Ascot Resources Ltd. (
TSX: AOT;
OTCQX: AOTVF) (“
Ascot” or the
“
Company”) is pleased to provide a construction
update on the Company’s Premier Gold Project
(“
PGP” or the “
Project”), located
on Nisga’a Nation Treaty Lands in the prolific Golden Triangle of
northwestern British Columbia. Project construction was 86%
complete as of December 31, 2023 (approximately 90% as of January
31, 2024) and is currently nearing completion, with first ore
delivery to the mill anticipated by the end of March 2024, and
first gold pour anticipated in April.
Derek White, President and CEO, commented, "With
Project construction nearing completion and early commissioning
underway, we eagerly anticipate progressing to the production and
operations phase at the Premier Gold Mine. The Project also
accomplished an impressive safety milestone having surpassed one
million hours without a lost time incident, along with another
quarterly reduction in total recordable incident frequency. We are
also proud to have recently closed an additional financing package
which we believe is sufficient for the Company to progress from
construction to first gold pour, ramp-up, commercial production and
steady-state operations. With the gold price still trading near
US$2,000 per ounce, this is an opportune time for us to become
Canada’s next gold producer.”
PROJECT CONSTRUCTION
Funding for Construction and
Ramp-UpOn February 20, 2024, the Company announced the
closing of its financing for a total of US$50 million from Sprott
Resource Streaming and Royalty Corp. and/or its affiliates
(“Sprott Streaming”) and Nebari Natural Resources
Credit Fund II, LP (“Nebari”), as further
described in the Company’s news release dated January 22, 2024.
Concurrently, the Company closed its previously announced bought
deal private placement financing with a syndicate of underwriters
co-led by BMO Capital Markets and Desjardins Capital Markets
(together, the “Joint Bookrunners”), and including
CIBC World Markets Inc., Raymond James Ltd. and Velocity Trade
Capital Ltd. (collectively, with the Joint Bookrunners, the
“Underwriters”). Under the bought deal financing,
the Company issued a total of 65,343,000 common shares of the
Company (the “Common Shares”) at a price of C$0.44
per Common Share, for gross proceeds of approximately C$29 million,
which included the full exercise of the Underwriters’ option.
Construction Progress Key Performance
Indicators (“KPI”)
At the end of Q4 2023, overall construction
excluding mine development was 86% complete (approximately 90% as
of January 31, 2024), compared with 66% complete at the end of Q3
2023. Numerous pre-commissioning activities in the mill have
commenced. The Company anticipates introducing first ore into the
mill by the end of March 2024, and pouring first gold in April.
Capital costs, including mining costs, incurred
as of December 31, 2023 were $292 million. As of December 31, 2023,
the remaining project construction capital required to complete
construction and achieve the first gold pour is approximately $47
million including mine development costs but excluding certain
pre-operating costs and working capital. This implies a total
project capital cost of $339 million, which is slightly higher than
the most recent total project budget of $334 million as reported
last quarter. The increase is mainly attributable to the increase
in duration of the earthworks and project indirect costs.
The Company ended December 2023 with a cash
balance of C$27 million. With the aforementioned additional
financing of US$50 million from Sprott Streaming and Nebari Credit
Fund II, and the equity financing with gross proceeds of C$29
million, the Company believes it is well financed to complete
construction of the Project, progress through the ramp-up phase to
commercial production and reach nameplate capacity at the Premier
Gold Mine.
SafetyThe Premier Gold Project
reached an important safety milestone in Q4 of 2023: one million
hours without lost time incidents (“LTI”). By the
end of Q4 2023, this figure reached 1,143,029 hours LTI free. The
total recordable incident frequency has been reduced yet again from
0.69 at the end of Q3 2023 to 0.52 by the end of Q4 2023. The
frequency of total incidents including property damage, first aid
injuries, and near misses, was relatively similar to Q3 2023.
Reporting activity continues to improve, and the Company will
continue to work on proactive safety training and measures to
reduce overall incidents on site, especially with pending
transition from construction to the operations phase.
Processing PlantIn Q3 2023,
mechanical and electrical work in the mill was substantially
advanced. In Q4 2023, work in the mill focused on piping, systems
& controls as well as remaining electrical terminations.
