Arizona Sonoran Copper Company Inc. (TSX:ASCU |
OTCQX:ASCUF) (“ASCU” or the “Company”) today announced it has
completed its NI 43-101 Prefeasibility Study (“PFS”) for its Cactus
Project in Arizona, USA. The Standalone PFS outlines a lower risk,
top 10 potential copper operation in the domestic USA, producing
LME Grade A copper cathodes onsite via heap leach and a Solvent
Extraction/Electrowinning (“SXEW”) plant. All dollar amounts
referenced herein in US dollars, and all references to tons are
short tons, unless otherwise noted.
This press release features multimedia. View
the full release here:
https://www.businesswire.com/news/home/20240221970177/en/
FIGURE 1: Annual Revenues and EBITDA Over
Annual Production (Graphic: Business Wire)
The Company intends to file a technical report (the
“Technical Report”) in respect of the PFS in accordance with
National Instrument 43-101 – Standards of Disclosure for Mineral
Projects (“NI 43-101”) on SEDAR+ (www.sedarplus.ca) under
the Company’s issuer profile and the Company’s website within 45
days of the date of this news release.
A webinar will be held on February 22, 2024, at 10:00 am ET.
Please join George Ogilvie, Nick Nikolakakis, Bernie Loyer and
Anthony Bottrill in discussion of the PFS and the Company’s next
steps by registering here
https://www.bigmarker.com/vid-conferences/ASCU-VID-THF.
Cactus PFS Highlights
Scalable, Long-Life Operations
- Average annual production of approximately 55
ktons or 110 million pounds (“lbs”) of copper (“Cu”), with a peak
of 74 ktons or 149 million pounds of copper
- Initial Life of Mine (“LOM”) 21 years, recovering 1,153
ktons or 2.31 billion pounds of Copper LME Grade A cathode onsite
via heap leach facility and SXEW
- Maiden Proven & Probable (“P&P”) Reserves of 276.3
million tons at 0.48% Soluble Copper (“Cu TSol”) or 3.0
Billion lbs Copper
- Favourable metallurgy with a range of 85%-92% LOM
average soluble copper recoveries
- Private land ownership with streamlined permitting
process
- Low carbon footprint mining project:
- Powered by an existing 69 KV Transmission line with access to
“Green Energy” through the Palo Verde Nuclear Plant West of Phoenix
for costs of $0.07/kWh
- Heap Leach and SXEW Process
- Conveyors and radial stackers used to move ore to leach
pads
Robust Economics
- First quartile capital intensity of $10,343/tonne of
average annual production
- Total initial capital cost of $515 million,
including $75 million of contingencies over an 18-24 month
construction period
- Total revenues of $9.0 billion over 21 years
- Post-tax unlevered Free Cash Flow of $2.4 billion
- C1 Cash Costs of $1.84/lb and All in Sustaining
Cost (“AISC”) of $2.34/lb
- Post-tax net present value (“NPV”) $509 million
(CA$687 million) using an 8% discount rate and an internal rate
of return (“IRR”) of 15.3% and using a $3.90/lb flat long-term
copper price
- Pre-tax NPV $733 million (CA$990 million)
- Post-tax payback period of 6.8 years from initial
production
- At $4.25/lb Copper the NPV increases to $780 million post-tax
(CA$1,054 million) and $1,064 million pre-tax (CA$1,436 million),
using an 8% discount rate
Significant Copper Project in the USA
- Proven & Probable (“P&P”) Reserves of 276.3 million
tons at 0.48% Soluble Copper (“Cu TSol”) or 3.0 Billion lbs
Copper
- Underground Proven Reserve grade of 0.89% and 0.82% Cu TSol
from Cactus East and Parks/Salyer, respectively
- Measured & Indicated Resources of 5.2 billion lbs Copper
and Inferred Resources of 2.2 billion lbs Copper (as announced
October 16, 2023) (inclusive of reserves)
Future Opportunities to Further Improve Business Case
- Drilling to upgrade known inferred resources and bring them
into the mine plan potentially increasing the LOM production,
reducing underground development costs, operating expenses, capital
expenses and overall strip ratio
- Drilling to prove a maiden resource at MainSpring as a
potential open pit providing operational flexibility and gaining
lower cost access to the Parks/Salyer deposit. Bringing MainSpring
into the mine plan potentially improves operational and financial
synergies within the Cactus Project
- Continued exploration success on the Cactus Project in the “Gap
Zone”, below the envelope of the existing Cactus West Open Pit
Shell and in the North-East Extension.
- Nuton LLC’s (“Nuton") leaching technology driving primary
sulphide optionality, currently excluded from the mine plan
George Ogilvie, ASCU President and CEO commented, “The
55,000-ton Copper Cathode per annum mine plan presented in the PFS
illustrates an achievable long-life operation with robust economics
and an opportunity for continued scaling of the asset. Our
operation has the potential to be among the top 10 copper
operations within the US, supplying the domestic supply chain with
copper cathodes in the near term. With global copper mine
disruptions occurring and a structural deficit currently underway,
our timing to develop the asset has a high likelihood to coincide
with much higher copper incentive prices. As compared to the
original PEA, the PFS demonstrates a significant increase of free
cash flow at a conservative long-term copper price assumption of
$3.90 per pound.”
He continued, “A real organic growth opportunity exists within
our 5,370 acres at the MainSpring Property. Based on initial
drilling of our MainSpring property there are early indications for
Mainspring to be the southern near surface extension of our
Parks/Salyer deposit and thus will be a focus of drilling in 2024.
Through our 2024 drilling programs, our team has the potential to
convert the 1.3 billion pounds of leachable inferred resources of
copper to the indicated resources category, contributing to an
extended mine life. Over and above, ASCU also looks forward to the
continued metallurgical testing and incorporation of the Nuton
technology to our Cactus flowsheet, which if executed, lowers our
cost of capital, provides a funding partner for the initial capex
and ongoing operating costs, as well as provides execution support
from a top global mining partner.”
“With this cornerstone now placed, we are excited to continue
building Cactus, which today is a significant asset, with plenty of
future optionality to continue upgrading the asset with scale.”
