Pan African Resources Plc Operational Update for the six months ended 31 Dec 2022
30 Janeiro 2023 - 4:06AM
UK Regulatory
TIDMPAF
Pan African Resources PLC Pan African Resources Funding
(Incorporated and registered in England Company Limited
and Wales under the Companies Act 1985 Incorporated in the Republic of
with registered number 3937466 on 25 South Africa with limited liability
February 2000) Registration number: 2012/021237/06
Share code on AIM: PAF Alpha code: PARI
Share code on JSE: PAN
ISIN: GB0004300496
ADR ticker code: PAFRY
("Pan African" or the "Company" or the
"Group")
OPERATIONAL UPDATE FOR THE SIX MONTHSED 31 DECEMBER 2022
Pan African is pleased to provide shareholders and noteholders with an
operational update for the six months ended 31 December 2022 ("current
reporting period").
Key features for the current reporting period
Operational
* Gold production of 92,307oz (2021: 108,085oz), with operational results as
follows:
+ Barberton Mines 32,022oz (2021: 39,991oz)
+ BTRP 10,012oz (2021: 9,126oz)
+ Elikhulu 25,830oz (2021: 25,900oz)
+ Evander Mines 24,443oz (2021: 33,068oz)
* Proactive journey to 'zero harm' through a number of health and safety
initiatives to address regression in underground mining safety rates
* Agreements with representative unions to restructure Barberton Mines
underground operations as follows:
+ Consort Mine loss-making operations are to be converted to a contractor
mining model, focussing on higher grade areas with reduced overheads,
whilst development and exploration will continue to increase future
mining flexibility and production; and
+ Fairview Mine and Sheba Mines' operations are to be reconfigured to a
continuous operations (24 hour) shift cycle with productivity expected
to increase commensurately
* The Group maintains its full year production guidance of 195,000oz to
205,000oz, a level similar to that achieved in 2022
Financial
* Issue of an inaugural sustainability-linked bond of US$47.3 million to
assist in the funding of Pan African's pipeline of growth projects, with
Mintails being the preeminent project for development
* Payment of a net dividend of US$20.0 million (2021: US$21.6 million) in
December 2022
* An increase in net senior debt by 108.8% to US$49.9 million (2021: US$23.9
million), primarily as a result of capital expenditure incurred on Pan
African's organic growth projects
Environmental, Social and Governance
* Average monthly cost savings of US$145,000 achieved from Evander Mines'
10MW renewable energy solar photovoltaic (PV) plant
* Site clearance completed for Barberton Mines' 8MW solar PV plant, with
construction scheduled to commence by June 2023
* Scheduling of further large renewable energy initiatives underway
Growth projects
* Mintails' project construction expected to commence by June 2023
* Royal Sheba's development plan to be finalised in the next months
Pan African CEO Cobus Loots commented:
"Reduced gold production over the past half year can primarily be attributed to
the performance of the Barberton Mines underground operations. We believe that
the concrete measures being implemented at this operation will result in a
significant improvement during the second half of the financial year and in the
years ahead. The balance of our portfolio delivered in line with expectations,
despite disruptions to our electricity supply and inclement weather conditions
impacting operations. At our Evander operation alone, electricity issues
impacted production by approximately 5%, reinforcing our imperative to expand
our renewable energy portfolio in the years ahead. Given the improved
production performance expected in the second half of the 2023 financial year,
we are maintaining production guidance of 195,000oz to 205,000oz for the full
year, subject to consistency in Eskom's electricity supply.
Safety of our people and contractors remains our number one priority and we
have implemented a number of programmes to address the regression in the safety
performance at our underground operations.
We are encouraged by the progress made with the Group's growth projects. The
Mintails acquisition was concluded during October 2022 and the senior debt
funding for the construction of the project is expected to be finalised in
April 2023. This project's definitive feasibility study (DFS) demonstrated
compelling economics at a much lower gold price than the prevailing spot price,
and this asset is expected to significantly increase Group gold production in
the years ahead.
Pan African is committed in its resolve to continued value creation for its
stakeholders by positioning the Group as a sustainable, safe, high-margin and
long-life gold producer with an attractive pipeline of growth projects. We look
forward to presenting our interim results on 15 February 2023, which will
include further details on our operational and financial performance, progress
with the Barberton restructuring initiatives and our growth projects."
Safety
The Group has regrettably seen a regression in the safety performance during
the current reporting period at its underground operations, following an
excellent record in the previous years. Pan African continues to focus on
industry leading safety initiatives in its pursuit of a 'zero-harm' working
environment.
