TIDMPAF 
 
Pan African Resources PLC                Pan African Resources Funding 
(Incorporated and registered in England  Company Limited 
and Wales under the Companies Act 1985   Incorporated in the Republic of 
with registered number 3937466 on 25     South Africa with limited liability 
February 2000)                           Registration number: 2012/021237/06 
Share code on AIM: PAF                   Alpha code: PARI 
Share code on JSE: PAN 
ISIN: GB0004300496 
ADR ticker code: PAFRY 
("Pan African" or the "Company" or the 
"Group") 
 
OPERATIONAL UPDATE FOR THE SIX MONTHSED 31 DECEMBER 2022 
 
Pan African is pleased to provide shareholders and noteholders with an 
operational update for the six months ended 31 December 2022 ("current 
reporting period"). 
 
Key features for the current reporting period 
 
Operational 
 
  * Gold production of 92,307oz (2021: 108,085oz), with operational results as 
    follows: 
      + Barberton Mines 32,022oz (2021: 39,991oz) 
      + BTRP 10,012oz (2021: 9,126oz) 
      + Elikhulu 25,830oz (2021: 25,900oz) 
      + Evander Mines 24,443oz (2021: 33,068oz) 
  * Proactive journey to 'zero harm' through a number of health and safety 
    initiatives to address regression in underground mining safety rates 
  * Agreements with representative unions to restructure Barberton Mines 
    underground operations as follows: 
      + Consort Mine loss-making operations are to be converted to a contractor 
        mining model, focussing on higher grade areas with reduced overheads, 
        whilst development and exploration will continue to increase future 
        mining flexibility and production; and 
      + Fairview Mine and Sheba Mines' operations are to be reconfigured to a 
        continuous operations (24 hour) shift cycle with productivity expected 
        to increase commensurately 
  * The Group maintains its full year production guidance of 195,000oz to 
    205,000oz, a level similar to that achieved in 2022 
 
Financial 
 
  * Issue of an inaugural sustainability-linked bond of US$47.3 million to 
    assist in the funding of Pan African's pipeline of growth projects, with 
    Mintails being the preeminent project for development 
  * Payment of a net dividend of US$20.0 million (2021: US$21.6 million) in 
    December 2022 
  * An increase in net senior debt by 108.8% to US$49.9 million (2021: US$23.9 
    million), primarily as a result of capital expenditure incurred on Pan 
    African's organic growth projects 
 
Environmental, Social and Governance 
 
  * Average monthly cost savings of US$145,000 achieved from Evander Mines' 
    10MW renewable energy solar photovoltaic (PV) plant 
  * Site clearance completed for Barberton Mines' 8MW solar PV plant, with 
    construction scheduled to commence by June 2023 
  * Scheduling of further large renewable energy initiatives underway 
 
Growth projects 
 
  * Mintails' project construction expected to commence by June 2023 
  * Royal Sheba's development plan to be finalised in the next months 
 
Pan African CEO Cobus Loots commented: 
 
"Reduced gold production over the past half year can primarily be attributed to 
the performance of the Barberton Mines underground operations. We believe that 
the concrete measures being implemented at this operation will result in a 
significant improvement during the second half of the financial year and in the 
years ahead. The balance of our portfolio delivered in line with expectations, 
despite disruptions to our electricity supply and inclement weather conditions 
impacting operations. At our Evander operation alone, electricity issues 
impacted production by approximately 5%, reinforcing our imperative to expand 
our renewable energy portfolio in the years ahead.  Given the improved 
production performance expected in the second half of the 2023 financial year, 
we are maintaining production guidance of 195,000oz to 205,000oz for the full 
year, subject to consistency in Eskom's electricity supply. 
 
Safety of our people and contractors remains our number one priority and we 
have implemented a number of programmes to address the regression in the safety 
performance at our underground operations. 
 
We are encouraged by the progress made with the Group's growth projects. The 
Mintails acquisition was concluded during October 2022 and the senior debt 
funding for the construction of the project is expected to be finalised in 
April 2023. This project's definitive feasibility study (DFS) demonstrated 
compelling economics at a much lower gold price than the prevailing spot price, 
and this asset is expected to significantly increase Group gold production in 
the years ahead. 
 
