Lithium Americas Corp. (TSX: LAC) (NYSE: LAC)
(“
Lithium Americas” or the
“
Company”) has reported financial and operating
results for the quarter ended June 30, 2023 (“
Q2
2023”).
HIGHLIGHTS
Argentina
Caucharí-Olaroz
- In June 2023,
Caucharí-Olaroz achieved first lithium production as the project
advances commissioning and ramp up to Stage 1 capacity of 40,000
tonnes per annum (“tpa”) of battery-quality
lithium carbonate
(”Li2CO3”),
which is scheduled to be completed in mid-2024.
- Since startup,
production quality has exceeded expectations with critical
equipment required to achieve battery-quality lithium carbonate in
the process of testing and commissioning.
- Caucharí-Olaroz
is expected to produce approximately 5,000 tonnes of lithium
carbonate in 2023.
- First lithium
product from Caucharí-Olaroz has left the site and is being
prepared for shipment at the port.
- As of June 30,
2023, $895 million of the $979 million total expected capex has
been spent (on a 100% basis). As of June 30, 2023, the Company
expects its remaining funding requirement to be less than $25
million for capital costs, value added taxes and working capital to
reach positive cash flow.
- Preparation for
Caucharí-Olaroz Stage 2 expansion targeting additional production
capacity of at least 20,000 tpa is underway.
Pastos Grandes
Basin
- On June 26,
2023, the Company announced the SEDAR filing of a National
Instrument 43-101 (“NI 43-101”) Technical Report
and resource update for the Pastos Grandes Project titled, “NI
43-101 Technical Report, Lithium Resources Update, Pastos Grandes
Project, Salta Province, Argentina,” with an effective date of
April 30, 2023.
- The Company
continues to advance Pastos Grandes’ $30 million development plan,
including engineering and evaluation work, which is expected to be
completed by the end of the year. Simultaneously, the Company is
working to complete a project review and an updated feasibility
study.
- A geophysics
program to map the basin and brine geological units has been
completed and drilling has commenced. This will allow the Company
to deepen its understanding of the brine reserves and provide key
inputs to design the brine production system.
- On April 20, 2023, the Company
completed its acquisition of Arena Minerals and its 65% ownership
interest in the Sal de la Puna project, adjacent to the Pastos
Grandes project in Salta, Argentina.
United
States
Thacker
Pass
- In mid-June
2023, major earthworks construction commenced at Thacker Pass to
support the target of initial production in the second half of
2026.
- Deposits on
long-lead items are expected to start in Q3 2023 and will continue
through Q4 2024.
- The Company
continues to work closely with the U.S. Department of Energy
(“DOE”) Loans Program Office to advance
confirmatory due diligence and term sheet negotiations for the
Advanced Technology Vehicles Manufacturing Loan Program
(“ATVM Loan Program”), following the receipt of a
Letter of Substantial Completion on February 22, 2023.
- The Company
expects the DOE ATVM Loan Program conditional approval process to
be completed in 2023 and if approved, to fund up to 75% of capital
costs for construction of Phase 1. Development costs incurred by
the project may qualify as eligible costs under the ATVM Loan
Program as of January 31, 2023.
- The Company has
approved a 2023 construction budget of $125 million with $48
million cash spent in Q2 2023 for construction of water pipelines
and ponds, infrastructure improvements and the start of major
earthworks.
- On February 6, 2023, the US
District Court, District of Nevada ruled favorably for the Company
in the appeal filed against the Bureau of Land Management by
declining to vacate the Record of Decision. The U.S. Court of
Appeals for the Ninth Circuit affirmed the District Court’s
decision on July 17, 2023.
Corporate
- As at June 30,
2023, the Company had $502.0 million in cash and cash equivalents
and short-term bank deposits, with an additional $75 million in
available credit.
- On July 31,
2023, at the annual, general and special meeting of Lithium
Americas shareholders, 98.85% of the votes cast by shareholders
present in person or by proxy at the meeting voted in favor of the
separation of the Company into Lithium Americas (Argentina) Corp.
(“Lithium Argentina”) and a new Lithium Americas
Corp. (“Lithium Americas (NewCo)”), pursuant to a
statutory plan of arrangement (the “Separation”).
The Separation is targeted to become effective in early October
2023.
- Additionally, in
connection with the second tranche of the previously announced $650
million investment by General Motors Holdings LLC
(“GM”), the Company’s shareholders passed two
resolutions approving: (a) the ownership by GM and its affiliates
of more than 20% of the issued and outstanding shares of the
Company (or following the Separation, Lithium Americas (NewCo));
and (b) $27.74 per share (as adjusted for the Separation) as the
maximum subscription price at which Tranche 2 of GM’s investment
would be made.
- On August 4,
2023, the Company obtained a final order from the Supreme Court of
British Columbia approving the plan of arrangement to effect the
Separation.
