Ero Copper Corp. (TSX: ERO, NYSE: ERO) (the
“Company”) is pleased to announce that it has received the
Operational License for the Tucumã Project (the "Project") – the
last remaining permitting milestone for commercial operation. With
physical completion at approximately 99%, commissioning well
advanced, and over 90% of the operational staff hired and trained,
first concentrate continues to be expected early in the third
quarter of 2024. The total direct capital cost estimate for Project
completion remains unchanged at approximately $310 million.
HIGHLIGHTS
- Permitting: Project awarded Operational
License by the Pará State environmental agency, Secretaria de
Estado de Meio Ambiente e Sustentabilidade ("SEMAS")
- Construction: Physical construction of the
Project has reached approximately 99% completion
- All mechanical equipment and electrical installations complete,
ball mill successfully handed over to operations
- Pre-stripping activities completed ahead of schedule, and full
mining operations have commenced. To date, approximately 110,000
tonnes of ore have been placed on the run-of-mine stockpile with an
additional 55,000 tonnes of ore drilled and ready to be blasted in
the mine
- Process control room, on-site process laboratory, and
administrative offices complete
- Remaining piping, electric cabling and instrumentation
installations on track to complete construction by the end of Q2
2024
- Commissioning Plan: Commissioning activities
continue to progress on site
- First ore through primary and secondary crushers as well as
screening and conveyance systems completed with approximately
10,000 tonnes of ore placed on the crushed ore stockpile to
date
- Mechanical completion and sub-component commissioning
(lubrication, hydraulic, electrical, instrumentation and automation
systems) completed
- First charge through the milling circuit completed, flotation
and filtration commissioning nearing completion - Project remains
on track to achieve first production and initiate Project ramp-up
in early Q3 2024
- People & Safety: To date, there have been
no lost-time injuries on the Project, with over six million hours
of work completed since 2022
- Additionally, all site-based management positions have been
filled and over 90% of the operational staff required for
full-scale operations have been hired and fully trained
- Project Capital Estimate: Direct Project
capital expenditure for completion remains unchanged at
approximately $310 million
"I am thrilled to announce that we have received
our operational license from SEMAS - the last regulatory approval
required for commercial operations to commence at Tucumã. Across
our operations and throughout the Project development, Brazil has
continued to demonstrate its commitment to advancing strategic
critical mineral projects, and the success of the Tucumã Project is
a testament to this effort," said David Strang, Chief Executive
Officer.
"With the commissioning of our Tucumã Project
progressing well and first concentrate production set to commence
next month, I want to highlight the outstanding performance
demonstrated by our entire site-based construction, commissioning,
and operational teams, who recently achieved over six million hours
of work without a lost time injury on the Project. The Company is
rapidly approaching a major inflection point, which we believe will
benefit all of our stakeholders for years to come."
Figure 1: June 2024 aerial view
of completed pre-strip and commencement of mining operations.
Figure 2: Completed crushing
circuit with ~10,000 tonnes of crushed ore placed on stockpile
(June 2024).
Figure 3: Ball mill completion
and handover to operations (June 2024).
Figure 4: Completion and
commissioning of Jameson flotation cells as of June 2024.
Figure 5: Completion and
commissioning of flotation circuit as of June 2024.
ABOUT ERO COPPER CORP
Ero is a high-margin, high-growth, low
carbon-intensity copper producer with operations in Brazil and
corporate headquarters in Vancouver, B.C. The Company's primary
asset is a 99.6% interest in the Brazilian copper mining company,
Mineração Caraíba S.A. ("MCSA"), 100% owner of the Company's
Caraíba Operations (formerly known as the MCSA Mining Complex),
which are located in the Curaçá Valley, Bahia State, Brazil and
include the Pilar and Vermelhos underground mines and the Surubim
open pit mine, and the Tucumã Project (formerly known as Boa
Esperança), an IOCG-type copper project located in Pará, Brazil.
The Company also owns 97.6% of NX Gold S.A. ("NX Gold") which owns
the Xavantina Operations (formerly known as the NX Gold Mine),
comprised of an operating gold and silver mine located in Mato
Grosso, Brazil. Additional information on the Company and its
operations, including technical reports on the Caraíba Operations,
Xavantina Operations and Tucumã Project, can be found on SEDAR+ at
www.sedarplus.ca/landingpage/ and on EDGAR (www.sec.gov). The
Company’s shares are publicly traded on the Toronto Stock Exchange
and the New York Stock Exchange under the symbol “ERO”.