Pan African is committed in its resolve to continued value creation for its 
stakeholders by positioning the Group as a sustainable, safe, high-margin and 
long-life gold producer with an attractive pipeline of growth projects. We look 
forward to presenting our interim results on 15 February 2023, which will 
include further details on our operational and financial performance, progress 
with the Barberton restructuring initiatives and our growth projects." 
 
Safety 
 
The Group has regrettably seen a regression in the safety performance during 
the current reporting period at its underground operations, following an 
excellent record in the previous years. Pan African continues to focus on 
industry leading safety initiatives in its pursuit of a 'zero-harm' working 
environment. 
 
  * The Group's lost-time injury frequency rate ('LTIFR') regressed to 2.54 
    (2021: 0.98) per million man hours 
  * The Group's reportable injury frequency rate ('RIFR') regressed to 1.34 
    (2021: 0.28) per million man hours 
  * Barberton Mines achieved an LTIFR of 1.88 (2021:1.02) and RIFR of 0.63 
    (2021: 0.20) per million man hours 
  * Elikhulu achieved excellent results with an improvement in both the LTIFR 
    and RIFR to 1.28 (2021:1.50) and RIFR 0.00 (2021: 1.01) per million man 
    hours 
  * Evander Mines underground operations achieved an LTIFR of 4.72 (2021: 0.65) 
    and RIFR of 3.76 (2021: 0.00) per million man hours, with the majority of 
    safety incidents attributable to new short term contractors 
 
The Group is implementing the following initiatives to improve its safety 
performance in the second half of the 2023 financial year: 
 
  * Additional systems implemented to monitor contractor safety compliance 
  * Pre-emptive production stoppages, where safety protocols are re-enforced 
  * Strengthening of the on-site safety staff complement 
  * Third-party safety systems audit for both Barberton and Evander Mines in 
    order to identify further areas for improvement 
 
Group Production 
 
Group production for the current reporting period decreased by 14.6% to 
92,307oz (2021: 108,085oz), following the record gold production achieved in 
2021. The gold production split per operation is as follows: 
 
Operation          Six months ended Six months ended  Guidance for six 
                   31 December 2021 31 December 2022 months to June 2023 
 
Barberton Mines -       39,991           32,022        40,000 - 43,000 
Underground 
 
Barberton Tailings      9,126            10,012        10,000 - 12,000 
Retreatment Plant 
(BTRP) 
 
Elikhulu                25,900           25,830        26,000 - 28,000 
 
Evander Mines -         33,068          24 443*        27,000 - 29,000 
Underground and 
surface sources 
 
Total ounces           108,085           92,307       103,000 - 112,000 
produced 
 
* Includes gold equivalent PGM ounces produced by Evander Gold Mines' 
Osmiridium circuit 
 
Barberton Mines 
 
Barberton Mines has been in operation for over 130 years with a remaining life 
of mine in excess of 20 years, positioning this asset as a long-life operation 
within Pan African's portfolio. 
 
Over the last years Barberton Mines has made good progress in increasing mining 
flexibility, with key initiatives including the following: 
 
  * Increased development rates at Fairview Mine, with up to five high grade 
    mining platforms established on the MRC orebody and three platforms 
    available on the Rossiter orebody 
  * Increased exploration drilling targeting further down-dip extensions to 
    these platforms to improve reserve delineation 
  * Improving the production profile through decongesting existing 
    infrastructure, including plans for optimising hoisting from a sub-vertical 
    shaft, development and equipping the 4 Decline from 42 to 64 Level and 
    investment in refrigeration to allow mining at deeper levels 
  * Optimising the mining method at Sheba Mine from long-hole stoping to up-dip 
    mining for reduced dilution 
  * Focus on equipping the PC Shaft remnant blocks at Consort Mine to extract 
    the high-grade ore between 41 and 44 Levels 
 
Despite the improvements detailed above, the underground operations have 
experienced a number of headwinds in maintaining and increasing gold 
production, with challenges including the following: 
 
  * Above inflationary increases in labour and energy costs 
  * Increasing depth and underground travel times at Fairview Mine, reducing 
    available face-time 
  * Depletion of the high-grade 42 Level block at Consort Mine 
 
To mitigate these challenges, a detailed review of operations at Barberton was 
completed and following intensive engagement with stakeholders, including the 
representative employee unions, agreement has been reached to restructure the 
underground operations. Consort Mine is to be converted to a contractor mining 
operation, and both Fairview and Sheba Mines will implement a continuous 
operating cycle, whilst still allowing for ongoing maintenance and other 
support activities. 
 