Bernie Loyer, ASCU SVP Projects notes “Our Cactus Project
PFS demonstrates a solid business case, and the potential to
deliver a long-life operation utilizing a well-established and
industry proven process technology in the treatment of ore from
four separate and well understood feed sources. All situated on
privately held ground, this brownfield project site located within
45 minutes of the Phoenix city center which is the 10th largest
metropolitan area within the United States, is wrapped with an
enviable complement of all required infrastructure. Add to all of
that, a project team with a strong combination of project and
operational experience on complex mining projects throughout North
and South America, and the foundation for the Cactus Project and
future operation is well-placed.”
Pre-Feasibility Summary
The 2024 PFS outlines a lower risk and long-life copper project
with low first quartile capital intensity. The heap leach operation
will produce on average 55 kstpa of LME Grade A copper cathodes via
SXEW. Key metrics are shown in TABLE 1 below.
Conventional open pit mining methods have been selected for the
extraction of oxide and secondary sulphide material from the lower
grade Cactus West pit, while the higher-grade Parks/Salyer and
Cactus East deposits will be mined via underground using the
Sublevel Caving (“SLC”) method from the 1,500 ft (457 m) and 1,200
ft (366 m) levels, respectively. Reserve grades of the Parks/Salyer
and Cactus East deposits are high grade, at 0.93% CuT and 0.95%
CuT, and 0.82% Cu TSol and 0.89% Cu TSol, respectively. The
Stockpile will be a rehandling exercise moving low grade tonnage to
a lined pad for leaching. Onsite facilities at the mine site will
consist of an open pit, underground mining operations, a fine
crushing plant incorporating all crushing, classification,
agglomeration and conveying systems and an SXEW process plant. On
site supporting infrastructure will include site power
distribution, access roads and heap leach facilities.
Table 1: 2024 PFS Highlights
Financial Metrics
Unit
PFS LOM
Copper Price Assumption
$/lb
$3.90
Revenue
$ millions
$8,994
Operating Costs*
$ millions
$4,029
EBITDA
$ millions
$4,746
Unlevered FCF (pre-tax)
$ millions
$3,099
Unlevered FCF (post-tax)
$ millions
$2,407
Base Case Economics
Pre-tax NPV(8%)
$ millions
$733
Pre-tax IRR
$ millions
17.7%
NPV / Initial Capital
(post-tax)
Ratio
1:1
Post-tax NPV(8%)
$ millions
$509
Post-tax IRR
%
15.3%
Post-tax Payback Period**
Years
6.8
Initial Capital
$ millions
$515
Sustaining Capital (primarily
UG)
$ millions
$1,221
Effective Tax Rate
%
22.3%
Production
Construction Period
Months
18-24
Mine Life
Years
21
Total Mineralized Material
Millions tons
276.3
Cu Avg Production (Years 1-5)
Millions lbs/year
100
Cu Avg Production (Years
6-10)
Millions lbs/year
105
Cu Avg Production (Years
11-15)
Millions lbs/year
136
Average Annual LOM Production
Millions lbs / ktons
110 / 55
Total Payable Copper
Million lbs
2,306
Average Head Grade
% Cu TSol
0.48%
Open Pit Strip Ratio
Waste:Ore
1.96
Costs
LOM C1 Cash Costs***
$/Cu lb
$1.84
LOM All-in Sustaining
Costs****
$/Cu lb
$2.34
Mining
Open Pit
$/ ton mined
$2.20
Underground
$/ ton mined
$20.21
Leaching & Processing
$/ ton placed
$2.96
General & Administrative
$/ ton placed
$0.12
kt = thousands of short tons; kstpa = thousands of short tons
per annum
FOREX Conversion = US $1.00 = CA $1.35
* Operating cash costs consist of mining costs, processing
costs, and G&A
** Payback period exclusive of construction
*** Total cash costs consist of operating cash costs plus
transportation cost, royalties, treatment and refining charges
**** AISC consist of total cash costs plus sustaining capital,
closure cost and salvage value
TABLE 2: Pre- and Post-Tax Sensitivity to the Copper
Price
$3.75
$3.90
$4.00
$4.25
$4.50
$4.75
Pre-tax
NPV(8%), $m
$592
$733
$828
$1,064
$1,299
$1,535
Post-tax
NPV(8%), $m
$389
$509
$587
$780
$971
$1,162
IRR, %
13.6%
15.3%
16.5%
19.3%
22.1%
24.9%
Payback years1
7.4
6.8
6.4
5.7
5.2
4.8
1 Payback period calculated starting from start of commercial
production
Project Overview
The Cactus Mine Project is a brownfield project located
approximately 6 mi (10 km) northwest of the city of Casa Grande and
40 road miles south-southwest of the Greater Phoenix metropolitan
area in Arizona. The Cactus Mine Project is accessible on North
Bianco Road off of West Maricopa-Casa Grande Highway with direct
access to interstate highway 10. During historic ASARCO operations
(1974-1984), a rail spur was connected directly with the United
Pacific Railroad to ship concentrates to its El Paso refinery in
Texas; while the spur has been removed, the onsite rail line is
still in existence. Current onsite infrastructure includes power
lines and substation, water wells and a water pond, geological
buildings, core sheds and administrative offices, keeping the
capital intensity low and demonstrating robust economics.
Since 2019, ASCU has drilled 141 new holes at the Cactus West
and East deposits to support verification, metallurgical testing,
and resource extension for the Cactus mineral resource estimate.
The Parks/Salyer resource database is composed primarily of 74 new
holes drilled by ASCU between late 2020 and 2023. The historical
ASARCO holes for the district comprised of 171 drillholes. The bulk
of these holes were in the Cactus West and Cactus East deposits or
comprised regional exploration holes. An extensive verification and
re-assay programs were undertaken to support the use of historical
drilling in resource estimates. Since 2020, ASCU has drilled 514
sonic drillholes to support resource estimates on the stockpile. In
addition to verification of historical drilling, for all ASCU holes
physical checks on collar, downhole survey, logging, and assay
quality assurance and quality control (“QA/QC”) have been completed
by the qualified person.
The Cactus Mine Project is host to a large porphyry copper
system that has been dismembered and displaced by Tertiary
extensional faulting. The major host rocks are Precambrian Oracle
Granite and Laramide monzonite porphyry and quartz monzonite
porphyry. The mine trend features the formation of horst and graben
blocks of mineralization where the Cactus deposits are situated,
extending from the Cactus East deposit, southwest to the
Parks/Salyer deposit. Drilling to the northeast and southwest along
the trend indicates that mineralization continues in both
directions and at depth at the Cactus West deposit.
