Alamos Gold Inc. (
TSX:AGI;
NYSE:AGI) (“Alamos” or the “Company”) today provided
updated three-year production and operating guidance incorporating
the recently completed acquisition of the Magino mine, as well as
increased 2024 production guidance for the Mulatos District.
Capital guidance has also been updated to include the development
of the Puerto Del Aire (“PDA”) project and a revised initial
capital estimate for the Phase 3+ Expansion at Island Gold.
Consolidated 2024 production guidance for
existing operations (pre-Magino acquisition) has increased 4%
reflecting the outperformance of La Yaqui Grande, while 2025 and
2026 production guidance (excluding Magino) remains unchanged from
previous guidance issued in January 2024. Consolidated cost
guidance for existing operations remains largely unchanged with a
slight increase in 2024 cost guidance and no changes across 2025
and 2026.
The inclusion of Magino contributed to a 13%
increase in consolidated production guidance in 2024, and more than
20% increase in both 2025 and 2026, enhancing the Company’s strong
growth profile. All-in sustaining cost (“AISC”) guidance has
increased 11% on average across the three years reflecting Magino’s
relatively higher costs. Company-wide AISC is expected to remain
well below industry average and continue decreasing over the
longer-term driven by low-cost production growth at Island Gold,
and continued improvements at the Magino operation.
“The addition of Magino has enhanced our already
strong growth profile, and its integration with Island Gold is
expected to drive significant synergies and open up longer-term
opportunities. Our near-term rate of production has increased by
more than 20%. Longer-term we have the capacity to grow
company-wide production to approximately 900,000 ounces per year,
with further upside potential through future expansions of the
Island Gold District,” said John A. McCluskey, President and Chief
Executive Officer. “Our costs remain well below the industry
average and are expected to decrease significantly over the next
several years as we deliver on our low-cost growth initiatives.
Through growing production and declining costs, we expect to
deliver substantial free cash flow growth in the years ahead.”
Three Year Guidance Overview: Operating
Mines
|
2024 |
2025 |
2026 |
|
Current |
Previous(1) |
Current |
Previous(1) |
Current |
Previous(1) |
|
|
|
|
|
|
|
Gold Production - ex Magino
(000 oz) |
510 - 540 |
485 - 525 |
470 - 510 |
470 - 510 |
520 - 560 |
520 - 560 |
Consolidated Gold Production (000
oz) |
550 - 590 |
485 - 525 |
575 - 625 |
470 - 510 |
630 - 680 |
520 - 560 |
|
|
|
|
|
|
|
Total Cash Costs(2) - ex
Magino ($/oz) |
$840 - 890 |
$825 - 875 |
$700 - 800 |
$700 - 800 |
$675 - 775 |
$675 - 775 |
Consolidated Total Cash Costs
($/oz) |
$890 - 940 |
$825 - 875 |
$775 - 875 |
$700 - 800 |
$750 - 850 |
$675 - 775 |
|
|
|
|
|
|
|
All-in Sustaining
Costs(2),(3) - ex Magino ($/oz) |
$1,150 -1,200 |
$1,125 - 1,175 |
$1,050 - 1,150 |
$1,050 - 1,150 |
$975 - 1,075 |
$975 - 1,075 |
Consolidated All-in
Sustaining Costs(2),(3)
($/oz) |
$1,250 - 1,300 |
$1,125 - $1,175 |
$1,175 - 1,275 |
$1,050 -
1,150 |
$1,100 - 1,200 |
$975 -
1,075 |
|
|
|
|
|
|
|
(1) Previous guidance was issued on January 10, 2024
and related to Young-Davidson, Island Gold and Mulatos District
only.(2) Refer to the “Non-GAAP Measures and Additional
GAAP” disclosure at the end of this press release for a description
of these measures.(3) All-in sustaining cost guidance
for 2025 and 2026 includes similar assumptions for G&A and
stock based compensation as included in 2024.
