver % |
73.4 |
All-in Cash Cost
LOM Costs |
($M) |
($/tonne milled) |
($/payable lb) |
Mining |
1,945 |
17.39 |
0.96 |
Processing |
711 |
6.36 |
0.35 |
G&A |
483 |
4.31 |
0.24 |
Offsite costs (transport, TC/RCs) |
723 |
6.47 |
0.36 |
By-product credits |
(654) |
(5.85) |
(0.32) |
C1 Cost |
3,208 |
28.69 |
1.58 |
Capex and closure cost |
1,477 |
13.20 |
0.73 |
Royalty costs |
205 |
1.83 |
0.10 |
Interest Cost (Equipment Financing) |
19 |
0.17 |
0.01 |
C3 Cost |
4,909 |
43.89 |
2.41 |
Environment and Permitting
The former White Pine mine has hosted mining
activities for over a century and most recent mining activities
spanned from the 1950’s to 1995. The site been the subject of an
extensive remediation program outlined in judicial Consent Decree
and Remedial Action Plan agreements between Copper Range Company,
Michigan’s Attorney General, and the Michigan Department of
Environment, Great Lakes, and Energy (EGLE). The entire surface
area overlying the underground mine along with the associated
surface component area and tailings impoundments are listed as a
“facility” under Part 201, Environmental Remediation, of Michigan’s
Public Act 451 of 1994 as Amended, the Natural Resource and
Environmental Protection Act (NREPA). With the completion of
the final closing of the acquisition of the mineral and surface
rights from CRC, the Company has assumed all environmental
liabilities related to the Consent Decree and on-going
environmental obligations, and has been indemnified by White Pine
LLC, the owner of the White Pine North project, for such
liabilities.
The Project considers additional ore extraction
and processing on site by modern methods and under current
regulations. No federal permits are applicable, however, state
(NREPA) permits will be needed, anticipated to include:
- Part 632 Mining Permit,
- Part 31 National Pollutant Discharge
Elimination System (NPDES)
- Part 55 Permit to Install (air
permit)
- Part 301/303 Wetlands and Streams
- Part 315 Dam Safety Permit
The Company had begun baseline environmental
surveys with intent to assemble baseline data suitable for
obtaining permits. Historical data exists on surface water, ground
water and near-surface soils. Updated baseline data collection is
underway or being planned, including groundwater, surface water,
biological and wetland surveys, archaeological surveys, and other
data that support the developing mine plan. The Company anticipates
this work will continue under the joint venture.
Qualified Persons
Carl Michaud, P. Eng., of GMSI, an independent
qualified person, as defined under NI 43-101, has read and approved
the technical portions of this news release. The following
qualified persons will be responsible for the preparation of their
relevant portions of the technical report to be prepared in
accordance with NI 43-101 and they have reviewed and approved this
news release.
Qualified Persons |
Company |
Area of expertise |
Carl Michaud, P.Eng. |
G Mining Services Inc. |
Operating cost estimation, economic analysis and mine
engineering |
Réjean Sirois, P.Eng. |
Consultant for G Mining Services Inc. |
Geology and mineral resource estimation |
Christian Beaulieu, P.Geo. |
Consultant for G Mining Services Inc. |
Geology and mineral resource estimation |
Luc Binette, P.Eng. |
G Mining Services Inc. |
Infrastructure and capital cost estimation |
Martin Houde, P.Eng. |
G Mining Services Inc. |
Mineral processing and recovery methods |
Andrea K. Martin, P.E. |
Foth Infrastructure & Environment LLC |
Environment and Permitting |
Technical Report
The Company is planning to file a technical
report in accordance with NI 43-101 on SEDAR, within 45 days from
the date of this news release. Readers are cautioned that the
conclusions, projections and estimates set out in this news release
are subject to important qualifications, assumptions and
exclusions, all of which are detailed in the technical report. To
fully understand the summary information set out in this news
release, the technical report that will be filed on SEDAR should be
read in its entirety.
About The White Pine North
Project
The White Pine North Copper Project is located
in the historical copper range district of the Upper Peninsula of
Michigan, approximately 7.5 km south of Lake Superior in Ontonagon
County. The Project covers approximately 4,500 hectares (11,000
acres) of surface rights and approximately 11,990 hectares (29,615
acres) of mineral rights. The former White Pine mine was in
production from 1953 through 1995. By the time it closed, over 4.5
billion pounds of copper had been produced from the mine. In July
2021, Highland Copper completed the acquisition of the White Pine
north project from Copper Range Company.
About Highland Copper
Company
Highland Copper Company Inc. is a Canadian
company focused on exploring and developing copper projects in the
Upper Peninsula of Michigan, U.S.A. The Company owns the Copperwood
deposit through long-term mineral leases and 34% of the White Pine
North project. The Company also owns surface rights securing access
to the deposit and providing space for infrastructure as required.
The Company has 736,363,619 common shares issued and outstanding.
Its common shares are listed on the TSX Venture Exchange under the
symbol "HI" and trade on the OTCQB Venture Market under symbol
"HDRSF".
More information about the Company is available
on the Company’s website at www.highlandcopper.com and on SEDAR at
www.sedar.com.