Reserves and Resources
The PFS is based on the updated 2023 Mineral Resource Estimate
(“MRE”), as published on October 16, 2023, showing a 221%
increase of leachable Measured and Indicated (“M&I”) pounds
over the mineral resource base used in the 2021 PEA. The Mineral
Resources and Reserves for the Cactus Mine Project are shown in
TABLES 3 and 4 and illustrated in FIGURE 3 below.
Table 3: Cactus Project Total Measured, Indicated and
Inferred Mineral Resource
Material Type
ktons (kt)
CuT (%)
TSol (%)
Contained Cu (k lbs)
Total Resources
MEASURED
Total Leachable
9,100
0.230
41,900
Total Primary
1,300
0.315
8,000
Total Measured
10,400
0.241
49,800
INDICATED
Total Leachable
348,500
0.629
4,387,200
Total Primary
86,800
0.425
737,000
Total Indicated
435,300
0.589
5,124,200
M&I
Total Leachable
357,600
0.619
4,429,000
Total Primary
88,000
0.423
745,000
Total M&I
445,700
0.580
5,174,000
INFERRED
Total Leachable
107,700
0.607
1,307,900
Total Primary
126,200
0.357
900,000
Total Inferred
233,800
0.472
2,207,900
Notes:
1.
Leachable copper grades are reported using sequential assaying
to calculate the soluble copper grade. Primary copper grades are
reported as total copper, Total category grades reported as
weighted average copper grades of soluble copper grades for
leachable material and total copper grades for primary material.
Tons are reported as short tons.
2.
Stockpile resource estimates have an effective date of 1 March
2022, Cactus resource estimates have an effective date of 29th
April 2022, Parks/Salyer resource estimates have an effective date
of 19th May 2023. All resources use a copper price of
US$3.75/lb.
3.
Technical and economic parameters defining resource pit shell:
mining cost US$2.43/t; G&A US$0.55/t, 10% dilution, and 44°-46°
pit slope angle.
4.
Technical and economic parameters defining underground resource:
mining cost US$27.62/t, G&A US$0.55/t, and 5% dilution.
5.
Technical and economic parameters defining processing: Oxide
heap leach (HL) processing cost of US$2.24/t assuming 86.3%
recoveries, enriched HL processing cost of US$2.13/t assuming 90.5%
recoveries, Primary mill processing cost of US$8.50/t assuming 92%
recoveries. HL selling cost of US$0.27/lb; Mill selling cost of
US$0.62/lb.
6.
Royalties of 3.18% and 2.5% apply to the ASCU properties and
state land respectively. No royalties apply to the MainSpring
(Parks/Salyer South) property.
7.
For Cactus: Variable cutoff grades were reported depending on
material type, potential mining method, and potential processing
method. Oxide material within resource pit shell = 0.099% TSol;
enriched material within resource pit shell = 0.092% TSol; primary
material within resource pit shell = 0.226% CuT; oxide underground
material outside resource pit shell = 0.549% TSol; enriched
underground material outside resource pit shell = 0.522% TSol;
primary underground material outside resource pit shell = 0.691%
CuT.
8.
For Parks/Salyer: Variable cut-off grades were reported
depending on material type, associated potential processing method,
and applicable royalties. For ASCU properties - Oxide underground
material = 0.549% TSol; enriched underground material = 0.522%
TSol; primary underground material = 0.691% CuT. For state land
property - Oxide underground material = 0.545% TSol; enriched
underground material = 0.518% TSol; primary underground material =
0.686% CuT. For MainSpring (Parks/Salyer South) properties - Oxide
underground material = 0.532% TSol; enriched underground material =
0.505% TSol; primary underground material = 0.669% CuT.
9.
Mineral resources, which are not mineral reserves, do not have
demonstrated economic viability. The estimate of mineral resources
may be materially affected by environmental, permitting, legal,
title, sociopolitical, marketing, or other relevant factors.
10.
The quantity and grade of reported inferred mineral resources in
this estimation are uncertain in nature and there is insufficient
exploration to define these inferred mineral resources as an
indicated or measured mineral resource; it is uncertain if further
exploration will result in upgrading them to an indicated or
measured classification.
11.
Totals may not add up due to rounding.
As shown in TABLE 4 below, a total of 276 million short
tons or 3.0 billion pounds were converted into a P&P Reserve
out of the leachable M&I Resource base of 4.43 billion lbs,
representing a conversion rate of 68%. The Inferred material and
primary sulphides are treated as waste, with conversion drilling at
Cactus West, a focus for 2024 as part of the dual track ASCU/Nuton
Work Plan as announced on January 30, 2024. Mineral
resources that are not mineral reserves do not have demonstrated
economic viability.
Table 4: Cactus Mine Project Reserves Statement by
Deposit
Unit
Cactus West Open Pit
Stockpile Open Pit
Cactus East
Underground
Parks/ Salyer
Underground
Totals
Proven
Tons
3,600,000
3,600,000
CuT (%)
0.249
0.249
Cu TSol (%)
0.225
0.225
Cu (M lbs)
17.9
17.9
Probable
Tons
71,921,000
76,777,000
27,739,000
96,248,000
272,686,000
CuT (%)
0.310
0.163
0.950
0.930
0.552
Cu TSol (%)
0.260
0.136
0.885
0.820
0.487
Cu (M lbs)
445.4
251.0
527.0
1,789.7
3,013.0
Proven + Probable
Tons
75,521,000
76,777,000
27,739,000
96,248,000
276,286,000
CuT (%)
0.307
0.163
0.950
0.930
0.549
Cu TSol (%)
0.259
0.136
0.885
0.820
0.484
Cu (M lbs)
463.3
251.0
527.0
1,789.7
3,031.0
Notes to the Mineral Reserves:
1.
Mineral Reserves have an effective date of November 10, 2023.
The Qualified Person for the underground estimates of Cactus East
and Parks/Salyer is Nat Burgio of AGP Mining Consultants Inc. The
Qualified Person for the open pit estimates of Cactus West and
Stockpile is Gordon Zurowski of AGP Mining Consultants Inc.
2.
The Mineral Reserves were estimated in accordance with the CIM
Definition Standards for Mineral Resources and Reserves.