* The Group's lost-time injury frequency rate ('LTIFR') regressed to 2.54
(2021: 0.98) per million man hours
* The Group's reportable injury frequency rate ('RIFR') regressed to 1.34
(2021: 0.28) per million man hours
* Barberton Mines achieved an LTIFR of 1.88 (2021:1.02) and RIFR of 0.63
(2021: 0.20) per million man hours
* Elikhulu achieved excellent results with an improvement in both the LTIFR
and RIFR to 1.28 (2021:1.50) and RIFR 0.00 (2021: 1.01) per million man
hours
* Evander Mines underground operations achieved an LTIFR of 4.72 (2021: 0.65)
and RIFR of 3.76 (2021: 0.00) per million man hours, with the majority of
safety incidents attributable to new short term contractors
The Group is implementing the following initiatives to improve its safety
performance in the second half of the 2023 financial year:
* Additional systems implemented to monitor contractor safety compliance
* Pre-emptive production stoppages, where safety protocols are re-enforced
* Strengthening of the on-site safety staff complement
* Third-party safety systems audit for both Barberton and Evander Mines in
order to identify further areas for improvement
Group Production
Group production for the current reporting period decreased by 14.6% to
92,307oz (2021: 108,085oz), following the record gold production achieved in
2021. The gold production split per operation is as follows:
Operation Six months ended Six months ended Guidance for six
31 December 2021 31 December 2022 months to June 2023
Barberton Mines - 39,991 32,022 40,000 - 43,000
Underground
Barberton Tailings 9,126 10,012 10,000 - 12,000
Retreatment Plant
(BTRP)
Elikhulu 25,900 25,830 26,000 - 28,000
Evander Mines - 33,068 24 443* 27,000 - 29,000
Underground and
surface sources
Total ounces 108,085 92,307 103,000 - 112,000
produced
* Includes gold equivalent PGM ounces produced by Evander Gold Mines'
Osmiridium circuit
Barberton Mines
Barberton Mines has been in operation for over 130 years with a remaining life
of mine in excess of 20 years, positioning this asset as a long-life operation
within Pan African's portfolio.
Over the last years Barberton Mines has made good progress in increasing mining
flexibility, with key initiatives including the following:
* Increased development rates at Fairview Mine, with up to five high grade
mining platforms established on the MRC orebody and three platforms
available on the Rossiter orebody
* Increased exploration drilling targeting further down-dip extensions to
these platforms to improve reserve delineation
* Improving the production profile through decongesting existing
infrastructure, including plans for optimising hoisting from a sub-vertical
shaft, development and equipping the 4 Decline from 42 to 64 Level and
investment in refrigeration to allow mining at deeper levels
* Optimising the mining method at Sheba Mine from long-hole stoping to up-dip
mining for reduced dilution
* Focus on equipping the PC Shaft remnant blocks at Consort Mine to extract
the high-grade ore between 41 and 44 Levels
Despite the improvements detailed above, the underground operations have
experienced a number of headwinds in maintaining and increasing gold
production, with challenges including the following:
* Above inflationary increases in labour and energy costs
* Increasing depth and underground travel times at Fairview Mine, reducing
available face-time
* Depletion of the high-grade 42 Level block at Consort Mine
To mitigate these challenges, a detailed review of operations at Barberton was
completed and following intensive engagement with stakeholders, including the
representative employee unions, agreement has been reached to restructure the
underground operations. Consort Mine is to be converted to a contractor mining
operation, and both Fairview and Sheba Mines will implement a continuous
operating cycle, whilst still allowing for ongoing maintenance and other
support activities.
This conversion of Consort Mine will result in a more optimal operating model
with a focus on the mining of high-grade areas and reduced overheads.
The shift cycle at Fairview and Sheba Mines will be changed to a continuous
operations cycle during February 2023, with the following rationale:
* Work flow studies on the current shift cycle at Fairview Mine indicated
actual face time of less than 3 hours, affecting the completion of a full
mining cycle as a result of the extended travelling time to current
production platforms
* Excess staff from Consort will be transferred to Fairview and Sheba to
bolster the existing staff complement in order to meet the requirements of
the new shift cycle, resulting in no large staff retrenchments
* The new continuous shift cycle is expected to result in an increase of
approximately 20% in available face time, with a progressive commensurate
increase in productivity
* The amended shift cycle will reduce overtime requirements, which in turn is
expected to result in cost savings
* Increased development rates will improve mining flexibility in the future.
Negotiations with the unions to enable the conversion to a continuous
operations cycle were concluded on 27 January 2023.
Future cost-saving and production improvement initiatives to be implemented in
the near-term include:
* Commissioning of the 8MW solar PV renewable energy plant to reduce energy
costs
* Optimised infrastructure plans to decongest ore flow and increase hoisting
capacity to improve the production profile, including completion of Project
Dibanisa development that will connect the underground infrastructure of
Fairview and Sheba Mines
* Increase in exploration drilling to identify down-dip extensions to mining
platforms and prove-up new exploration targets.
Processing of the 10,000t bulk sample from the Royal Sheba project at the Sheba
and Consort metallurgical plants was completed. The bulk sample's actual grade
was 1.22g/t relative to a planned grade of 0.5g/t, with recoveries of 84%
relative to a planned recovery of 85%. A development plan for mining the Royal
Sheba orebody will be provided together with the Group's interim results
presentation on 15 February 2023.
Elikhulu tailings retreatment plant (Elikhulu)
Gold production from Elikhulu remained steady at 25,830oz (2021: 25,900oz)
during the current reporting period, despite disruptions to electricity supply
and inclement weather conditions during the November and December rainy season.
