Burnstone Gold Project: Number 1 Vertical Shaft Enters Phase 2 of Development - Financial Forecast Update
10 Fevereiro 2009 - 11:30AM
PR Newswire (US)
VANCOUVER, Feb. 10 /PRNewswire-FirstCall/ -- Great Basin Gold Ltd,
("Great Basin" or the "Company"), (TSX: GBG; NYSE Alternext: GBG;
JSE: GBG) announces the successful erection of the permanent
headgear at the Number 1 Vertical Shaft of its Burnstone Project in
the Mpumalanga Province, 80 kilometers from Johannesburg, South
Africa. The Company's plan for the Burnstone Project is to access
the gold-bearing Kimberley Reef primarily by means of a decline
while extraction of ore and waste will occur via a shallow vertical
shaft. Great Basin has undertaken the decline shaft using employees
instead of contractors. The design, sinking, equipping and
commissioning of the Vertical Shaft was contracted to Grinaker -
LTA Mining, a business unit of Aveng (Africa) Ltd. Site preparation
for the vertical shaft started in January 2008, and sinking
commenced in April 2008. The 7.5-meter diameter Vertical Shaft is
planned to be sunk to a final depth of 501 meters, and is designed
to allow for the extraction of 125,000 tonnes of ore and 55,000
tonnes of waste per month. It will also be equipped for the
transportation of personnel and material. Under the mine plan, an
additional 50,000 tons of ore per month will be mined later via a
second decline accessing Area 2. The initial, pre-sink phase was
completed by the end of 2008, having reached a depth of 164 meters
below surface. Preparations for the next main sink phase, which is
to take place at a faster rate of excavation, are now underway and
nearing completion. As part of these preparations, the permanent
headgear was erected, allowing for three temporary sinking winders
to be installed. The winder installations have been completed and
two of the three winders were licensed to operate as of January 7,
2009. The third Kibble winder will be licensed by end of February
2009. These winders will be replaced by a permanent winder
arrangement near to the time of the completion of the project.
Erecting the 45-meter high pre-assembled headgear was a complex
process, requiring detailed planning and precision in execution.
The erection process commenced on Saturday, January 17 and was
completed on Monday, January 19, 2009 when the raker legs were
installed. Good progress has been made underground with drifts to
access mining blocks B and C, which are currently under
development. The decline shaft has also progressed to within 35
meters of intersection with the Kimberley Reef. Mining from the
decline and Block B is planned to commence in the March 2009
quarter and access to Block C is scheduled in the June 2009
quarter. The Metallurgical Plant design is in its final stages and
will be completed by end February 2009. Some used equipment has
been purchased for the Burnstone facility. The mills have been
subjected to non-destructive testing to determine the level of
refurbishment required. The Metallurgical Plant commissioning is on
track for completion by mid 2010. The 2007 Optimised Feasibility
Study (see Great Basin News Release dated July 5, 2007) has been
updated by Great Basin's in-house engineering and financial team
("2009 Update") based on mineral resources announced in 2008 (see
Great Basin News Release dated February 19, 2008) and mine planning
by Turgis Engineering. A number of the project plans remain as in
the 2007 Optimised Feasibility, with other key parameters described
below. A technical report currently being finalized is expected to
be filed on http://www.sedar.com/ during February 2009. The
continued exploration has resulted in a 15% increase in proven and
probable mineral reserves to 30 million tonnes grading 4.2 g/t at a
4 g/t gold cut-off(1), and increasing the planned number of ounces
to be mined from 3.5 million to 4.1 million ounces over a mine life
of 15 years. Capital expenditure estimates have been updated to
reflect the change in mine plan. During 2008, the Company spent
US$37 million (ZAR337 million) to develop the mine and related
infrastructure, bringing the total expenditure on the Burnstone
Project to US$54 million (ZAR490 million). The remaining required
capital necessary to bring the mine into commercial production is
estimated at US$124 million (ZAR1.1 billion). Cash costs for mining
and processing are estimated at US$303 per ounce (ZAR88,000 p/Kg).
At a long term gold price of US$750/oz, the Project has an Internal
Rate of Return (IRR) of 33% and an after-tax Net Present Value
(NPV) of US$612 million using a 5% discount rate. Using the current
gold price of US$900/oz and R9.00 to the US Dollar, the analysis
indicates an IRR of 43% and an after-tax NPV of US$879 million. The
Company is in the process of negotiating a project funding facility
with a syndicate of South African Banks and is optimistic that the
negotiations will be successfully concluded this month, subject to
execution of final documentation. Ferdi Dippenaar, President and
CEO, commented: "Erecting the permanent headgear and installing the
associated infrastructure are important and significant milestones
as we will be able to continue with the fast sink, lining and
equipping of this shallow 501-meter vertical shaft. Despite
intersecting water on 164 Level as well as in the barrel during the
pre-sinking, the team managed to gain approximately 4 weeks on the
scheduled sinking program. Good progress is also being made with
underground infrastructure development with multiple access points
to the deposit, which should see Burnstone producing approximately
40,000 oz over the next year." Johan Oelofse, PrEng, FSAIMM, Chief
Operating Officer for Great Basin is a qualified person. He
supervised the 2009 Update and has reviewed this news release.