FOR MORE INFORMATION, PLEASE
CONTACT
Courtney Lynn, SVP, Corporate Development,
Investor Relations & Sustainability (604) 335-7504
info@erocopper.com
CAUTION REGARDING FORWARD LOOKING INFORMATION
AND STATEMENTS
This press release contains “forward-looking
statements” within the meaning of the United States Private
Securities Litigation Reform Act of 1995 and “forward-looking
information” within the meaning of applicable Canadian securities
legislation (collectively, “forward-looking statements”).
Forward-looking statements include statements that use
forward-looking terminology such as “may”, “could”, “would”,
“will”, “should”, “intend”, “target”, “plan”, “expect”, “budget”,
“estimate”, “forecast”, “schedule”, “anticipate”, “believe”,
“continue”, “potential”, “view” or the negative or grammatical
variation thereof or other variations thereof or comparable
terminology. Forward-looking statements may include, but are not
limited to, statements with respect to the timing of construction
of remaining piping, electrical and instrumentation installations,
the timing of initial copper concentrate production, estimated
Project capital to be spent, the expected completion of activities
described in the commissioning plan, and any other statement that
may predict, forecast, indicate or imply future plans, intentions,
levels of activity, results, performance or achievements.
Forward-looking statements are not a guarantee
of future performance. There can be no assurance that
forward-looking statements will prove to be accurate, as actual
results and future events could differ materially from those
anticipated in such statements. Forward-looking statements involve
statements about the future and are inherently uncertain, and the
Company’s actual results, achievements or other future events or
conditions may differ materially from those reflected in the
forward-looking statements due to a variety of risks, uncertainties
and other factors, including, without limitation, those referred to
herein and in the AIF under the heading “Risk Factors”.
The Company’s forward-looking statements are
based on the assumptions, beliefs, expectations and opinions of
management on the date the statements are made, many of which may
be difficult to predict and beyond the Company’s control. In
connection with the forward-looking statements contained in this
press release and in the AIF, the Company has made certain
assumptions about, among other things: favourable equity and debt
capital markets; the ability to raise any necessary additional
capital on reasonable terms to advance the production, development
and exploration of the Company’s properties and assets; future
prices of copper, gold and other metal prices; the timing and
results of exploration and drilling programs; the accuracy of any
mineral reserve and mineral resource estimates; the geology of the
Caraíba Operations, the Xavantina Operations and the Tucumã Project
being as described in the respective technical report for each
property; production costs; the accuracy of budgeted exploration,
development and construction costs and expenditures; the price of
other commodities such as fuel; future currency exchange rates and
interest rates; operating conditions being favourable such that the
Company is able to operate in a safe, efficient and effective
manner; work force continuing to remain healthy in the face of
prevailing epidemics, pandemics or other health risks, political
and regulatory stability; the receipt of governmental, regulatory
and third party approvals, licenses and permits on favourable
terms; obtaining required renewals for existing approvals, licenses
and permits on favourable terms; requirements under applicable
laws; sustained labour stability; stability in financial and
capital goods markets; availability of equipment; positive
relations with local groups and the Company’s ability to meet its
obligations under its agreements with such groups; and satisfying
the terms and conditions of the Company’s current loan
arrangements. Although the Company believes that the assumptions
inherent in forward-looking statements are reasonable as of the
date of this press release, these assumptions are subject to
significant business, social, economic, political, regulatory,
competitive and other risks and uncertainties, contingencies and
other factors that could cause actual actions, events, conditions,
results, performance or achievements to be materially different
from those projected in the forward-looking statements. The Company
cautions that the foregoing list of assumptions is not exhaustive.
Other events or circumstances could cause actual results to differ
materially from those estimated or projected and expressed in, or
implied by, the forward-looking statements contained in this press
release. There can be no assurance that forward-looking statements
will prove to be accurate, as actual results and future events
could differ materially from those anticipated in such statements.
Accordingly, readers should not place undue reliance on
forward-looking statements.
Forward-looking statements contained herein are
made as of the date of this press release and the Company disclaims
any obligation to update or revise any forward-looking statement,
whether as a result of new information, future events or results or
otherwise, except as and to the extent required by applicable
securities laws.