3.
The Mineral Reserves are supported by a combined open pit and
underground mine plan, based on open pit and underground designs
and schedules, guided by relevant optimization procedures.
Inputs to that process are:
- Metal prices of Cu $3.70/lb.
- Processing costs which are variable and based upon material
type, processing destination, copper grade, and copper recovery.
Processing costs include a fixed unit cost component, a net
consumption cost, and a cost for refining and selling copper
cathode.
- General and administration cost of $0.47/ton processed.
- Royalty cost of 2.5% for BCE land and 2.54% for Parks/Salyer,
Cactus and Stockpile Ores, excluding BCE ore – royalty discussion
noted below.
- Process recoveries which are variable depending upon
mineralization type, sequential copper grades, and comminution
size.
- Open pit geotechnical design criteria from Call and Nicholas,
Underground geotechnical design criteria from Call and Nicholas,
Open pit mining costs including an escalation factor with pit
depth.
- Underground mining cost of $27.62.
4.
The footprint delineations for the Cactus East and Parks/Salyer
mines were based on a resource model block cash flow dollar value
(CFTC1) of $27.62 (net of process, G/A and royalties). Drawpoints
were shut-off when the grade value fell below a CFTC1 of $27.62
following the necessary removal of swell material within the
footprint.
5.
Dilution and mining loss adjustments are incorporated into the
underground mining inventories by way of cave flow modelling
software. Inferred resources included in the mixing process have
been assigned zero grade. No allowance for mining dilution or ore
loss has been provided in the open pit mining inventories.
Mining Operations
The Cactus Mine plan includes production from four separate
mining areas: Cactus West Open Pit, Historical Stockpile, Cactus
East Underground, and Parks/Salyer Underground. Ore processing in
the mine schedules involves oxides and secondary sulphides being
processed on a heap leach after multi-stage crushing.
The mine production schedule is initially focused on the surface
sources of ore (Stockpile and Cactus West Open Pit) beginning in
year -1, along with Parks/Salyer underground starting development
in Year 1. The Cactus East deposit is developed later in the mine
life, starting in Year 8. Cactus West and the Stockpile ore sources
are depleted in Year 7 after which the ore stream becomes
exclusively underground. The overall site layout is shown in
FIGURE 8.
The Cactus West mine life consists of 2 phases and includes one
year of pre-stripping and seven years of mining. Phase 1 starts
with 24 million tons (“Mt”) of pre-production stripping and is
completed in Year 4. Phase 2 mining begins in Year 2 and is mined
out in Year 6. Target ore production is 12 Mt per annum with a peak
mining rate of 47 Mt in Years 2 and 3. A total of 75.5 Mt of leach
ore grading 0.307% total copper is mined at a strip ratio of 1.9 to
1. Bench elevations at Cactus West range from the 1,440-ft level to
the 380-ft level.
Over the course of the open pit mine schedule, approximately
13.1 Mt of low-grade ore is stockpiled and reclaimed in order to
smooth the ore release from the open pits. This amount includes
approximately 3.0 Mt of material stockpiled in the first three
years of mining, and then processed in Year 3 and 4, and another 10
Mt stockpiled later in the mine schedule before being reclaimed in
Years 7 and 8.
Historic Stockpile (FIGURE 5) mining begins near the end
of the pre-production year with approximately 3.0 Mt of ore sent to
the leach pad. Mining continues concurrently with the Cactus West
pit into Year 7 at an annual ore production rate of 12 Mt. A total
of 76.8 Mt of leach ore at 0.163% total copper is mined. A small
amount, 5.5 Mt of waste is mined from the historic stockpile and
sent to the waste storage areas.
The initial Parks/Salyer SLC (FIGURE 6) level will
commence at 1,120 ft (341 m) below surface and include 11 sublevels
to a final depth of 1,930 ft (588 m) below surface. Access to the
Parks/Salyer deposit will be via a surface portal and twin
declines. One decline will be dedicated to ore haulage using an
inclined conveyor and the other decline providing access for
personnel and equipment. Production extends from year 1 to 20, with
steady state production beginning in year 7 to year 20, peaking at
6.9 Mtpa in year 13. A total of 96 Mt of leach ore @ 0.82% Cu TSol
will be processed.
The initial Cactus East SLC (FIGURE 7) level will
commence in year 9 at 1,325 ft (404 m) below the surface and will
be comprised of 7 sublevels to a final depth 1,845 ft (562 m) below
surface. Access will be via a single decline with a portal located
within the existing Cactus West pit. Ore haulage to surface will be
via a vertical conveyor which can be supplemented with truck
haulage to surface via the open pit if necessary. Production is
planned from year 9 to 19, with steady state production beginning
in year 12, peaking at 3.9 Mtpa in year 15. A total of 28 Mt of
leach ore @ 0.89% Cu TSol will be processed.
SLC production crosscuts have primarily been designed so that
each level is horizontally offset from the level above and below.
The design parameters for the SLC production drives at Cactus East
and Parks/Salyer are in line with other SLC operations.
The amount of ore to be extracted will be limited in the upper
three production levels to the following proportions:
- First Level ~40% (swell only)
- Second Level ~60%
- Third level ~100%
- Lower levels >100% to shutoff grades or dollar values.
The production strategy will help control caveability, minimise
the formation of air gaps and create a blasted ore blanket above
the production levels to minimise early dilution entry from the
overburden rocks. These restricted draw rates also apply to areas
where large step-outs distances are required from one sublevel to
the next.
The Cactus East Ore/Waste Handling System consists of a crusher
station and a 1,600 ft (488 m) vertical conveyor with a capacity of
630 tons/h that will convey ore from the top of the orebody to
surface via a vertical raise feeding an overland conveyor. Ore will
be hauled by 55-ton diesel trucks to a sizer located adjacent to
the bottom of the vertical conveyor. Ore will be crushed to a
maximum 6-in dimension. A short conveyor from the sizer will feed
the vertical conveyor. Waste will be trucked to the portal for
disposal within the Cactus West open pit.
The mine plan for Parks/Salyer consists of two ramps with one
dedicated for material handling. The ore/waste handling system
consists of a series of initially four, extending to five
switchback conveyors and two crushing sizers on -270 L, one of
which will subsequently be relocated at the -470 L. that will
deliver material from the mine working levels to the surface
portal, from where materials will then be transported on surface
via an overland conveyor.
