Gold Bull Resources Corp. (TSX-V: GBRC) (“
Gold
Bull” or the “
Company”) is pleased to
report completion of its Sandman Preliminary Economic Assessment
(PEA or Scoping) Phase 2 Study at its 100% owned Sandman Project
(“
Sandman” or the “
Project”)
located in Humboldt County, Nevada, USA.
The Sandman Scoping Phase 2 Study has identified
a stand-alone, low pre-production capital USD29M, conventional heap
leach gold project producing circa 35,000 to 40,000 ounces of gold
per year for 9 years. The project boasts an excellent Internal Rate
of Return (IRR) at 101% and a pre-tax payback period of 1.1 years,
using a conservative gold price of US$1800.
The Scoping Phase 2 Study focused on mining gold
mineralized material within optimized pit shells in two phases:
Phase 1 mines all mineralized material within the
pit shell above the water table (Phase 1 Study previously announced
September 12, 2022 titled “Gold Bull’s Sandman Project Scoping
Study points to near-term production potential”), with report filed
on October 27, 2022, and this Phase 2 study
focused on mineralized material below the water table and within
the pit shell, after completion of additional monitoring,
permitting and dewatering efforts paid by mine cashflow, thereby
reducing initial capital and completed during the above water table
mining process. The benefit of this two-phase approach, is enabling
sufficient time and mine sourced funding to continue to close out
existing mineral resources, discover additional gold resources, and
enable sufficient time to conduct the below water table mine
studies and permitting, all paid from Sandman Project mine
revenues. The model is organic growth and non-shareholder
dilutive.
The Study highlights
include:
- Production rate average of
2.2 Mtpa for a 9-year
operation
- 35,000-40,000
ounces of gold per annum produced from conventional
heap leach
- At US$1,800/oz gold
price:
- IRR of 101%
(pre-tax)
- NPV
6% US$145 M (pre-tax)
- Payback period of 1.1
years (pre-tax)
- Average grade 0.73g/t
gold
- LOM low strip ratio of
2.2:1
- Phase 1 Initial
pre-production Capital $29M and Phase 2 Capital US$20M
paid by Phase 1 mining revenues. Total LOM capital US$49.2M,
including working capital US$4.5M
- LOM Operating cost of
US$17.22 per tonne
- All in Sustaining
Cost (AISC) of US$1,204/oz of gold
This Scoping Phase 2 Study focused on the
efficient extraction of all mineralized material within an
optimized pit shell in a sequence that facilitates effective use of
initial pre-production capital and a more rapid mine commissioning.
This Scoping Phase 2 Study will be a preliminary economic
assessment, under NI 43-101 requirements, and will be filed on
SEDAR within 45 days.
Gold Bull CEO, Cherie Leeden commented:
Sandman
provides Gold Bull with a low-cost and moderate mine life start-up
opportunity. In our Phase 1 PEA we only examined the oxide gold
located above the water table, to enable a rapid timeline for mine
commissioning and limited the initial pre-production capital. This
Phase 2 scoping study focussed on extending the mine life from 5
years to 9 years while utilizing mine cashflow for Phase 2
development. The intent is to be mining, developing, and
discovering additional ounces at the project utilizing mining
cashflow. Excellent exploration potential exists at
Sandman.
The known gold
resources at Sandman remain open, therefore this PEA is the most
conservative base case done using only our pit constrained ounces
at a gold price of US$1800. If we were to use today's gold price of
circa $2000, it pushes our NPV from US$145M to US$189M, and our IRR
from 101% to 123%. Sandman is most sensitive to the gold
price.
Table 1. Pre-tax economic analysis summary
comparing the conservative $1,800 gold price utilized in this study
compared with the current gold price of circa $2,000.
STUDY HIGHLIGHTS
The Sandman Scoping Phase 2 Study was prepared
by Jerod Eastman, President of DJ 6E Consulting LLC, an independent
third-party consultant. The Study has demonstrated potentially
strong financial metrics for the Sandman Project based on a
proposed stand-alone low-cost start-up heap leach gold mine project
located approximately 25 km from the mining town of Winnemucca
(Figure 1 and 2) in central Northern Nevada, USA. Mr. Eastman was
also the author of the Company’s “Preliminary Economic Assessment
(Scoping Study), NI 43-101 Technical Report” for the Project with
an effective date of September 12, 2022 and filed on SEDAR on
October 27, 2022.