CAUTIONARY NOTES REGARDING MINERAL RESOURCE AND
MINERAL RESERVE ESTIMATES
Unless otherwise indicated, all reserve and
resource estimates included in this press release and the documents
incorporated by reference herein have been prepared in accordance
with National Instrument 43-101, Standards of Disclosure for
Mineral Projects (“NI 43-101") and the Canadian Institute of
Mining, Metallurgy and Petroleum (the “CIM”) — CIM Definition
Standards on Mineral Resources and Mineral Reserves, adopted by the
CIM Council, as amended (the “CIM Standards”). NI 43-101 is a rule
developed by the Canadian Securities Administrators that
establishes standards for all public disclosure an issuer makes of
scientific and technical information concerning mineral projects.
Canadian standards, including NI 43-101, differ significantly from
the requirements of the United States Securities and Exchange
Commission (the “SEC”), and reserve and resource information
included herein may not be comparable to similar information
disclosed by U.S. companies. In particular, and without limiting
the generality of the foregoing, this press release and the
documents incorporated by reference herein use the terms “measured
resources,” “indicated resources” and “inferred resources” as
defined in accordance with NI 43-101 and the CIM Standards.
Further to recent amendments, mineral property
disclosure requirements in the United States (the “U.S. Rules”) are
governed by subpart 1300 of Regulation S-K of the U.S. Securities
Act of 1933, as amended (the “U.S. Securities Act”) which differ
from the CIM Standards. As a foreign private issuer that is
eligible to file reports with the SEC pursuant to the
multi-jurisdictional disclosure system (the “MJDS”), Ero is not
required to provide disclosure on its mineral properties under the
U.S. Rules and will continue to provide disclosure under NI 43-101
and the CIM Standards. If Ero ceases to be a foreign private issuer
or loses its eligibility to file its annual report on Form 40-F
pursuant to the MJDS, then Ero will be subject to the U.S. Rules,
which differ from the requirements of NI 43-101 and the CIM
Standards.
Pursuant to the new U.S. Rules, the SEC
recognizes estimates of “measured mineral resources”, “indicated
mineral resources” and “inferred mineral resources”. In addition,
the definitions of “proven mineral reserves” and “probable mineral
reserves” under the U.S. Rules are now “substantially similar” to
the corresponding standards under NI 43-101. Mineralization
described using these terms has a greater amount of uncertainty as
to its existence and feasibility than mineralization that has been
characterized as reserves. Accordingly, U.S. investors are
cautioned not to assume that any measured mineral resources,
indicated mineral resources, or inferred mineral resources that Ero
reports are or will be economically or legally mineable. Further,
“inferred mineral resources” have a greater amount of uncertainty
as to their existence and as to whether they can be mined legally
or economically. Under Canadian securities laws, estimates of
“inferred mineral resources” may not form the basis of feasibility
or pre-feasibility studies, except in rare cases. While the above
terms under the U.S. Rules are “substantially similar” to the
standards under NI 43-101 and CIM Standards, there are differences
in the definitions under the U.S. Rules and CIM Standards.
Accordingly, there is no assurance any mineral reserves or mineral
resources that Ero may report as “proven mineral reserves”,
“probable mineral reserves”, “measured mineral resources”,
“indicated mineral resources” and “inferred mineral resources”
under NI 43-101 would be the same had Ero prepared the reserve or
resource estimates under the standards adopted under the U.S.
Rules.
Photos accompanying this announcement are available
at:https://www.globenewswire.com/NewsRoom/AttachmentNg/407f0e04-d215-40e2-baa6-c3417c18fa2f
https://www.globenewswire.com/NewsRoom/AttachmentNg/42c0f3c1-0bf2-414c-a71b-3fee59399fe1
https://www.globenewswire.com/NewsRoom/AttachmentNg/05576047-5f6b-4a36-a8ad-4a73c871c929
https://www.globenewswire.com/NewsRoom/AttachmentNg/bbdaae22-0b9b-4818-9f63-16a424a1aa2b
https://www.globenewswire.com/NewsRoom/AttachmentNg/f146cb32-8314-4624-880e-5ff68252ac6a
Ero Copper (TSX:ERO)
Gráfico Histórico do Ativo
De Out 2024 até Nov 2024
Ero Copper (TSX:ERO)
Gráfico Histórico do Ativo
De Nov 2023 até Nov 2024