Ventilation is driven by a fresh air drive developed from the
access drive, in which the fresh air will be splitting right and
left to connect to the return air drives at the extremities of the
footprint. This allows natural flow of ventilation through the
entire footprint.
Processing Operations
Material mined from the existing stockpile will be placed in
20-ft lifts and material from all other sources will be stacked in
30-ft lifts. Material will be reclaimed and transferred by haul
truck to the crushing circuit where it will be crushed down to P80
minus ¾-in. From the crushing circuit, the material will transfer
by overland conveyor to the agglomeration drums, mobile transfer
conveyors, and mobile radial stacker to be placed on the
geomembrane lined heap leach facility (HLF).
Leaching solutions, containing dilute sulfuric acid will be
pumped and applied to the top of each lift and allowed to percolate
though the copper leach material. Copper is dissolved into the
solution while acid is consumed at approximately 13.6 lb/ton of
material leached. Acid consumption is net of regenerated acid in
the SXEW process. The height of the leach material on the pad will
eventually reach approximately 180 ft (55 m) in overall height.
The pregnant leach solution (PLS) collected from the HLF will be
conveyed in pipes to the heap leach ponds where it will be pumped
for processing in a copper SX/EW plant capable of producing
initially up to 30,000 ton/y of copper cathodes with a design PLS
flow of up to 12,000 gpm and grade at approximately 3.0 g/pL Cu
based on an overall 71% total copper (85-92% soluble copper)
recovery from the heap leaching method for the resources
considered. The solvent extraction plant is designed to be operated
in a series, parallel, or series-parallel configurations with a
single stage of stripping. The optionality of the solvent
extraction plant will allow the plant to operate at 4,000 gpm,
8,000 gpm, or 12,000 gpm PLS flowrates based on the variability in
copper grades and tonnages in the mine plan.
The electrowinning circuit capacity will be expanded in Year 3,
doubling in size to the overall plant capacity required to a
nominal 60,000 ton/y of copper cathodes.
The principal objective of the HLF design is to efficiently
extract copper by leaching metals within the geotechnically stable
facility. The anticipated ore production will be approximately
65,000 tons/d for the first seven years and reduced to 24,500
tons/d after that for the life-of-mine (LOM) for an average of
55,000 tons of cathode production annually. The pad will be loaded
with conveyor belts coming in from the west along the northern side
of the pad to discharge to the eastern area of the pad (Phase 1).
This area provides a relatively flat area that facilitates the
construction of the first phase of the pad and allows for mining of
the existing stockpile to liberate additional space for the
consecutive phases of construction. A visual representation of the
flow sheet is depicted below, in FIGURE 9.
Cost Estimates
The capital cost estimates for the PFS were developed with a
-15% to +20% accuracy and an estimated contingency of approximately
15% according to the Association of the Advancement of Cost
Engineering International Class 4 estimate requirements. The
estimates include the cost to complete the design, engineering,
procurement, construction and commissioning of all process plant
facilities.
The project capital cost estimate was compiled by Ausenco
Engineering USA South Inc. (“Ausenco”) with input from AGP and
Samuel Engineering for the open pit, underground mining operation,
SXEW process plant, conveying, crushing and screening equipment,
site sub-station, site power distribution, access roads, heap leach
facilities and associated infrastructure. all direct costs, growth
allowances, project indirect costs, and associated contingency
within their scope of work, but separately identified.
An 18–24-month construction period is projected with the initial
capital costs and sustaining development costs summarized in the
table below.
Table 5: Initial and Sustaining Capital Costs (18% LOM
contingency included)
Capitalized Costs
Initial Capital
Sustaining Capital
Mining and Processing
$173 million
$905 million
Processing
$4 million
n/a
Mining (Pre-Stripping)
$78 million
n/a
MINING - Open Pit - Cactus West
$24 million
$20 million
MINING - Underground - Cactus East
n/a
$341 million
MINING - Underground - Parks/Salyer
$57 million
$544 million
MINING - Underground - Combined/Shared
$11 million
n/a
Other
$342 million
$315 million
Infrastructure
$56 million
$0.3 million
Crushing And Conveying
$29 million
$6 million
Leaching And Waste Rock Storage
$66 million
$126 million
Solvent Extraction (SX)
$30 million
n/a
Electrowinning (EW)
$26 million
$14 million
Reagents
$1 million
n/a
Process Plant Services and Utilities
$4 million
n/a
Project Execution
$54 million
$8 million
Provisions
$75 million
$160 million
Total
$515 million
$1,221 million
Operating Cost Summary
Mining operating cost estimates, prepared by AGP, are based on a
small owner’s team managing mining activities using an
owner-operator model. Process operating cost estimates were
prepared by Samuel Engineering and G&A cost estimates were
prepared by Ausenco with input from ASCU, as summarized in the
table above.
Unit Cost table
Operating costs have been based on a delivered diesel price of
$3.49 per gallon and are in line with current local pricing. Power
will be sourced from a grid supplying 69kv to site, with power
costs estimated at $0.07/kWh.
Site Infrastructure Summary
The facilities at the mine site will consist of an open pit,
underground mining operation, SXEW process plant, conveying,
crushing and screening equipment, site sub-station, site power
distribution, access roads, heap leach facilities and associated
infrastructure.
Local Resources and Infrastructure
The Cactus Mine Project is located approximately 3 miles
northwest of the City of Casa Grande, Pinal County, Arizona. It is
40 road miles south-southeast of the Greater Phoenix metropolitan
area and approximately 70 road miles northwest of Tucson. It is
easily accessible from the Interstate 10 (I-10) freeway, which is
approximately 10 mi east of the historic Sacaton Mine. The Greater
Phoenix area is a major population centre (approximately 4.8M
persons) with a major airport and transportation hub and
well-developed infrastructure and services that support the mining
industry. Location benefits include:
- Electric power is available from Arizona Public Service’s (APS)
69 kV transmission line which passes on the South side of the site
and connects to an existing substation owned by ASCU.
- Paved road and easy access to the interstate networks for
transport and two major Interstates Highways (I-10 & I-8) less
than 10 miles away from the Cactus Mine Project.
- Well established road network existing from either ADOT, Pinal
County or the City of Casa Grande surrounding the property.