Gold production from Elikhulu is expected to increase in the second half of the
2023 financial year, as material from the Leslie/Bracken tailings facility is
retreated, following the installation of the 6km pipeline and successful
commissioning of the pump station in September 2022.
Evander Mines' 8 Shaft Pillar project (8 Shaft Pillar) and surface sources
Production from Evander Mines' decreased by 26.1% to 24,443oz (2021: 33,068oz).
Underground production decreased by 29.8% to 19,173oz (2021: 27,312oz), despite
an increase in processed tonnes of 6% to 73,946t (2021: 69,790t). The decrease
in the 8 Shaft Pillar's production during the current reporting period was a
result of:
* Normalisation of mining face grades to 8g/t (2021: 13g/t), in line with
planned grades of 7g/t
* Reduced mining rates and face availability, which impacted ore tonnes
delivered for processing, following depletion of the Mineral Reserves in
accordance with geotechnical parameters for the safe extraction of the
pillar.
Expected production from surface sources in the second half of the 2023
financial year is underpinned by the treatment of the Leslie TSF buttressing
material, following the commencement of re-mining on the Leslie TSF facility.
Group net senior debt
The Group's net senior debt (comprising secured, interest-bearing debt, net of
available cash) increased by 108.8% to US$49.9 million (2021: US$23.9 million).
Relative to the 30 June 2022 financial year-end, Group net senior debt
increased from US$9.3 million, primarily as a result of capital expenditure in
the first half of the financial year, and the cash outflow of US$20.0 million
(2021: US$21.6 million), associated with the net rand dividend paid to
shareholders in December 2022.
Mintails project progress
Following the positive DFS results for the re-mining of Mogale Gold's TSFs, the
Group is in the process of completing optimisation and value engineering
activities in preparation for construction, which is expected to commence by
June 2023, subject to finalisation of funding and permitting. Funding for the
construction of the project is expected to be finalised in April 2023. Concept
engineering works on the Soweto cluster is also underway.
Further details on the Company's organic growth projects will be provided
together with the Group's interim financial results for the current reporting
period.
Sudan Exploration Project
The Group has successfully commissioned the first fire assay multi-element
analytical laboratory within the Republic of Sudan. This laboratory will be
used for the analyses of all of the Company's exploration samples being
extracted from the Block 12 exploration concessions granted to Pan African by
the Sudan Ministry of Mines.
An exploration team is currently active within Block 12A South and Block 12A
North, conducting soil geochemistry and hard rock chip sampling programmes to
further define the identified exploration anomalies. Initial assaying received
from the exploration targets identified in the south-eastern corner of Block
12A South averaged 1.7g/t from 12 samples taken from quartz veins, rock debris
and soil. However, some of the structures sampled indicated significantly
higher gold mineralisation, with values ranging from 2.9g/t up to 9.4g/t Au.
These structures will be further defined over the next 6 weeks as part of a
confirmatory sampling programme. No Mineral Resources or Mineral Reserves are
currently reported for any of the targets.
Interim results for the six months ended 31 December 2022
Pan African will announce its interim results on 15 February 2023.
The information contained in this update is the responsibility of the Pan
African board of directors and has not been reviewed or reported on by the
Group's external auditors.
Certain information communicated in this announcement was, prior to its
publication, inside information for the purposes of Article 7 of Regulation 596
/2014.
Rosebank
30 January 2023
For further information on Pan African, please visit the Company's website at
www.panafricanresources.com
Corporate information
Corporate Office Registered Office
The Firs Office Building 2nd floor
2nd Floor, Office 204 107 Cheapside
Cnr. Cradock and Biermann Avenues London
Rosebank, Johannesburg EC2V 6DN
South Africa United Kingdom
Office: + 27 (0)11 243 2900 Office: + 44 (0)20 7796 8644
info@paf.co.za info@paf.co.za
Chief Executive Officer Financial Director
Cobus Loots Deon Louw
Office: + 27 (0)11 243 Office: + 27 (0)11 243
2900 2900
Head: Investor Relations Website: www.panafricanresources.com
Hethen Hira
Tel: + 27 (0)11 243 2900
E-mail: hhira@paf.co.za
Company Secretary Nominated Adviser and Joint Broker
Jane Kirton Ross Allister/David McKeown
St James's Corporate Services Limited Peel Hunt LLP
Office: + 44 (0)20 7796 8644 Office: +44 (0)20 7418 8900
JSE Sponsor Joint Broker
Ciska Kloppers Thomas Rider/Nick Macann
Questco Corporate Advisory Proprietary BMO Capital Markets Limited
Limited Office: +44 (0)20 7236 1010
Office: + 27 (0)11 011 9200
Joint Broker
Matthew Armitt/Jennifer Lee
Joh. Berenberg, Gossler & Co KG (Berenberg)
Office: +44 (0)20 3207 7800
END
(END) Dow Jones Newswires
January 30, 2023 02:06 ET (07:06 GMT)
Pan African Resources (AQSE:PAF.GB)
Gráfico Histórico do Ativo
De Abr 2024 até Mai 2024
Pan African Resources (AQSE:PAF.GB)
Gráfico Histórico do Ativo
De Mai 2023 até Mai 2024