Piping installation included work inside the
mill building and also outside connections to the carbon-in-leach
(“CIL”) tanks, and cyanide destruction and
tailings thickener lines. Piping installation at the mill is over
90% complete. Electrical work progressed on completing terminations
and installation of the fire detection system. Instrumentation and
controls installations are advancing well. Staged commissioning has
started on the Ball and SAG mills, CIL circuit, and cyclone feed
pumps. As a part of the commissioning process, both Ball and SAG
mills have been energized and rotated. The Ball mill has been
loaded with water and successfully rotated for an 8-hour period
with no issues. The SAG mill has been rotated for several hours and
will undergo water load testing this week.
Tailings Storage Facility (“TSF”)
EarthworksWith the milder-than-average winter season so
far, much work was progressed on the TSF earthworks in Q4 2023 and
into early 2024. The South Dam, North Dam, and Southeast Dam have
been completed. The minor remaining work is focused on the smaller
East Dam and spillway which is expected to complete by
mid-March.
Currently the earthworks around the TSF are
substantially complete, with some minor works remaining anticipated
to be completed by late February.
Water Treatment Plant
(“WTP”)Commissioning of the WTP components started in Q4
2023, with most areas being commissioned in isolation. Upon the
delivery and installation of two transformers and a buffer tank in
December 2023, and the 138 kV power connection in January 2024, the
WTP is currently undergoing final commissioning. Normal operation
of the WTP is anticipated this month. As of the writing of this
release, Ascot can report that the High-Density Sludge
(“HDS”) plant has been successfully commissioned
and is awaiting final test results on the effluent water before
discharge into the environment is authorized. The Moving Bed
Bio-Reactor (“MBBR”) is mechanically and
electrically complete and media is being loaded into the tanks. The
plant will be brought into service mid-March in time for mill
start-up.
Site InfrastructureDuring Q3
2023, most of the new electrical substation was mechanically
completed, and crews completed the 138kV power line to connect to
the power grid less than 500 metres away. In Q4 2023, all 138kV
lines were pulled and linked up with the BC Hydro grid. Site
electrification was originally planned for mid-December, but three
new switches were required. Once these were delivered in early
January 2024, site powerup on the 138 kV line was completed on
January 14, 2024.
Off-Site InfrastructureOn
October 3, 2023, the town council of Stewart, B.C. approved a
Temporary Use Permit (“TUP”) to install a camp
facility in the town to provide additional accommodations for
workers at the Project. The TUP is for a three-year term with
potential to renew for another three years afterwards. The Company
quickly mobilized and installed living quarters with an initial
capacity of 76 beds in early December. This has alleviated some of
the pressure caused by the extended earthworks schedule.
On September 19, 2023, the Company acquired a
full-service laboratory facility (“Assay Lab”) in
Stewart, BC from Seacan Labs Corp. The Assay Lab will be used to
perform the testing required by Ascot for mineral exploration,
mining operation, and environmental monitoring. During Q4 2023, the
Assay Lab was re-commissioned for use and is currently ramping up
toward full capacity of 250-300 samples per day with a 24-hour
turnaround.
Mine DevelopmentIn Q3 2023, the
Company’s underground mining contractor Procon began their initial
mobilization to site and deployed senior project management
personnel to coordinate storage and laydown areas ahead of
operating crew mobilization.
In Q4 2023, once the Big Missouri Portal
infrastructure and mine services were re-established, underground
development was re-commenced. Procon advanced underground waste and
ore development including the decline, which will eventually
connect to the Silver Coin deposit. In advance of mill start-up in
Q1 2024, Ascot is stockpiling mineralized material from Big
Missouri in the Diego pit, ready for processing. Underground
development rates at Big Missouri have been gradually improving,
with linear advances as high as 16 metres per day achieved, and on
average crews are achieving approximately 10 to 12 metres per day
currently. Including development in 2022, total underground
development at Big Missouri totaled 1,300 metres as of Q4 2023, and
approximately 1,650 metres by February 15, 2024.
