Ascot Resources Ltd. (
TSX: AOT; OTCQX:
AOTVF) (“
Ascot” or the
“
Company”) is pleased to announce the Company’s
unaudited financial results for the three months ended March 31,
2024 (“
Q1 2024”), and also to provide a
construction update on the Company’s Premier Gold Project
(“
PGP” or the “
project”), located
on Nisga’a Nation Treaty Lands in the prolific Golden Triangle of
northwestern British Columbia. For details of the unaudited
condensed interim consolidated financial statements and
Management's Discussion and Analysis for the three months ended
March 31, 2024, please see the Company’s filings on SEDAR+
(www.sedarplus.ca).
All amounts herein are reported in $000s of
Canadian dollars (“C$”) unless otherwise
specified.
Q1 2024 AND RECENT HIGHLIGHTS
- On May 7, 2024,
the Company announced a $5,000 non-brokered flow through private
placement (the “Offering”), the proceeds of which will be used to
fund the 2024 exploration program at the PGP. The Offering will
consist of 6,024,096 common shares of the Company, which qualify as
"flow-through shares" within the meaning of the Income Tax Act
(Canada) (the “FT Shares”), at a price of $0.83 per FT Share. The
closing of the Offering is expected to occur in one or more
tranches in or around late-May to mid-June 2024, and is subject to
certain conditions including, but not limited to, the receipt of
all necessary regulatory approvals, including the acceptance of the
Toronto Stock Exchange.
- Rock was
introduced into the grinding circuit of the mill on March 31, 2024,
and first gold-bearing ore was introduced to the mills on April 5,
2024. On April 20, 2024, first gold was poured as a part of the
commissioning process. Commissioning of the processing plant at PGP
is ongoing, with commercial production anticipated in Q3 2024. Two
gold pours have been completed using gold recovered from the
gravity circuit. Another pour from gold recovered from the
carbon-in-leach (“CIL”) circuit is anticipated imminently.
- On February 20,
2024, the Company closed its previously announced financing package
for a total of US$50 million from Sprott Resource Streaming and
Royalty Corp. and its affiliates (“SRSR”) and Nebari Credit Fund
II, LP (“Nebari Credit Fund II”), as described in the Company’s
news release dated January 22, 2024. $13,700 of the above proceeds
were used to buy back two existing 5% NSR royalties on various PGP
property claims on March 15, 2024.
- On February 20,
2024, concurrently with the above-noted financing package, the
Company closed its previously announced bought deal private
placement financing, under which the Company issued a total of
65,343,000 common shares of the Company (the “Common Shares”) at a
price of $0.44 per Common Share, for gross proceeds of
$28,751.
- At the end of Q1
2024, overall construction excluding mine development was 98%
complete compared with 86% complete at the end of 2023. A few
remaining commissioning activities in the mill are underway. The
tailing storage facility was completed and signed off by the
engineer of record at the end of March 2024.
- The new water
treatment plant began operations in February 2024. The high-density
sludge plant has been successfully commissioned and water is being
treated and discharged into the environment. The moving bed
bio-reactor (“MBBR”) is complete and media have been loaded into
the tanks.
- As of April 30,
2024, underground development totaled approximately 2,710 metres at
Big Missouri and 150 metres at Premier.
DEVELOPMENT OF THE PROJECT
Project financingOn February
20, 2024, the Company closed a bought deal private placement for
gross proceeds of $28,751 and a financing package of US$50 million
for the completion and ramp-up of PGP. The financing package
consisted of a royalty restructuring and a cost overrun
facility.
Construction progress key performance
indicatorsAt the end of Q1 2024, overall construction was
98% complete, compared with 86% complete at the end of Q4 2023.
With first gold having been poured on April 20, 2024 via gold
recovered through the gravity circuit, the project construction is
100% complete on schedule and on the most recently provided budget
of approximately C$339 million. Commissioning and ramp-up
activities in the processing plant and in the mine continue towards
achieving commercial production in Q3 of 2024.