TECHNICAL
INFORMATION
The Technical
Information in this news release has been reviewed and approved by
Rene LeBlanc, PhD, SME, Chief Technical Officer of Lithium
Americas, and a Qualified Person as defined by National Instrument
43-101.
FINANCIAL
RESULTS
Selected consolidated
financial information is presented as follows:
(in US$ million except per share information) |
Quarters ended June 30, |
|
2023 |
|
|
2022 |
|
|
|
$ |
|
|
|
$ |
|
Expenses |
|
(17.1 |
) |
|
|
(90.3 |
) |
Net income/(loss) |
|
25.8 |
|
|
|
(16.6 |
) |
Income/(loss) per share – basic |
|
0.16 |
|
|
|
(0.12 |
) |
Income/(loss) per share – diluted |
|
0.16 |
|
|
|
(0.12 |
) |
(in US$ million) |
As at June 30, 2023 |
|
|
As at December 31, 2022 |
|
|
|
$ |
|
|
|
$ |
|
Cash, cash equivalents and
short-term bank deposits |
|
502.0 |
|
|
|
352.1 |
|
Total assets |
|
1,501.9 |
|
|
|
1,016.5 |
|
Total
long-term liabilities |
|
(203.5 |
) |
|
|
(212.9 |
) |
Net income in Q2 2023
versus loss in Q2 2022 is primarily due to lower share of loss of
Caucharí-Olaroz project partially offset by lower gain on change in
fair value of the GM agreements derivative liability and
convertible note derivative liability.
In H1 2023, total
assets increased primarily due to acquisition of Arena Minerals and
cash proceeds from the first tranche investment by GM of $320
million.
This news release
should be read in conjunction with Lithium Americas’ condensed
consolidated interim financial statements and management's
discussion and analysis for the quarter ended June 30, 2023, which
are available on SEDAR. All amounts are in U.S. dollars unless
otherwise indicated.
ABOUT LITHIUM
AMERICAS
Lithium Americas is advancing a separation of
its U.S. and Argentine business units into two public independent
companies. Lithium Argentina will retain Caucharí-Olaroz
(44.8%-interest), focused on advancing toward full production
capacity, and regional growth opportunities in the Pastos Grandes
basin with Pastos Grandes and Sal de la Puna projects (100%-owned
and 65%-interest, respectively). Lithium Americas (NewCo) will
retain the 100%-owned Thacker Pass, focused on advancing
construction with the target to commence production in the second
half of 2026. The Company currently trades on the TSX and on the
NYSE, under the ticker symbol “LAC.”
For further information contact:Investor
RelationsTelephone: 778-656-5820Email:
ir@lithiumamericas.comWebsite: www.lithiumamericas.com
FORWARD-LOOKING INFORMATION
This news release
contains “forward-looking information” within the meaning of
applicable Canadian securities legislation and “forward-looking
statements” within the meaning of the United States Private
Securities Litigation Reform Act of 1995 (collectively referred to
herein as “forward-looking information”). These statements relate
to future events or the Company’s future performance. All
statements, other than statements of historical fact, may be
forward-looking information. Information concerning Mineral
Resource and Mineral Reserve estimates also may be deemed to be
forward-looking information in that it reflects a prediction of
mineralization that would be encountered if a mineral deposit were
developed and mined. Forward-looking information generally can be
identified by the use of words such as “seek,” “anticipate,”
“plan,” “continue,” “estimate,” “expect,” “may,” “will,” “project,”
“predict,” “propose,” “potential,” “targeting,” “intend,” “could,”
“might,” “should,” “believe” and similar expressions. These
statements involve known and unknown risks, uncertainties and other
factors that may cause actual results or events to differ
materially from those anticipated in such forward-looking
information.
In particular, this
news release contains forward-looking information, including,
without limitation, with respect to the following matters or the
Company’s expectations relating to such matters: goals of the
Company; development of the Caucharí-Olaroz project and the Thacker
Pass project, including timing, progress, approach, continuity or
change in plans, construction, commissioning, milestones,
anticipated production and results thereof and expansion plans;
plans at the Caucharí-Olaroz project to prioritize commissioning;
expected remaining funding commitments at the Caucharí-Olaroz
project; expected timing of full capacity production at the
Caucharí-Olaroz project and plans for additional production
capacity; expectations regarding accessing funding from the ATVM
Loan Program, including the expected amount, timing and outcome of
the loan application; expectation that ATVM Loan Program, if
approved, will fund 75% of capital costs for construction of Phase
1 at the Thacker Pass project; that development costs at the
Thacker Pass project may qualify as eligible costs under the ATVM
Loan Program; anticipated timing to resolve, and the expected
outcome of, any complaints or claims made or that could be made
concerning the environmental permitting process in the United
States for the Thacker Pass project, including current lawsuits
involving the Record of Decision for the project; capital
expenditures and programs; the Company’s ability to raise capital
and the sufficiency of currently available funding; expected
expenditures to be made by the Company on its properties;
successful operation of the Caucharí-Olaroz project under its
co-ownership structure; ability to produce battery grade lithium
products; timing of deposits on long-lead items at the Thacker Pass
project; capital costs, operating costs, sustaining capital
requirements, after tax net present value and internal rate of
return, payback period, sensitivity analyses, and net cash flows of
the Caucharí-Olaroz project and the Thacker Pass project; expecting
timing to complete project review, feasibility studies, development
planning, evaluating opportunities for synergy, and reach a
construction decision for the Pastos Grandes and Sal de la Puna
projects; the ability of the Company to complete Tranche 2 of GM’s
investment on the terms and timeline anticipated, or at all; the
receipt of required stock exchange and regulatory approvals,
authorizations and court rulings; the expected timetable for
completing the Separation; the ability of the Company to complete
the Separation on the terms and timeline anticipated, or at all;
the receipt of required third party, stock exchange and regulatory
approvals required for the Separation; the expected holdings and
assets of the entities resulting from the Separation; the expected
benefits of the Separation for each business and to the Company’s
shareholders and other stakeholders; the strategic advantages,
future opportunities and focus of each business resulting from the
Separation; and the successful integration and expected benefits of
the acquisition of Arena Minerals, including opportunities for
regional growth and development of the Pastos Grandes basin
expected from the acquisition.