This Phase 2 Study investigated an expansion to
the previously announced Phase 1 five-year mine
plan of above water table mineralized material processed onsite via
conventional Heap Leach processing AND includes a Phase
2 plan to mine the mineralized material below the water
table after Phase 1 is finalized, and the necessary permitting and
dewatering efforts have been completed. Gold Bull considers Sandman
to be technically low risk, given the low strip ratio and
significant historical database that the Scoping Studies have been
based on. Both Scoping Studies were completed to an overall +/- 30%
accuracy summarized in Table 2 using key parameters and mine
factors set out in Table 3.
The figures in this Phase 2 Study focus on the
full project (prior Phase 1 plus this
Phase 2) mining scenario. The Phase 1 mine
scenario targeted low Initial pre-production capital and near-term
cash flow to then later fund below water table oxide mine studies
and development while producing revenue from the asset. The
deferred work includes below water table permitting, studies for
efficient product processing and additional resource drilling.
The Sandman Project Phase 2 Scoping Study
includes Life of Mine (LOM) and reports a pre-tax IRR of
101%,
NPV6% of
US$145M, annual cashflow of estimated
US$26Mpa, and a payback period of 1.1
years when applying a gold price of US$1,800/oz of
gold. The initial pre-production capital cost is
US$29M, which includes working capital of
US$4.5M, and a further US$20.2M
will be required as sustaining capital for additional mine studies,
dewatering, and leach pad expansions. Total operating cost is
$17.22 per tonne and all in sustaining cost of
$1,204/oz gold. Royalty is low at 1.2% of
product.
The Project is based on 455,000 gold
ounces contained within the put shells, with a
head grade of 0.73 g/t gold spread across four
known gold deposits. The four (4) gold resources (see Figure 3:
North Hill, Silica Ridge, Southeast Pediment, Abel Knoll) shall be
mined via conventional open pit mining methods, with an average
life of mine waste to ore ratio of 2.2:1, annual
production is 35-40K oz gold, with 2.2Mt
feed production rate. Refer Table 2 for further details
and estimated financial metrics.
Table 2. Scoping Study economic analysis summary
of Sandman Project for Phase 1 and Phase 2 Combined Studies
Please note, it was assumed in this Cash Flow
Model that Year 1 would follow the normal (reverse) S-curve for
costs and performance. As such, there is an assumed ramp-up period
for gold recovery, and operating costs are assumed to be higher in
Year 1 during this ramp-up to steady state.
Figure 1. Sandman Project location map of Northern Nevada
relative to the surrounding operating gold mines and mineral
resources. Reference to the nearby projects is for information
purposes only, and there are no assurances the Company will achieve
the same results.
Figure 2. Sandman Project location relative to
infrastructure and nearby regional mine servicing town of
Winnemucca. The project is located on Jungo Road 20-30 kms from
Winnemucca.
Figure 3. Sandman Scoping Study proposed mine
design. This has not changed from the Phase 1 study.
EXECUTIVE SUMMARY
The Sandman Project presents strong financial
results and a compelling mine opportunity for a stand-alone open
pit gold mine, with Phase 1 mining above water
table commencing at the North Hill deposit, followed by Silica
Ridge, Southeast Pediment and Abel Knoll deposits. Upon completion
of Phase 1, and the required below water table permitting and
dewatering efforts, Phase 2 mining is expected to
commence immediately in the same order as Phase 1
commencing at North Hill and heading southwards. The two-phase
approach conserves initial pre-production capital while enabling
rapid mine commissioning to achieve cashflow to then fund the below
water table permit and further exploration to increase the mine
resources.
The mine proposal includes onsite single-stage
crushing, which will move progressively from each pit location,
with separate dumps and two localized leach pads. The first leach
pad will be constructed for North Hill and Silica Ridge, and the
second leach pad will be constructed in year 3 and will receive
mineralized material feed from Southeast Pediment and Abel Knoll.
Leach Pad expansions will be required in years 5 and 6 to
accommodate the additional tonnage from Phase 2
mining.
