Mr. Renaud Hinse, President and C.E.O. of Abcourt Mines Inc. (TSX
VENTURE:ABI)(BERLIN:AML)(FRANKFURT:AML) (the "Company"), reports that the NI
43-101 preliminary economic assessment report (P.E.A.) on the Elder gold mine
project prepared by Roche Ltd., Consulting Group (Roche) and its independent
consultants, indicates a total cash flow of $138 M over a 10.4-year initial
period of mine life, a before-tax Net Present Value (NPV) of $81.8 M at a
discount rate of 8%, a before-tax Internal Rate of Return (IRR) of 140.5% and a
payback period of 1.1 years.


This study is based only on the 43-101 Elder resource calculations made by Mr.
Jean-Pierre Berube, Eng., previously reported (see Press Release dated April 25,
2012) and filed on SEDAR on May 9, 2012. It does not include any of the
indicated and inferred gold resources located on the adjacent Tagami property,
or any new resources that may be found by the proposed $3.5 M exploration budget
at the Elder mine.


The preliminary economic assessment includes inferred mineral resources that are
considered too speculative geologically to have the economic considerations
applied to them that would enable them to be categorized as mineral reserves,
and there is no certainty that the preliminary assessment will be realized.
Mineral resources that are not mineral reserves do not have demonstrated
economic viability.


The qualified persons responsible for this 43-101 report are Pierre Casgrain,
Eng., Garand Gagnon, Eng., Alain Dorval, Eng., and Martin Magnan, Eng., of Roche
Ltd., Consulting Group and Lise Chenard, Eng., Michel Bilodeau, Eng., and
Jean-Pierre Berube, Eng., independent consultants.


Here is the economic analysis extracted from the Roche report:

General 

A preliminary economic/financial analysis of the project has been carried out
using a cash flow model. The model is constructed using annual cash flows in
constant money terms (third quarter 2012). No provision is made for the effects
of inflation. As required in the financial assessment of investment projects,
the evaluation is carried out on a so-called "100% equity" basis, i.e., the debt
and equity sources of capital funds are ignored. 


Results are presented on a before-tax basis. The model reflects the base case
macro-economic and technical assumptions given in this report.


Macro-Economic Assumptions 

The main macro-economic assumptions used in the base case are given in Table 1
below. 


The gold price forecast is based on the average London Fix over the past
three-year period. The sensitivity analysis examines a range of gold prices 30%
above and below the base case price.


Table 1 - Macro-Economic Assumptions



                --------------------------------------------
                Item                            Unit   Value
                --------------------------------------------
                Gold Price                    $US/oz    1436
                --------------------------------------------
                Exchange Rate                CAD/USD    1.00
                --------------------------------------------
                Discount Rate             % per year       8
                --------------------------------------------
                Discount Rate Variants    % per year  6 & 10
                --------------------------------------------



Apart from the base case discount rate of 8 %, two variants of 6 and 10 % are
used to determine the net present value of the project. These discounts rates
represent possible weighted-average costs of capital to the investor.


Mineral Royalties 

The present financial analysis incorporates royalty agreements resulting in
three rates of payments that depend on the location of the resources extracted.
A 3 % NSR royalty applies to resources extracted from levels 1 to 9, a 2.5 % NSR
royalty applies to resources extracted from level 10, and a 2 % NSR royalty
applies to resources extracted from levels 11 to 15.


Technical Assumptions

The main technical assumptions used in the base case are given in Table 2 below.

Table 2 - Technical Assumptions



---------------------------------------------------------------------------
Item                                                          Unit    Value
---------------------------------------------------------------------------
Total Resources Mined                                     K tonnes   1488.9
---------------------------------------------------------------------------
Design Extraction Rate                        tonnes milled / year  150,000
---------------------------------------------------------------------------
Life of Mine                                                 Years     10.4
---------------------------------------------------------------------------
Average Mill Feed Grade                                     g/t Au  5.48(1)
---------------------------------------------------------------------------
Toll Mill Process Recovery                                       %       94
---------------------------------------------------------------------------
Total Gold Production                                     K ounces    246.5
---------------------------------------------------------------------------
Average Mining Operating Cost                  (CA$ / tonne mined)    66.41
---------------------------------------------------------------------------
Transport Cost to Toll Mill                   (CA$ / tonne milled)    12.50
---------------------------------------------------------------------------
Average Process Operating Cost (Toll mill)    (CA$ / tonne milled)    32.73
---------------------------------------------------------------------------
General & Administration Cost                 (CA$ / tonne milled)    15.34
---------------------------------------------------------------------------
Refining Cost                                        (CA$ / oz Au)     3.00
---------------------------------------------------------------------------
 (1) 5.48 g/t = 0.176 ounce of gold per tonne                               



A reduced production of 80,000 tonnes milled in the first year of production
provides for a ramp-up to the full capacity of 150,000 tonnes milled per year in
the following years.


Financial Model and Results 

A summary of the base case results is given in Table 3 below. 

The cash flow statement for the base case is reproduced in Table 4 of the report.  

In Table 3 and the cash flow statement, the following can be observed: 

A total at-mine revenue of $353.3 M is forecast. This amounts to an average of
$237.27 per tonne milled. 


The total pre-production capital expenditure is evaluated at $ 2.1 M, excluding
working capital, and the total sustaining capital requirement, excluding closure
costs, is evaluated at $2.2 M. An initial working capital, equivalent to 6
months of operating expenses in year 1, is provided at start-up, and is reduced
to an equivalent of 3 months thereafter. The Spare Parts and Capital Spares
entries listed under the indirect capital expenses are included in the initial
working capital requirement. The initial working capital outlay is $5.3 M.
Additional amounts are injected or withdrawn as total annual operating costs
increase or decrease over the life of mine. A total of $0.6 M is provided for
closure costs. 