Forward-looking
information does not take into account the effect of transactions
or other items announced or occurring after the statements are
made. Forward-looking information is based upon a number of
expectations and assumptions and is subject to a number of risks
and uncertainties, many of which are beyond the Company’s control,
that could cause actual results to differ materially from those
that are disclosed in or implied by such forward-looking
information. With respect to forward-looking information listed
above, the Company has made assumptions regarding, among other
things: current technological trends; a cordial business
relationship between the Company and third party strategic and
contractual partners, including the co-owners of the
Caucharí-Olaroz project; ability of the Company to fund, advance
and develop the Caucharí-Olaroz project and the Thacker Pass
project, and the respective impacts of the projects when production
commences; ability of the Company to advance and develop the Pastos
Grandes and Sal de la Puna projects; the Company’s ability to
operate in a safe and effective manner; uncertainties relating to
receiving and maintaining mining, exploration, environmental and
other permits or approvals in Nevada and Argentina; demand for
lithium, including that such demand is supported by growth in the
electric vehicle market; the impact of increasing competition in
the lithium business, and the Company’s competitive position in the
industry; general economic conditions; the stable and supportive
legislative, regulatory and community environment in the
jurisdictions where the Company operates; stability and inflation
of the Argentine peso, including any foreign exchange or capital
controls which may be enacted in respect thereof, and the effect of
current or any additional regulations on the Company’s operations;
the impact of unknown financial contingencies, including litigation
costs, on the Company’s operations; gains or losses, in each case,
if any, from short-term investments in Argentine bonds and
equities; estimates of and unpredictable changes to the market
prices for lithium products; development and construction costs for
the Caucharí-Olaroz project and the Thacker Pass project, and costs
for any additional exploration work at the projects; estimates of
Mineral Resources and Mineral Reserves, including whether Mineral
Resources not included in Mineral Reserves will be further
developed into Mineral Reserves; reliability of technical data;
anticipated timing and results of exploration, development and
construction activities, including the impact of COVID-19 on such
timing; timely responses from governmental agencies responsible for
reviewing and considering the Company’s permitting activities at
the Thacker Pass project; the Company’s ability to obtain
additional financing on satisfactory terms or at all; the ability
to develop and achieve production at any of the Company’s mineral
exploration and development properties; the impact of inflationary
and other conditions flowing from COVID-19, or otherwise, on the
Company’s business and global mark; and accuracy of development
budget and construction estimates.
Although the Company
believes that the assumptions and expectations reflected in such
forward-looking information are reasonable, the Company can give no
assurance that these assumptions and expectations will prove to be
correct. Since forward-looking information inherently involves
risks and uncertainties, undue reliance should not be placed on
such information. The Company’s actual results could differ
materially from those anticipated in any forward-looking
information as a result of the risk factors set out herein and in
the Company’s latest annual information form
(“AIF”) available on SEDAR.
All forward-looking
information contained in this news release is expressly qualified
by the risk factors set out in the Company’s latest AIF, management
information circular and management discussion & analysis. Such
risk factors are not exhaustive. The Company does not undertake any
obligation to update or revise any forward-looking information,
whether as a result of new information, future events or otherwise,
except as required by law. All forward-looking information
contained in this news release is expressly qualified in its
entirety by this cautionary statement. Additional information about
the above-noted assumptions, risks and uncertainties is contained
in the Company’s filings with securities regulators, including our
latest AIF and management information circular, which are available
on SEDAR at www.sedar.com.
Lithium Americas (TSX:LAC)
Gráfico Histórico do Ativo
De Nov 2024 até Dez 2024
Lithium Americas (TSX:LAC)
Gráfico Histórico do Ativo
De Dez 2023 até Dez 2024