Economics are based upon contract mining,
crushing and heap leach as the main processing method. It is
planned to load the gold onto activated carbon and then transport
the loaded carbon to off-site stripping and refining plants for
final gold doré recovery. A simplified mining schedule is
anticipated to produce 35,000-40,000 ounces of gold per annum.
Given the North Hill and Silica Ridge deposits
outcrop at surface, these deposits present the best strip ratio
starter pit mine scenarios. Phase 1 is targeting these low-strip
ratio resources to enable rapid permitting (above water table) for
mine start-up and initial cash flow. Initial mine production
revenue will be used to fund further mine studies, permitting and
dewatering efforts to allow the Phase 2 mining
below the water table and this is expected be included in future
feasibility studies.
Table 3. Sandman Project Scoping Study mine
factors applied to the economic evaluation
Comments
- This scenario includes all material
within an optimized pit shell
- Recoveries assumed at 70% for
oxide/transitional material heap leaching based on historic studies
by Newmont and others. Opportunity exists to further
optimize/increase recoveries and further metallurgical confirmation
test work is needed
- Optimized pit shells were applied,
not a refined pit design
- Future opportunity exists to
increase mine production, as this schedule assumes dayshift-only
mining to meet the planned material movement requirements
- Revenue from silver production is
included in this model where analysis exists within the resource
model, however, is too limited to classify the silver grade/tonnage
estimates and recovery due to a lack of consistent silver assay
data in historical drill analysis
- Cashflow model includes a 1.2%
Royalty
Capital Categories
- Contingency of 30% added to all
capital to cover unknown/ unrecognized categories
- Working capital is sufficient to
cover 2 months of operating costs
- All Capital estimates are based on
previous projects (within the past two years) and inflated to 2023
levels
- Engineering Procurement
Construction Management (EPCM)
- Earthworks – roads, stockpiles and
yard construction
- Crushing/stacking equipment, single
stage crushing for 6-8Kt per day, cost estimate includes
installation and commissioning, entire system to be mobile and
follow mining from pit to pit
- Leach pad and ponds, 5-8Kt per day,
cost estimate includes installation and commissioning. Initial pad
built near North Hill and Silica Ridge with a second pad built near
Southeast Pediment and Abel Knoll in year 3.
- Carbon columns, cost estimate
includes installation and commissioning. One set of columns for the
initial leach pad and second set to be constructed for the second
leach pad
- Sustaining capital includes
temporary construction facilities, construction services, supplies,
quality control, survey support, construction equipment and
safety
- Sample preparation conducted on
site with off site gold analysis
- Infrastructure includes portable
office, warehouse/parts storage, and a workshop
- Initial purchase or lease of water
rights necessary to operate the mine
- Option to purchase additional
surface rights included
Operational Categories
- Mining contractor mobilisation for
12-15 equipment units, office space and other resources.
- Contract mining comprises
- Drilling
- Blasting
- In-pit loading
- Waste haulage to near-pit waste
rock stockpile
- Product feed haulage to near-pit
stockpile location (for feed to crusher)
- Loader feed into a portable
(movable) crusher
- Loading of crushed material into
trucks
- Truck haulage to heap leach
pad
- Roads/dumps/stockpile
maintenance
- Company shall maintain small
workforce for project management, administration, SHE
permitting-training-compliance, general labor, crushing/heap leach
operations, supply chain etc.
- Contractor demobilization at the
end of the project life
- Centralised location for diesel,
gasoline, lubes, and oils
- Power Generation and Distribution
with mobile generators for crushing, pumping and other
infrastructure requirements, includes a back-up generator, power
poles, transformers for on-site distribution
- Further studies for alternative
power solutions are needed as this scenario uses diesel
generators
- Water supply and distribution,
water well construction and extraction, pumping and piping to
supply water for the project. Water usage 3,900 gallons per minute
with make-up water consumption rate of 285 gallons per minute
- Additional environmental and
hydrogeological baseline studies are required
- Initial purchase or lease of water
rights necessary to operate the mine
- Indirect owners’ costs include
temporary construction facilities, construction services, supplies,
quality control, survey support, construction equipment, safety
etc.
Operating CostsAn operating cost estimate has
been calculated at US$17.22 per tonne of mineralized material mined
and processed for the Project. The estimate relates to all costs to
allow production of gold doré, capturing the processing plant
facilities, contractor mining, product refining and general and
administration (G&A) costs.