About Kinterra
Kinterra Capital is a private equity
firm investing in the people, ideas, critical minerals, and
strategic infrastructure necessary to accelerate the energy
transition. Kinterra leverages significant domain specific
technical and transactional expertise to source and manage
investments that create value for key stakeholders, all while
enhancing the communities within which we operate through
meaningful partnerships. At Kinterra, the focus is on innovative
ideation, rigorous analysis and executing with excellence to make
investments that will create a more sustainable future. For more
information about Kinterra Capital, visit
www.kinterracapital.com.Cautionary Note
REGARDING FORWARD-LOOKING INFORMATION
This press release contains certain
“forward-looking information within the meaning of applicable
Canadian securities legislation. These forward-looking statements
are made as of the date of this news release and Highland Copper
Company Inc. does not intend, and does not assume any obligation,
to update these forward-looking information, except as required
under applicable securities legislation. Forward-looking
information relate to future events or future performance and
reflect Company management’s expectations or beliefs regarding
future events and include, but are not limited to, information with
respect to the estimation of mineral resources, the conversion of
mineral resources to mineral reserves, the expected timing for
completion of additional studies and exploration and development
work through to the commencement of construction of the White Pine
mine, Highland’s ability to raise the necessary debt and equity
contribution to the project, the realization of mineral resource
estimates, the timing and amount of estimated future production,
costs of production, capital expenditures, success of mining
operations, life of mine, environmental risks, the timing of the
receipt of permits, the timing and terms of a power purchase
agreement, unanticipated reclamation expenses, title disputes or
claims and limitations on insurance coverage, including
expectations with respect to Kinterra, the new majority owner of
the White Pine LLC, to advance the project as provided herein. In
certain cases, forward-looking information can be identified by the
use of words such as “plans”, “expects” or “does not expect”, “is
expected”, “outlook”, “budget”, “scheduled”, “estimates”,
“forecasts”, “intends”, “anticipates” or “does not anticipate”, or
“believes”, or variations of such words and phrases or information
that certain actions, events or results “may”, “could”, “would”,
“might” or “will be taken”, “occur” or “be achieved” or the
negative of these terms or comparable terminology. In this document
certain forward-looking information are identified by words
including “scheduled”, “plan”, “planned”, “estimated”,
“projections”, “projected” and “expected”. Forward-looking
information are based on a number of assumptions which may prove
incorrect, including, but not limited to, the include the specific
assumptions set out in this press release and in the Report, that
future capital and operating costs will be in line with Highland’s
assumptions, that mineral resource estimates prove accurate,
permits required to commence production will be obtained on a
timely basis, mineral and metals prices will remain consistent with
Highlands expectations, that there are no changes in the
development plans for White Pine as new information is received,
that Highland will be able to access financing, equipment to meet
its contribution obligations, and that sufficient qualified labor
to carry out the development plans. By their very nature
forward-looking information involves known and unknown risks,
uncertainties and other factors which may cause the actual results,
performance or achievements of the Company to be materially
different from any future results, performance or achievements
expressed or implied by the forward-looking information. Such
factors include, among others, changes in project parameters as
plans continue to be refined; fluctuations in the currency markets;
fluctuations in the spot and forward price of minerals; volatility
in the price of fuel and electricity; changes in national and local
government legislation, taxation, controls, regulations and
political or economic developments in Canada and the USA; operating
or technical difficulties in connection with mining or development
activities; employee relations; litigation; the speculative nature
of underground mine exploration and development, including the
risks of obtaining necessary licenses and permits; contests over
title to properties, particularly title to undeveloped properties;
failure of processing and mining equipment to perform as expected;
labor disputes; supply problems; uncertainty of production and cost
estimates; the interpretation of drill results; the assumptions
upon which the estimation of mineral resources prove inaccurate,
which could lead to a restatement of resources;; changes in project
parameters as plans continue to be refined; possible variations in
mineral resources, grade of mineralization or recovery rates may
differ from what is indicated and the difference may be material;
legal and regulatory proceedings and community actions; accidents,
title matters; regulatory restrictions; permitting and licensing;
volatility of the market price of Common Shares; insurance;
competition; and hedging activities. In addition, there are risks
and hazards associated with the business of exploration,
development and mining, including environmental hazards, industrial
accidents, unusual or unexpected formations, pressures, cave - ins,
flooding and the risk of inadequate insurance, or inability to
obtain insurance, to cover these risks.
Cautionary Note to United States
Investors
Highland advises U.S. investors that this press
release contains the terms "inferred", "indicated" and "measured"
resources. All resource estimates have been prepared in accordance
with NI 43-101. NI 43-101 is a rule developed by the Canadian
Securities Administrators which establishes standards for all
public disclosure an issuer makes of scientific and technical
information concerning mineral projects. Canadian standards differ
significantly from the requirements of the United States Securities
and Exchange Commission ("SEC"), and resource information contained
therein may not be comparable to similar information disclosed by
U.S. companies. In particular, and without limiting the generality
of the foregoing, the term "resource" does not equate to the term
"reserves". "Inferred resources" have a great amount of
uncertainty as to their existence, and great uncertainty as to
their economic and legal feasibility. It cannot be assumed that all
or any part of an "inferred resource" will ever be upgraded to a
higher category. U.S. investors are cautioned not to assume that
all or part of an inferred resource exists, or is economically or
legally mineable. U.S. Investors are also cautioned not to assume
that all or any part of mineral deposits in the "measured" or
"indicated" resource categories will ever be converted into
reserves.
Neither the TSX Venture Exchange nor its
Regulation Services Provider (as that term is defined in the
policies of the TSX Venture Exchange) accepts responsibility for
the adequacy or accuracy of this release.
For further information, please contact:
Denis Miville-Deschênes, President & CEO
Email: info@highlandcopper.com
Website: www.highlandcopper.com
Highland Copper (TSXV:HI)
Gráfico Histórico do Ativo
De Nov 2024 até Dez 2024
Highland Copper (TSXV:HI)
Gráfico Histórico do Ativo
De Dez 2023 até Dez 2024