This conversion of Consort Mine will result in a more optimal operating model 
with a focus on the mining of high-grade areas and reduced overheads. 
 
The shift cycle at Fairview and Sheba Mines will be changed to a continuous 
operations cycle during February 2023, with the following rationale: 
 
  * Work flow studies on the current shift cycle at Fairview Mine indicated 
    actual face time of less than 3 hours, affecting the completion of a full 
    mining cycle as a result of the extended travelling time to current 
    production platforms 
  * Excess staff from Consort will be transferred to Fairview and Sheba to 
    bolster the existing staff complement in order to meet the requirements of 
    the new shift cycle, resulting in no large staff retrenchments 
  * The new continuous shift cycle is expected to result in an increase of 
    approximately 20% in available face time, with a progressive commensurate 
    increase in productivity 
  * The amended shift cycle will reduce overtime requirements, which in turn is 
    expected to result in cost savings 
  * Increased development rates will improve mining flexibility in the future. 
 
Negotiations with the unions to enable the conversion to a continuous 
operations cycle were concluded on 27 January 2023. 
 
Future cost-saving and production improvement initiatives to be implemented in 
the near-term include: 
 
  * Commissioning of the 8MW solar PV renewable energy plant to reduce energy 
    costs 
  * Optimised infrastructure plans to decongest ore flow and increase hoisting 
    capacity to improve the production profile, including completion of Project 
    Dibanisa development that will connect the underground infrastructure of 
    Fairview and Sheba Mines 
  * Increase in exploration drilling to identify down-dip extensions to mining 
    platforms and prove-up new exploration targets. 
 
Processing of the 10,000t bulk sample from the Royal Sheba project at the Sheba 
and Consort metallurgical plants was completed. The bulk sample's actual grade 
was 1.22g/t relative to a planned grade of 0.5g/t, with recoveries of 84% 
relative to a planned recovery of 85%. A development plan for mining the Royal 
Sheba orebody will be provided together with the Group's interim results 
presentation on 15 February 2023. 
 
Elikhulu tailings retreatment plant (Elikhulu) 
 
Gold production from Elikhulu remained steady at 25,830oz (2021: 25,900oz) 
during the current reporting period, despite disruptions to electricity supply 
and inclement weather conditions during the November and December rainy season. 
 
 
Gold production from Elikhulu is expected to increase in the second half of the 
2023 financial year, as material from the Leslie/Bracken tailings facility is 
retreated, following the installation of the 6km pipeline and successful 
commissioning of the pump station in September 2022. 
 
Evander Mines' 8 Shaft Pillar project (8 Shaft Pillar) and surface sources 
 
Production from Evander Mines' decreased by 26.1% to 24,443oz (2021: 33,068oz). 
 
Underground production decreased by 29.8% to 19,173oz (2021: 27,312oz), despite 
an increase in processed tonnes of 6% to 73,946t (2021: 69,790t). The decrease 
in the 8 Shaft Pillar's production during the current reporting period was a 
result of: 
 
  * Normalisation of mining face grades to 8g/t (2021: 13g/t), in line with 
    planned grades of 7g/t 
  * Reduced mining rates and face availability, which impacted ore tonnes 
    delivered for processing, following depletion of the Mineral Reserves in 
    accordance with geotechnical parameters for the safe extraction of the 
    pillar. 
 
Expected production from surface sources in the second half of the 2023 
financial year is underpinned by the treatment of the Leslie TSF buttressing 
material, following the commencement of re-mining on the Leslie TSF facility. 
 
Group net senior debt 
 
The Group's net senior debt (comprising secured, interest-bearing debt, net of 
available cash) increased by 108.8% to US$49.9 million (2021: US$23.9 million). 
Relative to the 30 June 2022 financial year-end, Group net senior debt 
increased from US$9.3 million, primarily as a result of capital expenditure in 
the first half of the financial year, and the cash outflow of US$20.0 million 
(2021: US$21.6 million), associated with the net rand dividend paid to 
shareholders in December 2022. 
 