Functional Area |
Cost per Tonne
Processed (US$) |
Mining |
$7.80 |
Processing |
$5.52 |
G&A |
$2.58 |
Other |
$1.32 |
Total Site
Operating
Cost1 |
$17.22 |
Table 4. Sandman Project operating cost
Basis for Economic calculations
(tonnage/grades)The Company announced its Mineral Resource Estimate
on February 2, 2021 with combined Indicated and Inferred ounces
totaling 494K ounces of gold and summarized below. Refer to Table 8
for the prior 2021 published summary of the Sandman Mineral
Resource Estimate.
- Indicated Resource of 18,550kt @ 0.73g/t gold for 433kozs of
gold
- Inferred Resource of 3,246kt @ 0.58g/t gold for 61kozs of
gold
The Scoping Studies are preliminary in
nature, includes inferred mineral resources that are considered too
speculative geologically to have the economic considerations
applied to them that would enable them to be categorized as mineral
reserves, and there is no certainty that the Scoping Studies will
be realized.
A further grade model was created for the Phase
2 Scoping Study to include the 2021 and 2022 drill results and
estimate an above water table tonnage and grade model. This was
applied to the Scoping Phase 2 Study pit optimization work and the
resulting tonnes and grade used in the Phase 2 Study are summarised
in Table 5. The water table surface was conservatively defined by
first intercept of water in the exploration drill holes. Detailed
hydrogeological studies accurately defining the water table are yet
to be conducted.
Table 5. Scoping Study tonnes and grade depicting
455K oz contained gold within the pit optimisation.
Mining MethodsThe Sandman Project is planned to
be mined using conventional open pit mining methods on the four (4)
separate deposits and the nine (9) year mine schedule is summarized
in Table 6. The mining operation schedule is dayshift only with a
roster of two production crews on a 4-days on and 4-days off, 12
hours per day.
Pre-production stripping is expected to be
minimal as mineralized material is located at or near surface where
mining is anticipated to begin at the North Hill and Silica Ridge
deposits. The pit areas have small shrubs and grasses that can be
cleared with planned mining equipment.
Open pit mining is currently envisaged to be by
diesel-powered equipment, utilizing a combination of one rotary
blasthole rig drilling blastholes, one 8m3 front-end loader (or
similar size excavator), and five to six, 70-tonne capacity trucks
to handle mineralized material and waste. The mining fleet has
sufficient capacity to move up to approximately 6.0Mtpa of total
material on a dayshift-only schedule. Support equipment comprising
a grader, track dozer(s) and water truck will aid in the mining.
Mineralized material will be hauled to the crushing area for
stockpiling before being rehandled later for primary crushing.
Initially, waste rock will be stored in the waste rock dumps close
to the pit to reduce haulage costs. As space and design allows,
waste will be backfilled into the pit to reduce haulage costs and
surface disturbance.
Haul roads are contemplated to be 9-10m widths
for one-way traffic and 18-20m widths for two-way traffic. The
final location of the ramps are expected to be optimized to reduce
the overall pit slopes and to aid in efficient haulage to various
stockpile locations. The pit is considered dry in Phase 1 and wet
in Phase 2.
The mine plan was designed to deliver ~2.2Mt of
mineralized material per year to the processing facility. The mine
plan was based on efficient extraction of mineralized material
above the water table in Phase 1 and started at the North Hill
deposit (predicted higher-grade and low strip ratio) and then
working the deposits in a southerly direction without regard to
Indicated and Inferred Mineral Resource categories. Phase 2 mining
will continue below the water table also starting at North Hill and
working in a southerly direction.
The total estimated mining workforce is 45-50
people, comprising a team of 15 Gold Bull personnel and 30-35
mining contractors (20 production operators, 8 maintenance techs, 5
supervisory staff).