-
2024 production guidance increased 13%: to between
550,000 and 590,000 ounces. This reflects increased production
guidance from the Mulatos District driven by the outperformance of
La Yaqui Grande (relative to previous guidance issued in January
2024), and the inclusion of Magino. Production from Magino has been
included post completion of the Argonaut Gold acquisition on July
12, 2024, representing slightly less than half a year of
production
-
2025 and 2026 production guidance increased by over
20%: reflecting the inclusion of Magino for full years and
the operation at planned capacity. This includes a 22% increase in
2025 production guidance, and 21% increase in 2026 guidance to
between 630,000 and 680,000 ounces. This represents 30% production
growth relative to the mid-point of previous 2024 guidance issued
at the start of the year
-
Longer-term production potential of 900,000+ oz per
year: through the development of PDA, with initial
production expected mid-2027, and growth from Lynn Lake with first
production as early as the second half of 2027. An evaluation of a
longer-term expansion of the Magino mill to 15,000 to 20,000 tonnes
per day (“tpd”) is also underway which could support additional
growth bringing production closer to one million ounces per
year
-
AISC guidance increased 11% on average between 2024 and
2026: reflecting the inclusion of relatively higher cost
Magino production. Costs remain well below the industry average
with steady improvements expected through 2026 driven by low-cost
production growth
-
Declining cost profile with AISC expected to decrease 10%
by 2026 compared to 2024: AISC is expected to decrease to
between $1,100 and $1,200 per ounce in 2026 driven by low-cost
growth at Island Gold and improving costs at Magino. Beyond 2026,
AISC is expected to decrease below $1,100 per ounce, reflecting
additional low-cost growth from Island Gold and Lynn Lake
Three Year Guidance Overview: Capital
|
2024 |
|
2025 |
2026 |
($ millions) |
Current |
Previous(2) |
Current |
Previous(2) |
Current |
Previous(2) |
|
|
|
|
|
|
|
Sustaining & Growth
Capital (operating mines, ex. Exploration & Lynn Lake)(1) |
$325 - 365 |
$325 - 365 |
$310 - 350 |
$310 - 350 |
$175 - 200 |
$175 - 200 |
Addition of PDA |
- |
|
$20 |
|
$90 - 95 |
|
Addition of Magino |
$35 - 40 |
|
$55 - 60 |
|
$55 - 60 |
|
Changes to Phase 3+ Expansion |
($30) |
|
$40 - 45 |
|
$25 - 35 |
|
Total Capital (operating mines, ex. Exploration
& Lynn Lake)(1) |
$330 - 375 |
$325 - 365 |
$425 - 475 |
$310 - 350 |
$345 - 390 |
$175 - 200 |
|
|
|
|
|
|
|
(1) Refer to the "Non-GAAP Measures and Additional
GAAP" disclosure at the end of this press release for a description
of these measures.(2) Previous guidance was issued on
January 10, 2024 and related to Young-Davidson, Island Gold and
Mulatos District only.
- Capital spending increased
in 2025 and 2026 reflecting inclusion of Magino, PDA development,
and updated Phase 3+ Expansion capital:
- The main driver of the increase in
capital spending over the next three years is the inclusion of
growth and sustaining capital for the newly acquired Magino
operation, as well as growth capital for the development of PDA.
Both are in support of high-return, lower-risk organic growth
initiatives
- 2024 capital guidance range was
increased slightly to between $330 and $375 million (excluding
capitalized exploration), reflecting the inclusion of Magino from
July 2024 onward, largely offset by a reduction at Island Gold with
the mill expansion and tailings lifts no longer required with the
Magino acquisition
- 2025 and 2026 capital guidance was
revised to include:
- initial capital for the
high-return, PDA project as per the recently announced development
plan (see September 4, 2024 press release)
- the inclusion of Magino growth and
sustaining capital for the normal course operation, as well as for
the completion of the mill optimization and other projects that
were deferred by the previous operator
- additional capital for the
completion of the Phase 3+ Expansion
- Phase 3+ Expansion initial capital
has been increased by approximately $40 million with expected
completion on track for the first half of 2026. This represents a
5% increase from the initial capital estimate of $756 million
provided in the first half of 2022. Updated capital is now expected
to total $796 million, with $415 million remaining to be spent as
of June 30, 2024. The increase was driven by ongoing inflationary
pressures since 2022, and scope changes to the project, partly
offset by synergies from the Magino acquisition and the weaker
Canadian dollar
- Strong
ongoing free cash flow while funding high-return growth
initiatives: the Company generated $131 million in free
cash flow in the first half of 2024 and expects to continue
generating strong free cash flow at current gold prices while
funding the Phase 3+ Expansion at Island Gold, and development of
PDA. The completion of Phase 3+ Expansion in 2026 and PDA
development in 2027 are expected to drive growing free cash flow
generation through higher production, lower costs, and lower
capital spending
Guidance statements in this release are
forward-looking information. See the Assumptions section of this
release along with the cautionary note at the end of this
release.
