Great Basin Reports Progress in Quarter Ended June 30, 2009
12 Agosto 2009 - 9:30AM
PR Newswire (US)
VANCOUVER, Aug. 12 /PRNewswire-FirstCall/ -- Great Basin Gold Ltd,
("Great Basin" or the "Company"), (TSX: GBG; NYSE Amex: GBG; JSE:
GBG) announces results for the quarter ended June 30, 2009. Two of
the highlights were the good progress made with the discovery of
two new veins at the Hollister Property in Nevada, USA and
commencing the development of multiple reef drives at the Burnstone
Property in South Africa. The Company incurred a loss of CDN 4 cent
per share, which is similar to the loss incurred for the March 2009
quarter. Gross revenue of CDN$28.2 million, before toll milling
charges of CDN$6.3 million, was realized from the sale of 26,517
gold equivalent ("Au eqv") ounces (Mar '09 - 18,189 Au eqv ounces)
from trial mining at Hollister during the quarter. Cash costs,
excluding milling costs, were CDN$439 (US$375) per ounce (Mar '09 -
CDN$397 or US$320 per ounce). Quarter on quarter cash costs per ton
decreased by 15% to CDN$434 (US$371). A total of 18,442 tons of ore
(at a grade of 0.99 Au eqv ounces1 per ton or 34.1 g/t), containing
18,219 Au eqv ounces, was extracted during the quarter. The year to
date production costs of CDN$402 (US$344) per ounce and CDN$472
(US$403) per ton remain ahead of budgeted costs of CDN$426 (US$364)
per ounce and CDN$540 (US$462) per ton. Pre-development expenses
for the Hollister property increased from CDN$5.2 million to
CDN$8.5 million, quarter on quarter. To date, an amount of CDN$70
million has been expensed through the income statement for our
Hollister operations. At Hollister, underground waste development
continued with 2,307 ft (700 m) being completed, totaling 26,652 ft
(8,076 m) to date. Ore development feet were higher at 1,104 ft
(335 m) compared to 645 ft (195 m) planned. The focus in the past
quarter has been on development to establish the 5050 Level, where
a total of 434 ft (132 m) of access excavations were completed.
This is a high grade stope with a current length of approximately
700 ft (213 m) and where trial mining is planned to commence in the
third quarter. Underground evaluation and exploration drilling for
other mineralized structures totalled 19,590 ft (5,936 m).
Exploration expenses for the quarter increased to CDN$4.4 million
(March '09 - CDN$4 million), of which CDN$3.6 million was spent on
an underground exploration program at Hollister. Following the
discovery of two new veins in close proximity to the current
underground infrastructure, a follow-up drilling program has been
initiated to test the extent and depth of mineralization. The
refurbishment of the Esmeralda Mill was completed and commissioning
commenced in July 2009. A total of 3,000 tons have been shipped to
site and milling has commenced. It is planned to initially fill the
plant with low grade material until the delivery and installation
of the float and gravity section has been completed by October
2009. Permission by the Nevada Department of Environmental
Protection to construct a refinery on site can only be granted once
an analysis of the milled material from the operational plant has
been completed. The process typically takes 6 months to complete.
Until then Au concentrate will be shipped off-site for recovery.
For Burnstone, CDN$33 million (Mar '09 - CDN$7 million) was
capitalized in the quarter. In the six months ended June 30, 2009,
CDN$40 million was capitalized as activities related to the
construction of the mine infrastructure accelerated. Good progress
continues to be made with the development of surface and
underground infrastructure at the Burnstone Project. As at August
9, 2009, 7,709 ft (2,336 m) of decline development had been
completed. The access decline continued beyond the reef elevation,
with approximately 954 ft (289 m) remaining to vertical shaft
position. The cross-cut to Block B 3 has accessed the Kimberley
Reef and production stopes are being established. As at August 9,
2009, a total of 6,134 tons have been accumulated on the surface
ore stockpile. A total of 40 ft (12 m) remains to access Block C
before stope establishment for mining commences. Sinking of the
vertical shaft at Burnstone continued and at August 9, 2009, the
shaft had reached a depth of 1,188 ft (360 m) below surface with
436 ft (133 m) remaining to shaft bottom. At a depth of 1,181 ft
(358 m) the shaft also intersected the Kimberley reef at the
expected elevation, at which the cover diamond drill hole graded
7.54 g/t over 116 cm (for 874 cmg/t). Samples have been collected
for assaying. The final depth of the shaft is planned at 1,624 ft
(492 m). The refurbishment of the mills continues to be on schedule
and the civil excavations for the Metallurgical facility are
planned for completion by September 2009, after which the
Metallurgical Plant construction will commence. President and CEO
Ferdi Dippenaar commented: "The Company continues to make good
progress at both its development projects. With the commissioning
of the Esmeralda Mill, our Hollister Mine can look forward to
reporting more consistent results which will assist in the
understanding of its quarter on quarter performance. At our
Burnstone Mine, with the establishment of the first stopes
underway, the rate of mining should increase with more ore tons
reporting to the surface stockpile. Our target to have a fully
operational project at Burnstone by end June 2010 remains on track
with the construction of the metallurgical facility to commence
after the completion of the civil excavations, by the end of
September 2009." Johan Oelofse, Pr.Eng., FSAIMM, Chief Operating
Officer of Great Basin and a qualified person has reviewed this
release on behalf of the Company. No regulatory authority has
approved or disapproved the information contained in this news
release. Cautionary and Forward Looking Statement Information This
release includes certain statements that may be deemed
"forward-looking statements". All statements in this release, other
than statements of historical facts, that address possible future
commercial production, reserve potential, exploration drilling
results, development, feasibility or exploitation activities and
events or developments that Great Basin expects to occur are
forward-looking statements. Although the Company believes the
expectations expressed in such forward-looking statements are based
on reasonable assumptions, such statements are not guarantees of
future performance and actual results or developments may differ
materially from those in the forward-looking statements. Factors
that could cause actual results to differ materially from those in
forward-looking statements include market prices, exploitation and
exploration successes, and continued availability of capital and
financing, and general economic, market or business conditions.
Investors are cautioned that any such statements are not guarantees
of future performance and those actual results or developments may
differ materially from those projected in the forward-looking
statements. For more information on the Company, Investors should
review the Company's annual Form 40-F filing with the United States
Securities and Exchange Commission and its home jurisdiction
filings that are available at http://www.sedar.com/.
------------------------- (1) Gold equivalent was calculated using
a gold price of US$800 per ounce and a silver price of US$12 per
ounce. DATASOURCE: Great Basin Gold Ltd. CONTACT: on Great Basin
and its gold properties, please visit the Company's website at
http://www.grtbasin.com/ or contact Investor Services: Tsholo
Serunye in South Africa, 27 (0) 11 301 1800; Michael Curlook in
North America, 1-888-633-9332; Barbara Cano at Breakstone Group in
the USA, (646) 452-2334
Copyright