Period |
MineralizedMaterial |
GoldGrade |
ContainedGold |
TotalWaste |
TotalMaterial |
StripRatio |
|
tonnes |
g/t |
ounces |
tonnes |
tonnes |
w:o |
Year 1 |
1,633,000 |
0.82 |
42,857 |
3,120,000 |
4,753,000 |
1.9 |
Year 2 |
2,306,000 |
0.77 |
57,143 |
3,833,000 |
6,139,000 |
1.7 |
Year 3 |
2,685,000 |
0.66 |
57,143 |
2,799,000 |
5,484,000 |
1.0 |
Year 4 |
2,247,000 |
0.79 |
57,143 |
3,077,000 |
5,324,000 |
1.4 |
Year 5 |
2,844,000 |
0.57 |
51,714 |
5,371,000 |
8,215,000 |
1.9 |
Year 6 |
3,195,000 |
0.56 |
57,143 |
7,564,000 |
10,759,000 |
2.4 |
Year 7 |
2,042,000 |
0.87 |
57,143 |
7,678,000 |
9,720,000 |
3.8 |
Year 8 |
1,887,000 |
0.94 |
57,143 |
6,608,000 |
8,495,000 |
3.5 |
Year 9 |
580,000 |
0.94 |
17,571 |
2,031,000 |
2,611,000 |
3.5 |
Totals |
19,419,000 |
0.73 |
455,000 |
42,081,000 |
61,500,000 |
2.2 |
Table 6. Sandman Project annual mining production
schedule for 9 years for the four Sandman deposits.
Mineral Processing and Recovery MethodsPrecious
metal recovery from this Scoping Phase 2 Study is through
conventional heap leaching and adsorption, desorption, regeneration
(ADR) technology for metal extraction from crushed product using
industry standard equipment. Processing will involve mineralized
material passing through a single stage of crushing, which will
allow for haulage transport and end-dump stacking of the
mineralized material onto a heap leach pad. The processing
facilities accommodate a leachable tonnage of approximately 19.4Mt
of product at a gold grade of 0.73g/t and a process rate of
5,900tpd or 2.2Mtpa. The heap leach pad facilities have been
located and designed with expandability for a LOM production
increase.
Mineralized material will be delivered to the
heap leach pad from the open pit and placed in the stockpile
adjacent to the crushing plant. The mineralized material will be
fed to the crushing plant using a front-end loader and will be
crushed and then transported to the heap leach pad via haul trucks.
The mineralized material will be stacked onto the heap using
industry standard end-dumping and dozer pushing and then leached
with a weak cyanide solution to extract the precious metal values.
The gold will then be recovered from the pregnant solution in the
carbon columns by adsorbing the dissolved gold onto activated
carbon, which will be bagged and transported off-site to an
external facility to extract gold from the loaded carbon. The
stripped carbon will be returned from the external treatment
facility to site for continuous reuse in the process plant. The
doré will be sent to a contract refiner for final refining.
Sensitivity AnalysisHigh level sensitivity
analysis of the Sandman Project economics was conducted, indicating
the project is most sensitive towards gold price and less sensitive
towards operating cost and least sensitive to capital cost. Figure
5 and Table 7 demonstrate the range of NPV in million dollars over
a range of gold prices.
Figure 4. Sandman sensitivity analysis evaluating
gold price, capital costs and operating costs
Figure 5. Sandman sensitivity analysis is most
sensitive to the gold price
Table 7. Gold price impact on NPV 6% and IRR.
Table 8. January 2021 NI 43-101 Sandman Gold
Resource Estimate. Full report available:
Sandman-NI-43-101_2021-01-20.pdf (goldbull.ca) Please note that the
Sandman 2021 NI 43-101 Resource Estimate does not include drilling
conducted by Gold Bull in 2021 and 2022.
NEXT STEPS
Further metallurgical, geotechnical and
hydrogeological studies are required for inclusion in a Feasibility
Study and for use in mine permitting.
Baseline hydrogeological, cultural, and
biological surveys have previously been conducted at Sandman,
however, may need to be updated for mine permitting. Additional
technical and design optimization studies will also be required for
Inclusion In the Feasibility Study. Infill resource and reserve
drilling is required ahead of the mine schedule.
Optional additional exploration is warranted and
recommended to expand the current resource base.
CAUTIONARY STATEMENT
This Scoping Studies are preliminary technical
and economic studies investigating the potential viability of
commissioning and running a gold mine at the Sandman Project. The
Scoping Studies includes inferred mineral resources that are
considered too speculative geologically to have the economic
considerations applied to them that would enable them to be
categorized as mineral reserves, and there is no certainty that the
Scoping Studies will be realized.