Upcoming catalysts
- Burnt Timber and Linkwood
study (satellite deposits to Lynn Lake): Q4 2024
- 2024 year-end Mineral
Reserve and Resource update: February 2025
- Island Gold District Life
of Mine Plan: mid-2025
- Island Gold District
Expansion Study: Q4 2025
- Island Gold District,
Mulatos District & Young-Davidson exploration updates:
ongoing
2024 Guidance
|
2024 Guidance |
|
|
Young-Davidson |
IslandGold |
MaginoMine(1) |
MulatosDistrict |
LynnLake |
TotalCurrent |
TotalPrevious
(2) |
Gold production (000 oz) |
180 - 190 |
145 - 155 |
40 - 50 |
185 - 195 |
|
550 - 590 |
485 - 525 |
Total cash costs(3) ($/oz) |
$1,000 - 1,050 |
$550 - 600 |
$1,450 - 1,550 975 |
$925 - 975 |
- |
$890 - 940 |
$825 - 875 |
All-in sustaining costs(3) ($/oz) |
|
|
|
|
|
$1,250 - 1,300 |
$1,125 - 1,175 |
Mine-site all-in sustaining costs(3)(4)
($/oz) |
$1,225 - 1,275 |
$875 - 925 |
$2,250 - 2,350 |
$1,000 - 1,050 |
- |
|
|
Capital expenditures ($ millions) |
|
|
|
|
|
|
|
Sustaining capital(3) |
$40 - 45 |
$50 - 55 |
$35 - 40 |
$3 - 5 |
- |
$128 - 145 |
$93 - 105 |
Growth capital(3) |
$20 - 25 |
$180 - 200 |
- |
$2 - 5 |
- |
$202 - 230 |
$232 - 260 |
Total Sustaining and Growth Capital(3)
- producing mines ($ millions) |
$60 - 70 |
$230 - 255 |
$35 - 40 |
$5 - 10 |
- |
$330 - 375 |
$325 - 365 |
Growth capital(3) – development
projects ($ millions) |
|
|
|
|
$25 |
$25 |
$25 |
Capitalized exploration(3) ($ millions) |
$10 |
$13 |
$2 |
$9 |
$9 |
$43 |
$41 |
Total capital expenditures and capitalized
exploration(3) ($ millions) |
$70 - 80 |
$243 - 268 |
$37 - 42 |
$14 - 19 |
$34 |
$398 - 443 |
$391 - 431 |
(1) The guidance for the Magino Mine
is for Alamos’ ownership period from July 12, 2024 to December 31,
2024.(2) Previous guidance was issued on January 10,
2024 and related to Young-Davidson, Island Gold and Mulatos
District only.(3) Refer to the "Non-GAAP Measures and
Additional GAAP" disclosure at the end of this press release for a
description of these measures.(4) For the purposes of
calculating mine-site all-in sustaining costs at individual mine
sites, the Company does not include an allocation of corporate and
administrative and share based compensation expenses to the mine
sites.
Gold production in 2024 is expected to range
between 550,000 and 590,000 ounces, a 13% increase from the
guidance provided in January 2024 (based on mid-point). The
increase is driven by the incorporation of the Magino mine, as well
as increased guidance from the Mulatos District.
With the closing of the Argonaut Gold
acquisition on July 12, 2024, less than half a year of production
from Magino is being incorporated into 2024 estimates. Magino is
expected to produce 40,000 to 50,000 ounces in the second half of
2024. As previously outlined, the third quarter is expected to be
impacted by downtime to implement various improvements to the
crushing and conveying circuit. Combined with the partial reporting
period, third quarter Magino production is expected to be slightly
less than the second quarter. Production rates at Magino are
expected to improve in the fourth quarter and into 2025 reflecting
various improvements to the Magino mill that are being implemented
in the third quarter.