Mintails project progress 
 
Following the positive DFS results for the re-mining of Mogale Gold's TSFs, the 
Group is in the process of completing optimisation and value engineering 
activities in preparation for construction, which is expected to commence by 
June 2023, subject to finalisation of funding and permitting. Funding for the 
construction of the project is expected to be finalised in April 2023. Concept 
engineering works on the Soweto cluster is also underway. 
 
Further details on the Company's organic growth projects will be provided 
together with the Group's interim financial results for the current reporting 
period. 
 
Sudan Exploration Project 
 
The Group has successfully commissioned the first fire assay multi-element 
analytical laboratory within the Republic of Sudan. This laboratory will be 
used for the analyses of all of the Company's exploration samples being 
extracted from the Block 12 exploration concessions granted to Pan African by 
the Sudan Ministry of Mines. 
 
An exploration team is currently active within Block 12A South and Block 12A 
North, conducting soil geochemistry and hard rock chip sampling programmes to 
further define the identified exploration anomalies. Initial assaying received 
from the exploration targets identified in the south-eastern corner of Block 
12A South averaged 1.7g/t from 12 samples taken from quartz veins, rock debris 
and soil. However, some of the structures sampled indicated significantly 
higher gold mineralisation, with values ranging from 2.9g/t up to 9.4g/t Au. 
These structures will be further defined over the next 6 weeks as part of a 
confirmatory sampling programme. No Mineral Resources or Mineral Reserves are 
currently reported for any of the targets. 
 
Interim results for the six months ended 31 December 2022 
 
Pan African will announce its interim results on 15 February 2023. 
 
The information contained in this update is the responsibility of the Pan 
African board of directors and has not been reviewed or reported on by the 
Group's external auditors. 
 
Certain information communicated in this announcement was, prior to its 
publication, inside information for the purposes of Article 7 of Regulation 596 
/2014. 
 
Rosebank 
 
30 January 2023 
 
For further information on Pan African, please visit the Company's website at 
 
www.panafricanresources.com 
 
Corporate information 
 
Corporate Office                              Registered Office 
The Firs Office Building                      2nd floor 
2nd Floor, Office 204                         107 Cheapside 
Cnr. Cradock and Biermann Avenues             London 
Rosebank, Johannesburg                        EC2V 6DN 
South Africa                                  United Kingdom 
Office: + 27 (0)11 243 2900                   Office: + 44 (0)20 7796 8644 
info@paf.co.za                                info@paf.co.za 
 
Chief Executive Officer                       Financial Director 
Cobus Loots                                   Deon Louw 
Office: + 27 (0)11 243                        Office: + 27 (0)11 243 
2900                                          2900 
 
Head: Investor Relations                      Website: www.panafricanresources.com 
Hethen Hira 
Tel: + 27 (0)11 243 2900 
E-mail: hhira@paf.co.za 
 
Company Secretary                             Nominated Adviser and Joint Broker 
Jane Kirton                                   Ross Allister/David McKeown 
St James's Corporate Services Limited         Peel Hunt LLP 
Office: + 44 (0)20 7796 8644                  Office: +44 (0)20 7418 8900 
 
JSE Sponsor                                   Joint Broker 
Ciska Kloppers                                Thomas Rider/Nick Macann 
Questco Corporate Advisory Proprietary        BMO Capital Markets Limited 
Limited                                       Office: +44 (0)20 7236 1010 
Office: + 27 (0)11 011 9200 
 
                                              Joint Broker 
                                              Matthew Armitt/Jennifer Lee 
                                              Joh. Berenberg, Gossler & Co KG (Berenberg) 
                                              Office: +44 (0)20 3207 7800 
 
 
 
END 
 
 

(END) Dow Jones Newswires

January 30, 2023 02:06 ET (07:06 GMT)

Pan African Resources (AQSE:PAF.GB)
Gráfico Histórico do Ativo
De Abr 2024 até Mai 2024 Click aqui para mais gráficos Pan African Resources.
Pan African Resources (AQSE:PAF.GB)
Gráfico Histórico do Ativo
De Mai 2023 até Mai 2024 Click aqui para mais gráficos Pan African Resources.