The Scoping Studies in this announcement is
based on technical mine factors and economic assumptions and
assessments which could be further refined and evaluated in a
feasibility study. If the Company were to attempt to bring the
Sandman Project into production without established mineral
reserves on the project supported by a full feasibility study, the
Company cautions that this could result in a higher risk of
economic or technical failure of the operation than if a full
feasibility study had been prepared demonstrating economic and
technical viability.
The Scoping Studies are based on material
assumptions outlined in this announcement. These include
assumptions about the availability of funding and other parameters.
While the Company considers all the material assumptions are based
on reasonable grounds, there is no certainty they will prove to be
correct or that the range of outcomes indicated in this Scoping
Study announcement can be achieved or realised. There are no
assurances that the Sandman Project will be found to be
economic.
To achieve the potential mine development
outcomes indicated in the Phase 1 and Phase 2 Scoping Study,
significant funding is required as well as further metallurgical,
hydrogeological, and environmental assessments and permits received
prior to confirming mining can take place. The Study has focussed
only on Phase 1 initial oxide mining of mineralized material above
the water table, then Phase 2 mining of material below the water
table, using conventional heap leach processing. Investors should
note there is no certainty that the Company will be able to raise
the required funding when needed, however the Company has concluded
that it has a reasonable basis for providing the forward-looking
statements included in this announcement and believes that it has a
“reasonable basis” to expect it will be able to fund the gold
development project upon receiving satisfactory and favourable
results for further metallurgical, hydrogeological and
environmental studies and permits enabling economic ore extraction.
Further studies are required to confirm the proposed mine scenario
and confirm assumptions made in this Scoping Study.
It is also possible that such funding may only
be available on terms that may be dilutive, or otherwise affect the
value of the Company’s existing shares. It is also possible that
the Company could pursue other strategies to provide alternative
funding options including project finance. Given the uncertainties
involved for the metallurgical, hydrogeological and environmental
assessments and permits, investors should not make any investment
decision based solely on the results of the Scoping Studies and
assume a mine will be developed, however every effort will be made
by the Company to progress towards mine development.
ABOUT SANDMAN
In December 2020, Gold Bull purchased the
Sandman Project from Newmont. Gold mineralization was first
discovered at Sandman in 1987 by Kennecott and the project has been
intermittently explored since then. There are four known pit
constrained gold resources located within the Sandman Project,
consisting of 21.8Mt at 0.7g/t gold for 494,000 ounces of gold;
comprising of an Indicated Resource of 18,550kt at 0.73g/t gold for
433kozs of gold plus an Inferred Resource of 3,246kt at 0.58g/t
gold for 61kozs of gold. Several of the resources remain open in
multiple directions and the bulk of the historical drilling has
been conducted to a depth of less than 100m. Sandman is
conveniently located circa 25-30 km northwest of the mining town of
Winnemucca, Nevada.
QUALIFIED PERSON
The technical information in this news release
has been reviewed and approved by Mr. Jerod Eastman, a Qualified
Person under National Instrument 43-101. Mr. Eastman is a
Registered Member (#00885850) of the Society for Mining, Metallurgy
and Exploration, Inc. and is completely independent of Gold Bull
Resources Corp. The information in this news release that relates
to mining and cost estimation is based on, and fairly reflects,
information compiled by Mr. Eastman.
ABOUT GOLD BULL RESOURCES CORP.
Gold Bull’s mission is to grow into a US focused
mid-tier gold development Company via rapidly discovering,
developing and acquiring additional ounces. The Company’s
exploration hub is based in Nevada, USA, a top-tier mineral
district that contains significant historical production, existing
mining infrastructure and an established mining culture. Gold Bull
is led by a Board and Management team with a track record of
exploration and acquisition success.
Gold Bull’s core asset is the Sandman Project,
located in Nevada which has a 494,000 oz gold
resource as per 2021 43-101 Resource Estimate. Sandman is located
23 km south of the Sleeper Mine and boasts excellent large-scale
exploration potential.
Gold Bull is driven by its core values and
purpose which includes a commitment to safety, communication &
transparency, environmental responsibility, community, and
integrity.