- Union Pacific rail road line and rail spur adjacent to the
property.
- Five miles distance to Casa Grande and allowing the ability of
the town to supply materials/consumables in addition to just
labor.
- Kinder Morgan/El Paso Natural Gas two high pressure natural gas
pipelines adjacent to the property should natural gas be
needed.
- The City of Casa Grande Water Treatment Facility located within
3 miles of the Cactus Mine Project that can supply effluent water
for the operation and possibly treat waste.
- An existing Arizona Water Company potable water line is
adjacent to the property.
- Water supply is already available via buried pipeline to the
property boundary as a result of prior mining and commercial
operations.
- The cities of Casa Grande and Maricopa are nearby and, combined
with Phoenix, can supply sufficient skilled labor for the Cactus
Mine Project. In addition, the State of Arizona has a significant
presence of copper mining in the state that can specifically
provide skilled labor to the Cactus Mine Project.
Metallurgical Testwork
The metallurgical studies and testing for the Cactus Project has
been ongoing since late 2019, via 45 column tests covering the
resources identified in the study. Additional tests include, bottle
roll testing, mineralogical analyses and other metallurgical and
materials property testing. Arizona Sonoran geologists are working
with metallurgical engineers to quantify the metallurgical
performance from the samples obtained in a large drilling campaign.
The drill core samples were safely recovered and placed in bags to
be studied by geologists and subsequently shipped for testing to a
well-established Mineral Processing research and development firm
in Reno, Nevada (McClelland Analytical Service Laboratory
(“McClelland”), an ISO 9000, ISO 17025 accredited facility).
Additional testing work was completed on-site by ASCU staff and at
HydroGeoSense Inc. (“HGS”) laboratories in Tucson, Arizona. The
metallurgical test program completed at McClelland has been
developed by and supervised by Mr. James L. Sorensen. Mr. Sorensen
has also reviewed and inspected the ongoing metallurgical testing
at site and information developed by HGS.
Ownership, Social License, Permitting, Taxes and
Royalties
The Cactus Mine Project is 100% controlled by ASCU through its
wholly owned subsidiary Cactus 110 LLC and encompasses an area of
approximately 5,381 acres, as shown in FIGURE 10. The Cactus
Mine Project includes exploration and mining on private land and on
two Arizona State Land Department ("ASLD”) leases. There is no
federal nexus for permitting the project.
Of the 5,381 acres, 4,731.92 acres is fee simple land, three
ASLD prospecting permits that the State has surface and minerals
(649.12 acres), two ASLD prospecting permits that the State has
minerals only with ASCU owning the surface (797.5 acres) and 18 BLM
unpatented mining claims, this is for mineral only as ASCU owns the
surface rights (320 acres). The BLM unpatented mining claims are
outside of the known mineralization and there are currently no
plans for mining at this area.
ASCU has a well-developed community engagement plan that it has
implemented through numerous public meetings and outreach. With the
presence of legacy mining in the Casa Grande area and the
determination of Cactus as a “brownfield” and disturbed site, the
local community is supportive of the Cactus Mine Project. There is
no significant opposition to the Cactus and Parks/Salyer
Project.
Permitting is limited to State of Arizona-required permits
including the Aquifer Protection Permit, Industrial Air permits and
the Mined Land Reclamation Permit which ASCU has received from
state regulators. Modifications of each will be required to address
changes in the mine plan presented in this PFS.
A Mined Land Reclamation Plan was completed and submitted to the
Arizona State Mine Inspector’s office in January 2023. The
submitted plan does not include the Parks/Salyer mine plan and will
therefore need to be modified to reflect the addition of new
facilities described in this PFS.
In 2009, approximately 25 years after the Cactus Mine ceased
operation, the mine was conveyed to the ASARCO Multi-State
Environmental Custodial Trust as part of ASARCO bankruptcy
proceedings, who helped lead a subsequent remediation program.
Structures were demolished and reclaimed, and site characterization
studies were conducted. Based on the results of the
characterization studies and reclamation work, the ADEQ released
ASCU from potential legacy liabilities, under the terms of the
Prospective Purchaser Agreement (“PPA”) signed in 2019. The PPA
does not cover unidentified environmental conditions or
contamination.
A corporate tax rate of 25.9% combined federal and state taxes
has been applied to taxable income in the PFS with an effective tax
rate of 22.3% after applicable deductions and credits. A royalty of
2.5% was applied to all sales from the Cactus deposits and the
Parks/Salyer deposit. A royalty of 2.5% was applied to all sales
from the Bronco Creek Exploration (“BCE”) land (west of the
Parks/Salyer deposit). As cathodes will be produced onsite, no
transport or refining fees have been added.
The Cactus Mine Project is subject to three royalties based on
potential mining production. Tembo/Elemental Altus holds a 3.18%
net smelter return (“NSR”) royalty, with an option to buy back
0.64% possible for payment of $8.9 million. BCE holds a 1.50% NSR
royalty based on a portion of the Parks/Salyer Deposit, with an
option to buy back 1% for payment of $0.5 million. ASLD owns a
sliding net return royalty (2.00% to 8.00% and estimated at 2%)
that is payable to ASLD and the State Trust on a portion of
production from the Parks/Salyer Deposit, overlapping with BCE
land. ASCU still needs to formalize the royalty percentages with
ASLD. Formalization will be done once ACSU submits a Mineral
Development Report to ASLD to convert the existing MEP to a Mineral
Lease.
Exploration Upside
The Cactus Mine Project mineral resource estimate includes three
deposits along a 4 km mine trend. The mineralization is present
within horst blocks developed as part of regional extensional
faulting. High grade mineralization was emplaced within brecciated
host granite at the margin of the intruding monzonite porphyry zone
and locally forms a linear NE trend called the mine trend.
Drilling has demonstrated potential for extending mineralization
south of Parks/Salyer onto MainSpring as shown in FIGURE 11.
At the Cactus West deposit, potential to extend resources exists
towards the SW adjacent to the PFS pit and also on the NE edge.
These are zones where higher-grade primary mineralization as part
of the mine trend have been intercepted previously. The NE
Extension zone represents a further horst block of mineralization
to the NE of Cactus East that to date has been explored by wide
spaced historical drilling. ASCU drilled one exploration hole into
the target in 2023. The Gap Zone represents a deeper target between
Parks/Salyer and Cactus West. There is potential to explore for a
down dropped extension of Parks/Salyer within this zone with
analogies to Cactus East.