Reflecting the strong outperformance of La Yaqui
Grande during the first half of the year, Mulatos District
production guidance has been increased by 15% to between 185,000
and 195,000 ounces.
AISC guidance has increased 11% relative to
previous guidance (based on the mid-point) with nearly all of the
increase attributable to the inclusion of relatively higher cost
production from Magino during the ramp up of the operation.
Young-Davidson’s AISC guidance was increased by
4% to reflect higher realized costs during the first quarter which
had been impacted by temporary downtime to replace head ropes in
the Northgate shaft. Young-Davidson’s costs decreased significantly
in the second quarter and are expected to continue to improve in
the second half of the year. Additionally, the increase in the
Company’s share price during the year resulted in a revaluation of
previously issued stock based compensation which contributed to
approximately $10 per ounce increase in AISC guidance.
Capital guidance for 2024 has increased by 2%
relative to previous guidance. The increase reflects the inclusion
of Magino, largely offset by capital savings at Island Gold through
the integration of the two operations. With ore from Island Gold to
be processed at lower operating costs through the larger Magino
mill starting early 2025, the Island Gold mill expansion and
tailings lift previously planned for 2024 are no longer
required.
Capital spending at Magino during the second half of 2024 will
be comprised of capitalized stripping and equipment leases, as well
as ongoing work on the mill optimization.
2024 – 2026 Guidance: Operating Mines
|
2024 |
2025 |
2026 |
|
Current |
Previous(1) |
Current |
Previous(1) |
Current |
Previous(1) |
Gold
Production (000 oz) |
|
|
|
|
|
|
Young-Davidson |
180 - 190 |
180 - 195 |
180 - 195 |
180 - 195 |
180 - 195 |
180 - 195 |
Island Gold
District(2) |
145 - 155 |
145 - 160 |
275 - 300 |
170 - 185(1) |
330 - 355 |
220 - 235(1) |
Magino
Mine(2) |
40 - 50 |
n/a |
n/a |
n/a |
Mulatos District |
185 - 195 |
160 - 170 |
120 - 130 |
120 - 130 |
120 - 130 |
120 - 130 |
Total Gold Production (000 oz) |
550 - 590 |
485 - 525 |
575 - 625 |
470 - 510 |
630 - 680 |
520 - 560 |
|
|
|
|
|
|
|
Total Cash
Costs(3)
($/oz) |
$890 - 940 |
$825 - 875 |
$775 - 875 |
$700 - 800 |
$750 - 850 |
$675 - 775 |
All-in Sustaining
Costs(3),(4)
($/oz) |
$1,250 - 1,300 |
$1,125 - 1,175 |
$1,175 - 1,275 |
$1,050 - 1,150 |
$1,100 - 1,200 |
$975 - 1,075 |
|
|
|
|
|
|
|
Sustaining
capital(3),(5)
($ millions) |
$128 - 145 |
$93 - 105 |
$145 - 160 |
$115 - 125 |
$135 - 150 |
$105 - 115 |
Growth
capital(3),(5)
($ millions) |
$202 - 230 |
$232 - 260 |
$280 - 315 |
$195 - 225 |
$210 - 240 |
$70 - 85 |
Total sustaining &
growth
capital(3),(5)
(Operating mines; ex. Exploration) ($ millions) |
$330 - 375 |
$325 - 365 |
$425 - 475 |
$310 - 350 |
$345 - 390 |
$175 - 200 |
|
|
|
|
|
|
|
(1) Previous guidance was issued on January 10, 2024
and related to Young-Davidson, Island Gold and Mulatos District
only.(2) 2024 production and cost estimates are for the
Island Gold Mine, for 2025 and 2026 the Island Gold District
includes both the Island Gold and Magino mines.(3) Refer
to the “Non-GAAP Measures and Additional GAAP” disclosure at the
end of this press release for a description of these
measures.(4) All-in sustaining cost guidance for 2025
and 2026 includes similar assumptions for G&A and stock based
compensation as included in 2024.(5) Sustaining and
growth capital guidance is for producing mines and PDA development,
but excludes capital for Lynn Lake and capitalized exploration.