SafetyThe Project had no lost
time injuries in Q1 2024. There was an increase in recordable
injuries at the end of the quarter which in part, can be
attributable to seasonal changes and the transition from
construction to operations. As the Project continues its transition
from construction into operations, focus has been placed on the
ongoing development of standard operating procedures, in field job
hazard analysis and worker training. There was a small increase in
property damage reported in the quarter due in part to weather
conditions and the onboarding of a significant number of new
workers to the site. The re-enforcement of reporting to the
operating team remains a key focus to ensure that all learnings are
identified and applied to prevent re-occurrence and reflect in the
future training plans. In Q2 2024, significant work will be placed
to support the operational teams to begin to operate the newly
constructed plant through the final stages of C4 and C5
commissioning.
Processing plant and site
infrastructure Mechanical and electrical work in the mill
was substantially completed in Q1 2024 with minor associated
systems and punch list items to complete. Focus has shifted to
commissioning the process plant and ramp up as well as completing
minor deficiencies.
Stage one of the tailings storage facility
(“TSF”) raise was completed and accepted by the Engineer of Record
for use. Earthworks activities in 2024 will focus on raising the
spillway dam by three metres, producing material for the 2025 raise
and advanced work on the Cascade Creek Diversion in preparation for
the 2025 works and final completion of the diversion.
The new water treatment plant was substantially
mechanically and electrically completed in Q4 2023 with some minor
areas remaining. The high-density sludge circuit was commissioned
in Q1 2024 and is advancing towards full ramp up. The MBBR circuit
was substantially complete in Q1 2024 and will begin full
commissioning as the process plant continues to deposit tailings
into the TSF and feed nitrogen species into the MBBR circuit.
The site power reticulation was completed in Q1
2024. Sustaining capital works in 2024 will focus on reticulation
to the Premier portal as well as the Big Missouri portal.
Mine developmentProcon Mining
& Tunnelling (“Procon”) a mine contractor with extensive
experience in BC and the Golden Triangle continued to advance mine
development at two portal areas: S1 about 9 kilometres north of the
mill which accesses the Big Missouri and Silver Coin deposits, and
the mill adjacent Premier Northern Light (“PNL”) portal which
accesses the Premier and Northern Light orebodies. As of the end of
Q1 2024, Procon had about 57 people on site, 40 of whom were miners
and 10 were maintenance personnel.
At Big Missouri, Procon advanced development
into several ore headings in the A zone, as well as reactivating
the S1 ramp heading that goes to Silver Coin deposit. In Q1 Procon
developed 936 metres at Big Missouri (258 metres in ore and 678
metres in waste, and by April 29, 2024, development advanced to 905
metres in waste and 507 metres in ore total in 2024. Including the
development completed in late 2022 and late 2023, the total
development to date is approximately 2,710 metres in both ore and
waste. Productivities at Big Missouri have continued to improve,
with availability of key equipment such as Maclean bolters being
made a priority.
During Q1 2024, the geological team continued to
encounter high grade material occurrences in both face sampling and
probe hole drilling in multiple areas of the A zone. As previously
reported, these occurrences are in or very near existing wireframes
or logical extensions of wireframes. At the end of March 31, 2024,
a total of approximately 30,000 tonnes of ore was mined from Big
Missouri and stockpiled at Diego pit.
At PNL, Procon dealt with issues related to near
surface structure and weak ground. These issues seem to have abated
at the end of April, and Procon has started to make better progress
as they move into the better ground conditions expected at Premier
given what was seen historically. In Q1 2024 approximately 85
metres were advanced at PNL, and at the end of April this increased
to approximately 150 metres as ground conditions improved.
Mining development is being advanced down into
the Premier deposit for initial mining in the Prew Zone, with ore
development now anticipated to begin in early Q3 2024, and initial
longhole stope production following later in Q3 2024. The ramp has
been strategically laid out to allow for underground drilling on
the Sebakwe Zone in 2024 and will eventually connect a footwall
ramp over to the 602 area at the southern end of the Premier
deposit. Although progress has been slow, the quality of the
resultant work with ground control and shotcrete arches has been
excellent, allowing for a secure and stable ramp for the
life-of-mine production to come from this area approximately 350
metres from the Premier Mill.
RecruitmentAt the end of Q1
2024, total site recruitment has reached approximately 90% of the
planned operational team. A key achievement was the successful
recruitment for some challenging roles pertaining particularly to
some of the maintenance roles, health and safety (specifically,
mine rescue), and technical roles for the mine and processing area.