The total operating costs are estimated at $200.7 M for the life of the mine or
on average $134.83/tonne milled. The total NSR royalty payments are evaluated at
$9.8 M or on average $6.56 per tonne milled. 


The financial results indicate a total before-tax cash flow of $137.9 M, a
before-tax Net Present Value (NPV) of $81.8 M at a discount rate of 8 %, a
before-tax Internal Rate of Return (IRR) of 140.5 % and a payback period of 1.1
years.


Table 3 - Project Evaluation Summary



      ----------------------------------------------------------------
                                                             Base Case
      Items                                                  (M CAD $)
      ----------------------------------------------------------------
      Total At-mine Revenue                                    353.276
      ----------------------------------------------------------------
      Pre-production Capital Expenditures (excludes Spares)      2.121
      ----------------------------------------------------------------
      Sustaining Capital Expenditures                            2.228
      ----------------------------------------------------------------
      Initial Working Capital Requirement                        5.317
      ----------------------------------------------------------------
      Mine Closure Costs                                         0.562
      ----------------------------------------------------------------
      Total Operating Costs                                    200.745
      ----------------------------------------------------------------
      Total NSR Royalty Payments                                 9.766
      ----------------------------------------------------------------
      Total Before-tax Cash Flow                               137.854
      ----------------------------------------------------------------
      Before-tax NPV @ 8%                                       81.823
      ----------------------------------------------------------------
      Before-tax NPV @ 6%                                       92.562
      ----------------------------------------------------------------
      Before-tax NPV @ 10%                                      72.636
      ----------------------------------------------------------------
      ----------------------------------------------------------------
      Before-tax IRR (%)                                         140.5
      ----------------------------------------------------------------
      Before-tax Payback Period (years)                            1.1
      ----------------------------------------------------------------



Sensitivity Analysis 

A sensitivity analysis indicates that, within the level of accuracy of the cost
estimates, project viability does not appear to be affected by the
under-estimation of capital costs and operating costs, taken individually. The
net present value is more sensitive to variations in operating expenses and the
price of gold. A gold price of approximately $875 per ounce results in
break-even condition i.e. yields an NPV of zero at a discount rate of 8%.


The full report will be filed on Sedar shortly under the heading "technical
report" and on our website.


This positive economic analysis justifies the continuation of our mine
development program at the Elder mine with the objective of completing a
preliminary feasibility study, or a feasibility study and putting the Elder gold
mine in production as soon as possible (within the next 12 months).


About Abcourt Mines Inc. 

Abcourt Mines Inc. is an exploration and development company with strategically
located properties in northwestern Quebec, Canada. The Elder Mine with 43-101
gold resources, the Abcourt-Barvue Project with 43-101 silver-zinc ore reserves
and resources and the Aldermac property with historical copper-zinc resources
are all former producers. Abcourt is now focused on bringing the Elder and
Abcourt-Barvue projects back into production with Elder as the first priority.
At the same time the company is working on other projects (Aldermac, Vezza,
Jonpol and Vendome) to increase its mineral resources inventory. A 43-101
resource calculation was completed in July, 2012, for the Elder Mine. A positive
43-101 feasibility study was completed by GENIVAR in 2007 on the Abcourt-Barvue
Project. In addition, mill equipment was purchased. To know more about Abcourt,
please visit our web site at www.abcourt.com and SEDAR. 


FORWARD-LOOKING STATEMENTS: Certain of the information contained in this news
release may contain "forward-looking information". Forward-looking information
and statements may include, among others, statements regarding the future plans,
costs, objectives or performance of Abcourt Mines Inc. (the "Company"), or the
assumptions underlying any of the foregoing. In this news release, words such as
"may", "would", "could", "will", "likely", "believe", "expect", "anticipate",
"intend", "plan", "estimate" and similar words and the negative form thereof are
used to identify forward-looking statements. Forward-looking statements should
not be read as guarantees of future performance or results, and will not
necessarily be accurate indications of whether, or the times at or by which,
such future performance will be achieved. Forward-looking statements and
information are based on information available at the time and/or management's
good-faith belief with respect to future events and are subject to known or
unknown risks, uncertainties, assumptions and other unpredictable factors, many
of which are beyond the Company's control. These risks, uncertainties and
assumptions include, but are not limited to, those described under "Risk
Factors" in the Company's amended and restated annual information form dated
November 26, 2010 and could cause actual events or results to differ materially
from those projected in any forward-looking statements. The Company does not
intend, nor does the Company undertake any obligation, to update or revise any
forward-looking information or statements contained in this news release to
reflect subsequent information, events or circumstances or otherwise, except if
required by applicable laws.


This press release was prepared by Mr. Renaud Hinse, a qualified person,
President of Abcourt Mines Inc.


FOR FURTHER INFORMATION PLEASE CONTACT: 
Abcourt Mines Inc.
Renaud Hinse
President and CEO
819 768-2857 or 450 446-5511
819 768-5475 or 450 446-3550 (FAX)
rhinse@abcourt.com


Caliber Investor Relations
Steve Zinanni
(647) 699-9957
Cell: (647) 896-0280
steve@caliberir.com

Abcourt Mines (TSXV:ABI)
Gráfico Histórico do Ativo
De Mai 2024 até Jun 2024 Click aqui para mais gráficos Abcourt Mines.
Abcourt Mines (TSXV:ABI)
Gráfico Histórico do Ativo
De Jun 2023 até Jun 2024 Click aqui para mais gráficos Abcourt Mines.