Production guidance for 2025 has increased 22%
relative to previous guidance reflecting a full year of production
from Magino, at higher milling rates. Starting in 2025, production
and costs from Magino will be reported as part of the Island Gold
District with both operations to be integrated and utilizing one
centralized mill and tailings facility. Milling rates at the Magino
mill are expected to increase to design rates of 10,000 tonnes per
day (“tpd”) within the fourth quarter of 2024, with a further
increase to an optimized rate of 11,200 tonnes per day expected
early in 2025.
At that point, the Island Gold mill will be shut
down and Island Gold ore will be processed through the Magino mill
at significantly lower processing costs. An expansion of the mill
to 12,400 tpd is expected to be completed in 2026 and coincide with
the completion of the Phase 3+ Expansion. This is expected to
accommodate 10,000 tpd of ore from Magino and 2,400 tpd from Island
Gold.
Production guidance for 2026 has increased 21%
to between 630,000 and 680,000 ounces. This represents a 30%
increase from previous guidance for 2024 reflecting the inclusion
of Magino, as well as the completion of the Phase 3+ Expansion at
Island Gold. There are no changes to 2025 and 2026 guidance for the
Company’s other operations compared to previous guidance.
This growth is expected to continue into 2027
driven by a full year of production following the completion of the
Phase 3+ Expansion, as well as initial production from PDA in the
second half of the year. The Lynn Lake project represents further
growth potential with initial production as early as the latter
part of 2027.
AISC guidance for 2025 and 2026 has increased
11% and 12%, respectively, relative to previous guidance.
Consistent with 2024, this reflects the inclusion of relatively
higher-cost production from Magino. AISC is expected to decrease to
between $1,100 and $1,200 per ounce in 2026, a 10% decrease from
2024 driven by low-cost growth at Island Gold, and improving costs
at Magino. This trend is expected to continue beyond 2026 with AISC
expected to decrease below $1,100 per ounce reflecting additional
low-cost growth from Island Gold and Lynn Lake.
Capital spending in 2025 and 2026 was revised
higher from the previous guidance to reflect:
-
capital for the construction of the high-return PDA project, as
outlined in the development plan announced on September 4,
2024
-
the inclusion of Magino and associated capital for tailings,
equipment leases, normal-course maintenance, as well as projects
that were deferred by the previous operator, including the
construction of a truck shop and fish habitat
-
capital to connect Magino to the electric grid by 2026. This is
expected to drive significant operating cost savings with power to
Magino currently generated by a Compressed Natural Gas (“CNG”)
plant
- a 5% increase in capital to
complete the Phase 3+ Expansion reflecting ongoing inflation since
the first half of 2022, and scope changes. This was largely offset
by synergies through the integration of Magino and Island Gold, as
well as the weaker Canadian dollar
(1) Production and AISC are based on mid-point of guidance;
previous guidance was issued on January 10, 2024 and related to
Young-Davidson, Island Gold and Mulatos District only.(2) Refer to
the “Non-GAAP Measures and Additional GAAP” disclosure at the end
of this press release for a description of these measures.(3) Total
consolidated all-in sustaining costs include corporate and
administrative and share based compensation expenses.
Updated Phase 3+ Expansion
CapitalThe Phase 3+ Expansion initial capital estimate has
been updated to reflect inflation and scope changes since the Phase
3+ Expansion Study was completed in the first half of 2022, as well
as synergies from the acquisition of Magino.
Initial capital for the Phase 3+ Expansion has
been increased by approximately $40 million to the expected
completion of the expansion in 2026. Initial capital is now
expected to total $796 million, a 5% increase from the initial
capital estimate of $756 million provided in the first half of
2022.