Policies and procedures development have been ongoing throughout Q1
2024 and key documents will be rolled out in Q2 2024.
Permitting and Environmental
ComplianceA Joint Permit Amendment Application (“JPAA”)
was required to be re-aligned with the project completion dates and
was submitted in October 2023. The JPAA underwent first round
comments through February 2024 and second round comments were
received in late April 2024, with our responses anticipated to be
submitted in May 2024.
The air permit was received on March 25, 2024.
The updated environmental permit PE-8044, including the sewage
treatment facility discharge permit is anticipated to be received
in late May 2024.
2024 EXPLORATION PROGRAM
Planning for the 2024 exploration program is in
full swing with an anticipated start date in late June. There are
several areas on the properties that will be targeted by new
drilling. Near the Premier mill, several drill holes have been
planned around the Prew and Sebakwe zones of the Premier deposit.
The new holes will complement the existing drill pattern at Prew
and test induced polarization geophysical anomalies from last
year’s survey.
Additional drill holes have been planned for the
Big Missouri deposit where underground development is rapidly
providing access to different parts of the deposit. The new holes
will be designed for resource conversion and mine plan addition at
this deposit. Specific new drill targets have been identified at
the Day Zone on the western edge of the deposit, where geophysical
anomalies seem to outline previously untested mineralization along
strike of known ore zones.
Additional exploration drill holes are targeting
a large geophysical anomaly to the west of the Dilworth deposit
that extends surface showings to the north onto Ascot’s PGP
property. This target has a large strike extent and may require
drilling over more than one exploration season.
The Company anticipates a drill program of
between 15,000 and 20,000 metres distributed over the areas
described above. The program will require utilization of two drill
rigs into late September or early October 2024.
FINANCIAL RESULTS FOR THE THREE MONTHS
ENDED MARCH 31, 2024
The Company reported a net loss of $6,208 for Q1
2024 compared to $7,589 for Q1 2023. The lower net loss for the
current period is primarily attributable to a $2,170 decrease in
the loss on extinguishment of debt and a $1,196 decrease in
financing costs, partially offset by increases in other expense
categories.
LIQUIDITY AND CAPITAL
RESOURCES
As at March 31, 2024, the Company had cash &
cash equivalents of $47,028 and working capital deficiency of
$33,030. The working capital deficiency is caused by an estimated
$23,024 as the current portion of the deferred revenue only to be
settled with future production from the Project and the $25,180
value of the Convertible facility, which is classified as current
due to the lender’s right to exercise the conversion option at any
time at a variable exercise price. Excluding these non-cash current
liabilities, working capital was $15,174. In Q1 2024, the Company
issued 67,807,135 common shares, 10,164,528 warrants, and granted
110,000 stock options and 28,667 Deferred Share Units. Also,
100,766 stock options expired or were forfeited, 24,427 Restricted
Share Units were forfeited, and 99,039 stock options, 137,533
Deferred Share Units and 158,726 Restricted Share Units were
exercised in Q1 2024.
MANAGEMENT’S OUTLOOK FOR
2024
In 2024, the Company will transition from the
construction of the mine and related infrastructure to the
operation of the entire site and becoming a gold producer. Despite
the challenges associated with this transition, there are many
opportunities for the Company to grow and create value.
The key activities and priorities for 2024
include:
- Making health
and safety a priority in the commencement of operations
- Completing the
commissioning of the process plant
- Completing the
access ramp and starting the mine production at the Premier
deposit
- Continuing to
expand the mine production and development at the Big Missouri
deposit
- Shipping and
selling of gold doré
- Advancing the
exploration and infill drilling program on the numerous
opportunities to increase resources
- Compliance with
the environmental requirements of the site and making sure water
treatment and the tailings management facility operate as
designed
- Successfully
transition from a mine developer to a mine operator
Qualified Person
John Kiernan, P.Eng., Chief Operating Officer of
the Company is the Company’s Qualified Person (QP) as defined by
National Instrument 43-101 and has reviewed and approved the
technical contents of this news release.
On behalf of the Board of Directors of
Ascot Resources Ltd.“Derek C. White”President & CEO,
and Director
For further information
contact:
David Stewart, P.Eng.VP, Corporate Development
& Shareholder Communications dstewart@ascotgold.com
778-725-1060 ext. 1024
About Ascot Resources Ltd.