Next Steps
Future opportunities to build value may include a potential
MainSpring starter pit, and the successful application of the Nuton
technology for leaching of primary sulphides. A Preliminary
Economic Assessment (“PEA”) will define the impact of those two
opportunities.
- A PEA inclusive of an inferred MainSpring mineral resource and
the application of the Nuton technologies to the primary sulphides
using the same PFS assumptions is underway with M3 Engineering as
lead consultant. The study is expected in the summer of 2024
- Continued metallurgical testing
- Infill drilling at MainSpring and around the Cactus West
Pit
- An updated PFS to include the MainSpring opportunity is
expected in 2H 2024
- A DFS is expected to begin post MainSpring PFS, for release in
1H 2025
- Nuton and ASCU have agreed to working towards the Integrated
Nuton PFS release by the end of 2024, unless extended mutually by
both parties.
- Nuton phase 2 metallurgy
- Infill drilling at MainSpring and Cactus West at depth and
southwest and west of the deposit
Links from the Press Release:
Webinar:
https://www.bigmarker.com/vid-conferences/ASCU-VID-THF
Figures and Tables:
https://arizonasonoran.com/projects/cactus-mine-project/press-release-images/
SEDAR+: https://www.sedarplus.ca
January 30, 2024:
https://arizonasonoran.com/news-releases/arizona-sonoran-announces-2024-work-plan/
October 16, 2023:
https://arizonasonoran.com/news-releases/arizona-sonoran-announces-updated-mineral-resource-estimate-for-the-cactus-project/
Cactus PEA, effective date of November 10, 2022:
https://arizonasonoran.com/site/assets/files/6218/2022-11-10_-_ps_cactus_mre_tech_report.pdf
Quality Assurance and Quality Control Procedures
Skyline Labs is accredited in accordance with the recognized
International Standard ISO/IEC 17025:2005. Their quality management
system has been certified as conforming to the requirements defined
in the International Standard ISO 9001:2015. The standard operating
procedure (SOP) used while processing the ASCU samples was to
process samples in groups of 20. Each tray consisted of 18 samples
with samples No. 1 and No. 10 repeated as duplicates. The results
from each tray were analyzed and any variance in the duplicates of
more than 3% would result in the entire tray being re-assayed.
The results of these analyses, including the QA/QC checks, were
transmitted to a select set of individuals at ASCU and the
qualified persons.
Qualified Persons
The authors of the Technical Report, each of whom is an
independent qualified person within the meaning of NI 43-101 are
listed below. The responsibilities of the engineering consultants
are as follows:
- Ausenco was commissioned by ASCU to manage and coordinate the
work related to the PFS and the technical report. Ausenco was also
retained to complete the infrastructure design, leach pad design,
and to compile the overall cost estimate and financial model.
- AGP and Call & Nicholas (CNI) were commissioned to provide
the mining methods for the underground and open pit. AGP provided
designs for view berms, waste piles, and the stockpile relocation.
Capital and operating costs were included in their scope.
- Samuel Engineering was commissioned to provide the mineral
processing and metallurgical testing basis and plant design.
Samuel’s scope included the metallurgical test work supervision and
analysis, SXEW plant, leaching process, conveyor systems, crushing
and stacking system designs. Capital and operating costs for these
areas were included as part of their scope.
- Clear Creek managed the drilling programs, hydrogeologic
evaluations and environmental field work for the study.
- ALS Geo Resources LLC was retained to provide drilling and
resource modelling components of the project.
- Minefill was involved in paste backfill evaluations and
trade-off studies. However, this process is not being utilized in
the current project scope.
The Qualified Person’s listed below for the technical report
have reviewed and verified the contents of this press release as it
relates to their responsibilities. By virtue of their education,
experience and professional association, they are considered
Qualified Person as defined by NI 43-101.
Technical aspects of this news release have been reviewed and
verified by Dan Johnson, ASCU Director of Projects, who is a
qualified person as defined by National Instrument 43-101.
Qualified Person
Professional Designation
Position
Employer
Erin L. Patterson
P.E.
Director of Minerals &
Metals
Ausenco Engineering USA South,
Inc.
Scott C. Elfen
P.E.
Global Lead Geotechnical
Services
Ausenco Engineering Canada
ULC.
R. Douglas Bartlett
RG, CHG,
Principal
Clear Creek Associates, a
subsidiary of Geo-Logic Associates
Gordon Zurowski
P.Eng.
Principal Mine Engineer
AGP Mining Consultants Inc.
Nat Burgio
FAusIMM (CP)
Principal Geologist
AGP Mining Consultants Inc.
Todd Carstensen
RM-SME
Principal Mine Engineer
AGP Mining Consultants Inc.
Allan L. Schappert
CPG, SME-RM
Principal
ALS Geo Resources LLC
James L. Sorensen
FAusIMM
Director
Samuel Engineering, Inc.
Paul F. Cicchini
P.E.
President
North Star Geotech LLC
About Arizona Sonoran Copper Company (www.arizonasonoran.com |
www.cactusmine.com)
ASCU’s objective is to become a mid-tier copper producer with
low operating costs and to develop the Cactus and Parks/Salyer
Projects that could generate robust returns for investors and
provide a long term sustainable and responsible operation for the
community and all stakeholders. The Company's principal asset is a
100% interest in the Cactus Project (former ASARCO, Sacaton mine)
which is situated on private land in an infrastructure-rich area of
Arizona. Contiguous to the Cactus Project is the Company’s
100%-owned Parks/Salyer deposit that could allow for a phased
expansion of the Cactus Mine once it becomes a producing asset. The
Company is led by an executive management team and Board which have
a long-standing track record of successful project delivery in
North America complemented by global capital markets expertise.
Non-IFRS Financial Performance Measures
This news release contains certain non-IFRS measures, including
sustaining capital, sustaining costs,
C1 cash costs and AISC. The Company believes that these
measures, together with measures determined in accordance with
IFRS, provide investors with an improved ability to evaluate the
underlying performance of the Company. Non-IFRS measures do not
have any standardized meaning prescribed under IFRS, and therefore
they may not be comparable to similar measures employed by other
companies. The data is intended to provide additional information
and should not be considered in isolation or as a substitute for
measures of performance prepared in accordance with IFRS.