Recently in ore drive 6 at Big Missouri, the
geology team noted an occurrence of coarse, visible gold in a
quartz vein (see Figure 1 below). This material was within a
geological wireframe approximately on dip with an existing stope
shape about 20 metres away. In conjunction with exploration
drilling intercepting high-grade gold mineralization outside of
existing stope shapes in 2023, this occurrence provides further
evidence of the potential for expansion beyond the current mine
plan.
In August 2023, surface work commenced on the
new Premier Portal close to the mill. In Q4 2023, Procon continued
the portal face preparations including holes for cable bolts and
other ground support and began clearing a pad area for service
infrastructure including gensets and compressors. The underground
decline development started in early December with initial rounds
and placement of shotcrete arches similar to what was done at Big
Missouri in 2022. Poor ground near surface and extreme cold
temperatures slowed advance in January 2024, but conditions have
improved in February. Mining development will be advanced down into
the Premier deposit for initial mining in the Prew Zone, with ore
development anticipated to begin in Q2 2024, and stope production
following in Q3 2024. The ramp has been strategically laid out to
allow for underground drilling on the Sebakwe Zone in 2024 and will
eventually connect a footwall ramp over to the 602 area at the
southern end of the Premier deposit.
RecruitmentRecruitment efforts
and activity materially increased in the past quarter, as Ascot
continues to have many qualified candidates applying for open
positions. In January 2024, Ascot representatives attended a
recruitment fair in Campbell River, BC, after it was announced that
the nearby Myra Falls underground mine and mill was being placed on
care & maintenance. During the job fair Ascot conducted two
hundred in person and virtual interviews, and the Company has since
been able to fill many open positions for skilled trades and
operators.
Key senior level roles filled during Q4 2023 and
recently include Operations Manager, a second Mine Superintendent,
a Senior Mining Engineer, Maintenance Superintendent, Maintenance
General Foreman, Mill Operations General Foreman and a number of
Supervisors.
PROJECT PHOTOS
Figure 1 – Visible gold in quartz vein
found in ore drive 6 at Big Missouri
A photo accompanying this announcement is available at
https://www.globenewswire.com/NewsRoom/AttachmentNg/0f95859f-74a5-4636-bb6b-8aa32858447e
Figure 2 – TSF overview looking
south
A photo accompanying this announcement is available at
https://www.globenewswire.com/NewsRoom/AttachmentNg/baa9433f-711f-4d0e-8803-7fc62c4b08c2
Figure 3 – TSF South and Southeast dams
complete
A photo accompanying this announcement is available at
https://www.globenewswire.com/NewsRoom/AttachmentNg/fd6b8cbc-3caa-40f8-b3e0-aefbc5db4642
Figure 4 – WTP
commissioning
A photo accompanying this announcement is available at
https://www.globenewswire.com/NewsRoom/AttachmentNg/820ab280-80f4-4d0c-ae13-a222266c20e7
Figure 5 – WTP MBBR system
A photo accompanying this announcement is available at
https://www.globenewswire.com/NewsRoom/AttachmentNg/370cc686-75a0-494e-b01d-ee718a85d15f
Figure 6 – Mill piping over 90%
complete
A photo accompanying this announcement is available at
https://www.globenewswire.com/NewsRoom/AttachmentNg/5825c50d-248d-40ab-9fd8-1c4f48506532
Figure 7 – Premier underground portal
overhead
A photo accompanying this announcement is available at
https://www.globenewswire.com/NewsRoom/AttachmentNg/7eef4fa5-4824-4305-ad3a-afefbafd20cc
Figure 8 – Premier underground portal
front view
A photo accompanying this announcement is available at
https://www.globenewswire.com/NewsRoom/AttachmentNg/d1458d74-ec5d-4a40-b7fa-212e4d300137
Figure 9 – Mill area
overview
A photo accompanying this announcement is available at
https://www.globenewswire.com/NewsRoom/AttachmentNg/d8216177-8e47-43da-8cf9-7003210ecbd4
Qualified Person
John Kiernan, P.Eng., Chief Operating Officer of
the Company is the Company’s Qualified Person (QP) as defined by
National Instrument 43-101 and has reviewed and approved the
technical contents of this news release.