Ascot is a Canadian mining company focused on
commissioning its 100%-owned Premier Gold Mine, which poured first
gold in April 2024 and is located on Nisga’a Nation Treaty Lands,
in the prolific Golden Triangle of northwestern British Columbia.
Concurrent with commissioning Premier towards commercial production
anticipated in Q3 of 2024, the Company continues to explore its
properties for additional high-grade gold mineralization. Ascot’s
corporate office is in Vancouver, and its shares trade on the TSX
under the ticker AOT and on the OTCQX under the ticker AOTVF. Ascot
is committed to the safe and responsible operation of the Premier
Gold Mine in collaboration with Nisga’a Nation and the local
communities of Stewart, BC and Hyder, Alaska.
For more information about the Company, please
refer to the Company’s profile on SEDAR+ at www.sedarplus.ca or
visit the Company’s web site at www.ascotgold.com.
The TSX has not reviewed and does not accept
responsibility for the adequacy or accuracy of this release.
Cautionary Statement Regarding
Forward-Looking Information
All statements and other information contained
in this press release about anticipated future events may
constitute forward-looking information under Canadian securities
laws ("forward-looking statements").
Forward-looking statements are often, but not always, identified by
the use of words such as "seek", "anticipate", "believe", "plan",
"estimate", "expect", "targeted", "outlook", "on track" and
"intend" and statements that an event or result "may", "will",
"should", "could", “would” or "might" occur or be achieved and
other similar expressions. All statements, other than statements of
historical fact, included herein are forward-looking statements,
including statements in respect of the terms of the Offering, the
closing of the Offering, the advancement and development of the PGP
and the timing related thereto, the completion of the PGP mine, the
production of gold and management’s outlook for the remainder of
2024 and beyond. These statements involve known and unknown risks,
uncertainties and other factors that may cause actual results or
events to differ materially from those anticipated in such
forward-looking statements, including risks associated with
entering into definitive agreements for the transactions described
herein; fulfilling the conditions to closing of the transactions
described herein, including the receipt of TSX approvals; the
business of Ascot; risks related to exploration and potential
development of Ascot's projects; business and economic conditions
in the mining industry generally; fluctuations in commodity prices
and currency exchange rates; uncertainties relating to
interpretation of drill results and the geology, continuity and
grade of mineral deposits; the need for cooperation of government
agencies and indigenous groups in the exploration and development
of Ascot’s properties and the issuance of required permits; the
need to obtain additional financing to develop properties and
uncertainty as to the availability and terms of future financing;
the possibility of delay in exploration or development programs and
uncertainty of meeting anticipated program milestones; uncertainty
as to timely availability of permits and other governmental
approvals; and other risk factors as detailed from time to time in
Ascot's filings with Canadian securities regulators, available on
Ascot's profile on SEDAR+ at www.sedarplus.ca including the Annual
Information Form of the Company dated March 25, 2024 in the section
entitled "Risk Factors". Forward-looking statements are based on
assumptions made with regard to: the estimated costs associated
with construction of the Project; the timing of the anticipated
start of production at the Project; the ability to maintain
throughput and production levels at the PGP mill; the tax rate
applicable to the Company; future commodity prices; the grade of
mineral resources and mineral reserves; the ability of the Company
to convert inferred mineral resources to other categories; the
ability of the Company to reduce mining dilution; the ability to
reduce capital costs; and exploration plans. Forward-looking
statements are based on estimates and opinions of management at the
date the statements are made. Although Ascot believes that the
expectations reflected in such forward-looking statements and/or
information are reasonable, undue reliance should not be placed on
forward-looking statements since Ascot can give no assurance that
such expectations will prove to be correct. Ascot does not
undertake any obligation to update forward-looking statements,
other than as required by applicable laws. The forward-looking
information contained in this news release is expressly qualified
by this cautionary statement.
Ascot Resources (TSX:AOT)
Gráfico Histórico do Ativo
De Dez 2024 até Jan 2025
Ascot Resources (TSX:AOT)
Gráfico Histórico do Ativo
De Jan 2024 até Jan 2025