Cautionary Statement Regarding Estimates of Mineral
Resources
This news release uses the terms measured, indicated and
inferred mineral resources as a relative measure of the level of
confidence in the resource estimate. Readers are cautioned that
mineral resources are not mineral reserves and that the economic
viability of resources that are not mineral
reserves has not been demonstrated. The mineral resource
estimate disclosed in this news release may be materially affected
by geology, environmental, permitting, legal, title,
socio-political, marketing or other relevant issues. The mineral
resource estimate is classified in accordance with the Canadian
disclosure requirements of Institute of Mining, Metallurgy and
Petroleum’s “CIM Definition Standards on Mineral Resources and
Mineral Reserves” incorporated by reference into NI 43-101. Under
NI 43-101, estimates of inferred mineral resources may not form the
basis of feasibility or pre-feasibility studies or economic studies
except for preliminary economic assessments. Readers are cautioned
not to assume that further work on the stated resources will lead
to mineral reserves that can be mined economically.
Forward-Looking Statements
This news release contains “forward-looking statements” and/or
“forward-looking information” (collectively, “forward-looking
statements”) within the meaning of applicable securities
legislation. All statements, other than statements of historical
fact, are forward-looking statements. Generally, forward-looking
statements can be identified by the use of forward-looking
terminology such as “plans”, “expect”, “is expected”, “in order
to”, “is focused on” (a future event), “estimates”, “intends”,
“anticipates”, “believes” or variations of such words and phrases
or statements that certain actions, events or results “may”,
“could”, “would”, or the negative connotation thereof. In
particular, statements regarding ASCU’s future operations, future
exploration and development activities or other development plans
constitute forward-looking statements. By their nature, statements
referring to mineral reserves or mineral resources constitute
forward-looking statements. Forward-looking statements in this news
release include, but are not limited to statements with respect to
the results (if any) of further exploration work to define and
expand or upgrade mineral resources and reserves at ASCU’s
properties; the anticipated exploration, drilling, development,
construction and other activities of ASCU and the result of such
activities; the mineral resources and mineral reserves estimates of
the Cactus Project (and the assumptions underlying such estimates);
the ability of exploration work (including drilling) to accurately
predict mineralization; the ability of management to understand the
geology and potential of the Cactus Project; the focus of the 2024
drilling program at the Cactus Project including the Parks/Salyer
deposit and MainSpring property; the ability to generate additional
drill targets; the ability of ASCU to complete its exploration
objectives in 2024 in the timing contemplated (if at all); the
completion and timing for the filing of the Technical Report; the
timing and ability of ASCU to produce a preliminary economic
assessment (including the MainSpring property) (if at all); the
timing and ability of ASCU to produce the Nuton Case PFS (if at
all); the scope of any future technical reports and studies
conducted by ASCU; the ability to realize upon mineralization in a
manner that is economic; the impact of bringing the MainSpring
property into the mine plan; the ability and timing of ASCU to
commence operations (if at all); the robust economics and
opportunity represented by the Cactus Project; the ability of
ASCU’s operations to be among the top 10 copper operations in
Arizona and the US (if at all); the impact of the NutonTM
technologies on ASCU operations and cost relating to same; the
impact of the relationship with Nuton on ASCU and its operations
and any other information herein that is not a historical fact.
ASCU considers its assumptions to be reasonable based on
information currently available but cautions the reader that their
assumptions regarding future events, many of which are beyond the
control of the Company, may ultimately prove to be incorrect since
they are subject to risks and uncertainties that affect ASCU, its
properties and business. Such risks and uncertainties include, but
not limited to, the global economic climate, developments in world
commodity markets, changes in commodity prices (particularly prices
of copper), risks relating to fluctuations in the Canadian dollar
and other currencies relative to the US dollar, risks relating to
capital market conditions and ASCU’s ability to access capital on
terms acceptable to ASCU for the contemplated exploration and
development at the Company’s properties, changes in exploration,
development or mining plans due to exploration results and changing
budget priorities of ASCU or its joint venture partners, the
effects of competition in the markets in which ASCU operates,
results of further exploration work, the ability to continue
exploration and development at ASCU’s properties, the ability to
successfully apply the NutonTM technologies in ASCU’s properties,
the impact of the NutonTM technologies on ASCU operations and cost
relating to same, the timing and ability for ASCU to prepare and
complete the Nuton Case PFS and the costs relating to same, errors
in geological modelling, changes in any of the assumptions
underlying the PFS, the ability to expand operations or complete
further exploration activities, the ability to obtain regulatory
approvals, the impact of changes in the laws and regulations
regulating mining exploration, development, closure, judicial or
regulatory judgments and legal proceedings, operational and
infrastructure risks and the additional risks described in ASCU’s
most recently filed Annual Information Form, annual and interim
management’s discussion and analysis, copies of which are available
on SEDAR+ (www.sedarplus.ca) under ASCU’s issuer profile. ASCU’s
anticipation of and success in managing the foregoing risks could
cause actual results to differ materially from what is anticipated
in such forward-looking statements.
Although management considers the assumptions contained in
forward-looking statements to be reasonable based on information
currently available to it based on information available at the
date of preparation, those assumptions may prove to be incorrect.
There can be no assurance that these forward-looking statements
will prove to be accurate, as actual results and future events
could differ materially from those anticipated in such statements.
Accordingly, readers should not place undue reliance on
forward-looking statements and are urged to carefully consider the
foregoing factors as well as other uncertainties and risks outlined
in ASCU’s public disclosure record.
ASCU disclaims any obligation to update any forward-looking
statements, whether as a result of new information, future events
or results or otherwise, except as required by law.
View source
version on businesswire.com: https://www.businesswire.com/news/home/20240221970177/en/
For more information Alison Dwoskin, Director, Investor
Relations 647-233-4348 adwoskin@arizonasonoran.com George Ogilvie,
President, CEO and Director 416-723-0458
gogilvie@arizonasonoran.com
Arizona Sonoran Copper (TSX:ASCU)
Gráfico Histórico do Ativo
De Dez 2024 até Jan 2025
Arizona Sonoran Copper (TSX:ASCU)
Gráfico Histórico do Ativo
De Jan 2024 até Jan 2025