VANCOUVER, BC, Aug. 9, 2023
/CNW/ - Century Lithium Corp. (TSXV: LCE)
(OTCQX: CYDVF) (Frankfurt: C1Z) (Century Lithium or the
Company) is pleased to report successful progress in its
collaboration with Koch Technology Solutions (KTS), a Koch
Engineered Solutions (KES) company. As reported previously (see
April 17, 2023, news release) Century
Lithium and KTS are working together on the application of KTS's
Li-Pro™ system at Century's Lithium Extraction
Facility (Pilot Plant) in Amargosa
Valley, Nevada, USA.
"Century Lithium is delighted to see the progress made in our
collaboration with Koch Technology Solutions" stated Bill Willoughby, President, and CEO of Century
Lithium. "Our team, with KTS's input has successfully incorporated
and operated the equipment at our Pilot Plant with significantly
improved results."
Since October 2021, Century
Lithium has been continuously testing the extraction of lithium
from the claystone found at its 100%-owned Clayton Valley Lithium
Project (Project) in Nevada
utilizing a chloride-based leaching process. Testing of the
Li-Pro™ system was conducted to evaluate potential
improvements in the direct lithium extraction (DLE) area of the
Pilot Plant.
Adam Sackett, President of Koch
Technology Solutions, added, "The steady state results generated
onsite with the Koch Technology Solutions Li-Pro™ Direct Lithium
Extraction process has hit all our key milestones for the Century
pilot program. We are excited to move towards engineering and
executing a Li-Pro™ installation with commercial process
guarantees."
With the integration of KTS's DLE process, the grades of the
intermediate lithium solution produced at the Pilot Plant have
increased to the highest levels to date, with an average grade of
7.5 grams/liter (g/l) (7,500 parts per million) lithium. These
lithium concentrations are four times higher than previously
generated, with sodium concentrations almost an order of magnitude
lower.
Highlights To Date
- Successful installation and operation of Koch's
Li-Pro™ DLE process
- Li-Pro™ plant achieved steady state using Century
Lithium's chloride leaching process
- Manufacture intermediate solutions with lithium grades of 7 to
8 g/l concentrations with average lithium to sodium ratios of 0.9
to 1.1
- No observed degradation of media or accumulation of deleterious
elements
Operational Results
Since the installation of KTS's
DLE equipment, Century Lithium has focused on improvements related
to the operational aspects of the Pilot Plant and adjustments to
the final flowsheet. These improvements were well supported through
the development and incorporation of KTS's DLE equipment at the
Pilot Plant.
Century Lithium, with the support of KTS, has identified
techniques to improve lithium recovery within the DLE area while
minimizing deleterious elements in the final solutions.
Collaboration between Century Lithium and Koch staff is very
productive, generating ideas and changes that have resulted in the
complete removal of calcium and magnesium, and marked reduction of
sodium and potassium in the product solutions.
Qualified Person
Todd Fayram, MMSA-QP is the
qualified person as defined by National Instrument 43-101 and has
approved the technical information in this release.
About Century Lithium
Corp.
Century Lithium Corp. (formerly Cypress Development Corp.) is an
advanced stage lithium company, focused on developing its
100%-owned Clayton Valley Lithium Project in west-central
Nevada, USA. Century Lithium is
currently in the pilot stage of testing on material from its
lithium-bearing claystone deposit at its Lithium Extraction
Facility in Amargosa Valley,
Nevada and progressing towards completing a Feasibility
Study and permitting, with the goal of becoming a domestic producer
of lithium for the growing electric vehicle and battery storage
market.
ON BEHALF OF CENTURY LITHIUM CORP.
WILLIAM WILLOUGHBY, PhD., PE
President & Chief Executive Officer
NEITHER THE TSX VENTURE EXCHANGE NOR ITS REGULATION SERVICES
PROVIDER ACCEPTS RESPONSIBILITY FOR THE ADEQUACY OR ACCURACY OF THE
CONTENT OF THIS NEWS RELEASE.
Cautionary Note Regarding Forward-Looking
Statements
This release includes certain statements
that may be deemed to be "forward-looking
statements". Forward-looking statements are subject to risks,
uncertainties and assumptions and are identified by words such
as "expects," "estimates," "projects," "anticipates,"
"believes," "could," "scheduled," and other similar words. All
statements in this release, other than statements of historical
facts, that address events or developments that management of the
Company expects, are forward-looking statements. Although
management believes the expectations expressed in such
forward-looking statements are based on reasonable assumptions,
such statements are not guarantees of future performance, and
actual results or developments may differ materially from those in
the forward-looking statements. The Company undertakes no
obligation to update these forward-looking statements if
management's beliefs, estimates or opinions, or other factors,
should change. Factors that could cause actual results to differ
materially from those in forward-looking statements, include market
prices, exploration, and development successes, continued
availability of capital and financing, and general economic, market
or business conditions. Please see the public filings of the
Company at www.sedar.com for further
information.
View original content to download
multimedia:https://www.prnewswire.com/news-releases/century-lithium-updates-progress-on-testing-with-koch-technology-solutions-301896776.html
SOURCE Century Lithium Corp.