Ferdi Dippenaar President and CEO (1) The mineral reserves are
comprised of 27.6 million tonnes grading 4.27 g/t of proven
reserves and 2.4 million tonnes grading 4.01 g/t of probable
reserves. No regulatory authority has approved or disapproved the
information contained in this news release. Cautionary and Forward
Looking Statement Information This release includes certain
statements that may be deemed "forward-looking statements". All
statements in this release, other than statements of historical
facts, that address possible future commercial production, bank
loan arrangements, reserve potential, exploration drilling results,
development, feasibility or exploitation activities and events or
developments that Great Basin Gold expects to occur are
forward-looking statements. Although the Company believes the
expectations expressed in such forward-looking statements are based
on reasonable assumptions, such statements are not guarantees of
future performance and actual results or developments may differ
materially from those in the forward-looking statements. Factors
that could cause actual results to differ materially from those in
forward-looking statements include market prices for precious
metals, credit availability, development and exploration successes,
continuity of mineralization, uncertainties related to the ability
to obtain necessary permits, licenses and title and delays due to
third party opposition, geopolitical uncertainty, changes in
government policies regarding mining and natural resource
exploration and exploitation, and continued availability of capital
and financing, and general economic, market or business conditions.
Investors are cautioned that any such statements are not guarantees
of future performance and those actual results or developments may
differ materially from those projected in the forward-looking
statements. For more information on the Company, Investors should
review the Company's annual Form 40-F filing with the United States
Securities and Exchange Commission and its Canadian jurisdiction
filings that are available at http://www.sedar.com/. All
information relating to the contents of the 2009 Update and to the
2007 Optimised Feasibility Study, including but not limited to
statements of the Burnstone project's potential and information
such as capital and operating costs, production summary, and
financial analysis are forward looking statements. The 2009 Update
was prepared to quantify the Burnstone project's capital and
operating cost parameters and to determine the project's likelihood
of feasibility and optimal production rate. The capital and
operating cost estimates which were used have been developed based
on detailed capital cost to production level relationships. The
following are the principal risk factors and uncertainties which,
in management's opinion, are likely to most directly affect the
ultimate feasibility of the Burnstone project. The mineralized
material at the Burnstone project is currently classified as a
measured and indicated resource, and a portion of it qualifies
under Canadian mining disclosure standards as a proven and probable
reserve, but readers are cautioned that no part of the Burnstone
project's mineralization is not yet considered to be a reserve
under US mining standards as all necessary mining permits and
project financing would be required in order to classify the
project's mineralized material as an economically exploitable
reserve. Although work has been done to confirm the mine design,
mining methods and processing methods assumed in the 2009 Update,
construction and operation of the mine and processing facilities
depend on securing environmental and other permits on a timely
basis. Authorization has been received for mining. Additional
permits, when required, have yet to be applied for and there can be
no assurance that required permits can be secured or secured on a
timely basis. Although costs, including design, procurement,
construction and on-going operating costs and metal recoveries have
been established at a level of detail required for a feasibility
study, these could be materially different from those contained in
the 2009 Update. There can be no assurance that these
infrastructure facilities can be developed on a timely and
cost-effective basis. Energy risks include the potential for
significant increases in the cost of fuel and electricity. The 2009
Update assumes specified, long-term prices levels for gold. The
price of this metal is historically volatile, and the Company has
no control of or influence on its price which is determined in
international markets. There can be no assurance that the price of
gold will continue at current levels or that it will not decline
below the prices assumed in the 2009 Update. Prices for gold have
been below the price ranges assumed in 2009 Update at times during
the past ten years, and for extended periods of time. The project
will require additional financing. Although interest rates are at
historically low levels, there can be no assurance that debt and/or
equity financing will be available on acceptable terms. Other
general risks include those ordinary to very large construction
projects, including the general uncertainties inherent in
engineering and construction cost, the need to comply with
generally increasing environmental obligations, and accommodation
of local and community concerns. South African mining tenure laws
require that significant economic ownership in Burnstone be held by
historically disadvantaged South Africans (HDSAs) and for which
ownership rights the Company may not be significantly compensated.
The Company has an agreement with Tranter Gold (Pty) Ltd which
represents the required interest by HDSA. The economics of the
Burnstone Project are sensitive to the US Dollar and South African
Rand exchange rate and this rate has been subject to large
fluctuations in the last several years. DATASOURCE: Great Basin
Gold Ltd. CONTACT: For additional details on Great Basin Gold Ltd.
and its gold properties, please visit the Company's website at
http://www.grtbasin.com/ or contact Investor Services: Tsholo
Serunye in South Africa, +27 (0)11 301 1800; Michael Curlook in
North America, (888) 633-9332; Barbara Cano at Breakstone Group in
the USA, (646) 452-2334
Copyright