Cherie LeedenPresident and CEO, Gold Bull Resources Corp.
For further information regarding Gold Bull
Resources Corp., please visit our website at www.goldbull.ca or
email admin@goldbull.ca or phone 778.401.8545.
Cautionary Note Regarding Forward-Looking
StatementsNeither the TSX Venture Exchange nor its
Regulation Services Provider (as that term is defined in the
policies of the TSX Venture Exchange) accepts responsibility for
the adequacy or accuracy of this release.
This news release contains certain statements
that may be deemed “forward-looking statements” with respect to the
Company within the meaning of applicable securities laws.
Forward-looking statements are statements that are not historical
facts and are generally, but not always, identified by the words
“expects”, “plans”, “anticipates”, “believes”, “intends”,
“estimates”, “projects”, “potential”, “indicates”, “opportunity”,
“possible” and similar expressions, or that events or conditions
“will”, “would”, “may”, “could” or “should” occur. Although Gold
Bull believes the expectations expressed in such forward-looking
statements are based on reasonable assumptions, such statements are
not guarantees of future performance, are subject to risks and
uncertainties, and actual results or realities may differ
materially from those in the forward-looking statements. Such
material risks and uncertainties include, but are not limited to,
the Company’s ability to raise sufficient capital to fund its
planned activities at the Sandman Project; the timing and costs of
future activities on the Company’s properties; maintaining its
mineral tenures and concessions in good standing, to explore and
develop its projects, to repay its debt and for general working
capital purposes; changes in economic conditions or financial
markets; the inherent hazards associates with mineral exploration
and mining operations, future prices of gold and other metals,
changes in general economic conditions, accuracy of mineral
resource and reserve estimates, the potential for new discoveries,
the ability of the Company to obtain the necessary permits and
consents required to explore, drill and develop the projects and if
obtained, to obtain such permits and consents in a timely fashion
relative to the Company’s plans and business objectives for the
projects; the general ability of the Company to monetize its
mineral resources; and changes in environmental and other laws or
regulations that could have an impact on the Company’s operations,
compliance with environmental laws and regulations, dependence on
key management personnel and general competition in the mining
industry. Forward-looking statements are based on the reasonable
beliefs, estimates and opinions of the Company’s management on the
date the statements are made. Except as required by law, the
Company undertakes no obligation to update these forward-looking
statements in the event that management’s beliefs, estimates or
opinions, or other factors, should change.
Photos accompanying this announcement are available at
https://www.globenewswire.com/NewsRoom/AttachmentNg/c3f4d80d-4129-404f-81e1-48bc70a771e7
https://www.globenewswire.com/NewsRoom/AttachmentNg/7810ce2f-1ec1-4137-ac8b-8882f1fa277b
https://www.globenewswire.com/NewsRoom/AttachmentNg/148f75fa-05c6-4387-bfc4-abd0ec16d3b6
https://www.globenewswire.com/NewsRoom/AttachmentNg/71a77c70-2988-40ac-b944-3ca5dd932838
https://www.globenewswire.com/NewsRoom/AttachmentNg/978d9d98-8d6f-428f-a0e0-c19cbdfc3d4c
https://www.globenewswire.com/NewsRoom/AttachmentNg/2586cf40-218f-4724-90b3-a94f73ce3f59
https://www.globenewswire.com/NewsRoom/AttachmentNg/fed89199-6d9f-4318-81b7-a7cd0e6b6976
https://www.globenewswire.com/NewsRoom/AttachmentNg/88d2934e-fd15-43cc-ac64-c5b3cd71a244
https://www.globenewswire.com/NewsRoom/AttachmentNg/398fbc43-4105-49bf-9ac2-974bacda835b
https://www.globenewswire.com/NewsRoom/AttachmentNg/85ad4863-aefd-45cc-a425-b22f4ce209b0
https://www.globenewswire.com/NewsRoom/AttachmentNg/5aae4e9b-2d26-4425-8d42-c5599d5e017d
Gold Bull Resources (TSXV:GBRC)
Gráfico Histórico do Ativo
De Nov 2024 até Dez 2024
Gold Bull Resources (TSXV:GBRC)
Gráfico Histórico do Ativo
De Dez 2023 até Dez 2024