On behalf of the Board of Directors of
Ascot Resources Ltd.“Derek C. White”President &
CEO
For further information
contact:
David Stewart, P.Eng. VP, Corporate Development &
Shareholder
Communications dstewart@ascotgold.com 778-725-1060 ext.
1024
About Ascot Resources Ltd.
Ascot is a Canadian junior exploration and
development company focused on re-starting the past producing
Premier Gold Mine, located on Nisga’a Nation Treaty Lands, in
British Columbia’s prolific Golden Triangle. Ascot shares trade on
the TSX under the ticker AOT. Concurrent with progressing the
development of Premier, the Company continues to explore its
properties for additional high-grade underground resources. Ascot
is committed to the safe and responsible development of Premier in
collaboration with Nisga’a Nation as outlined in the Benefits
Agreement.
For more information about the Company, please
refer to the Company’s profile on SEDAR+ at www.sedar.ca or visit
the Company’s web site at www.ascotgold.com, or for a virtual tour
visit www.vrify.com under Ascot Resources.
The TSX has not reviewed and does not accept
responsibility for the adequacy or accuracy of this release.
Cautionary Statement Regarding
Forward-Looking Information
All statements and other information contained
in this press release about anticipated future events may
constitute forward-looking information under Canadian securities
laws ("forward-looking statements").
Forward-looking statements are often, but not always, identified by
the use of words such as "seek", "anticipate", "believe", "plan",
"estimate", "expect", "targeted", "outlook", "on track" and
"intend" and statements that an event or result "may", "will",
"should", "could", “would” or "might" occur or be achieved and
other similar expressions. All statements, other than statements of
historical fact, included herein are forward-looking statements,
including statements in respect of advancement and development of
the PGP and the timing related thereto, the completion of the PGP
mine, the production of gold and management’s outlook for the
remainder of 2024 and beyond. These statements involve known and
unknown risks, uncertainties and other factors that may cause
actual results or events to differ materially from those
anticipated in such forward-looking statements, including risks
associated with entering into definitive agreements for the
transactions described herein; fulfilling the conditions to closing
of the transactions described herein, including the receipt of TSX
approvals; the business of Ascot; risks related to exploration and
potential development of Ascot's projects; business and economic
conditions in the mining industry generally; fluctuations in
commodity prices and currency exchange rates; uncertainties
relating to interpretation of drill results and the geology,
continuity and grade of mineral deposits; the need for cooperation
of government agencies and indigenous groups in the exploration and
development of Ascot’s properties and the issuance of required
permits; the need to obtain additional financing to develop
properties and uncertainty as to the availability and terms of
future financing; the possibility of delay in exploration or
development programs and uncertainty of meeting anticipated program
milestones; uncertainty as to timely availability of permits and
other governmental approvals; and other risk factors as detailed
from time to time in Ascot's filings with Canadian securities
regulators, available on Ascot's profile on SEDAR+ at
www.sedarplus.ca including the Annual Information Form of the
Company dated March 23, 2023 in the section entitled "Risk
Factors". Forward-looking statements are based on assumptions made
with regard to: the estimated costs associated with construction of
the Project; the timing of the anticipated start of production at
the Project; the ability to maintain throughput and production
levels at the PGP mill; the tax rate applicable to the Company;
future commodity prices; the grade of mineral resources and mineral
reserves; the ability of the Company to convert inferred mineral
resources to other categories; the ability of the Company to reduce
mining dilution; the ability to reduce capital costs; and
exploration plans. Forward-looking statements are based on
estimates and opinions of management at the date the statements are
made. Although Ascot believes that the expectations reflected in
such forward-looking statements and/or information are reasonable,
undue reliance should not be placed on forward-looking statements
since Ascot can give no assurance that such expectations will prove
to be correct. Ascot does not undertake any obligation to update
forward-looking statements, other than as required by applicable
laws. The forward-looking information contained in this news
release is expressly qualified by this cautionary statement.
Ascot Resources (TSX:AOT)
Gráfico Histórico do Ativo
De Dez 2024 até Jan 2025
Ascot Resources (TSX:AOT)
Gráfico Histórico do Ativo
De Jan 2024 até Jan 2025