The increase was driven by ongoing inflationary
pressures since 2022, and scope changes to the project, partly
offset by synergies from the Magino acquisition, and the weaker
Canadian dollar. The key changes within the updated capital
estimate are as follows:
-
Magino mill expansion: $40 million increase for the expansion of
the Magino mill to 12,400 tpd by 2026. This will accommodate ore
from both Magino and the increased production from Island Gold
following the completion of the Phase 3+ Expansion
-
Inflation: $90 million increase in capital driven by more than two
years of labour and material inflation representing a 12% increase
on the total capital spend between 2022 and 2026. Since the Phase
3+ Expansion Study was completed in the first half of 2022,
company-wide inflation has averaged 5% per year
-
Scope changes: $30 million increase reflecting the following
changes to the project:
-
Relocation of crushing facility from surface to underground. This
will further optimize the flow of ore handling from the underground
to the mill, and reduce required maintenance of the hoisting
plant
-
Construction of a larger and modern administrative building at the
shaft site, replacing the existing buildings located near the
soon-to-be decommissioned Island Gold mill
-
Construction of a new haul road from the underground portal at
Island Gold to the Magino mill, allowing ore to be transported to
the larger Magino mill for processing starting early 2025
-
Synergies: $90 million decrease in capital with the mill expansion
at Island Gold no longer required. Ore from Island Gold is expected
to be processed through the significantly larger Magino mill
starting in 2025
-
Weaker Canadian dollar: $30 million decrease in capital based on
updated USD/CAD assumption of $0.75:1 to reflect more current
exchanges rates. The initial capital estimate prepared in 2022 was
based on a USD/CAD exchange rate of $0.78:1
In addition to the initial capital savings to be
realized through the cancellation of the Island Gold mill
expansion, the Company expects to benefit from additional life of
mine capital savings with no further expansions of the Island Gold
tailings facility required. The operation is also expected to
realize approximately $25 million per year of operating cost
savings through the integration of the two operations and use of
the significantly larger and more productive Magino mill to process
Island Gold ore.
As of June 30, 2024, $381 million had been spent
on the Phase 3+ Expansion, representing 48% of the updated initial
capital estimate. The Phase 3+ Expansion remains on track for
completion in the first half of 2026 with total remaining initial
capital expected to be $415 million.
AssumptionsThe 2024 to 2026
production forecast, operating cost and capital estimates remain
based on a USD/CAD foreign exchange rate of $0.75:1 and MXN/USD
foreign exchange rate of 17:1, with the exception of PDA capital
which is based on a foreign exchange rate of 18:1. Cost assumptions
for 2025 and 2026 are based on 2024 input costs and have not been
increased to reflect potential inflation in those years. These
estimates may be updated in the future to reflect inflation beyond
what is currently forecast for 2024.
Qualified PersonsChris
Bostwick, Alamos’ Senior Vice President, Technical Services, who is
a qualified person within the meaning of National Instrument 43-101
Standards of Disclosure for Mineral Projects, has reviewed and
approved the scientific and technical information contained in this
press release.
About AlamosAlamos is a
Canadian-based intermediate gold producer with diversified
production from three operations in North America. This includes
the Young-Davidson mine and Island Gold District in northern
Ontario, Canada, and the Mulatos District in Sonora State, Mexico.
Additionally, the Company has a strong portfolio of growth
projects, including the Phase 3+ Expansion at Island Gold, and the
Lynn Lake project in Manitoba, Canada. Alamos employs more than
2,400 people and is committed to the highest standards of
sustainable development. The Company’s shares are traded on the TSX
and NYSE under the symbol “AGI”.
FOR FURTHER INFORMATION, PLEASE CONTACT:
Scott K. Parsons |
|
Senior Vice President, Corporate Development & Investor
Relations |
|
(416) 368-9932 x 5439 |
|
|
|
Khalid Elhaj |
|
Vice President, Business Development & Investor Relations |
|
(416) 368-9932 x 5427 |
|
ir@alamosgold.com |
|
|
|
The TSX and NYSE have not reviewed and do not accept
responsibility for the adequacy or accuracy of this release.
Cautionary NoteThis press
release contains or incorporates by reference “forward-looking
statements” and “forward-looking information” as defined under
applicable Canadian and U.S. securities laws. All statements, other
than statements of historical fact, which address events, results,
outcomes or developments that the Company expects to occur are, or
may be deemed to be, forward-looking statements and are generally,
but not always, identified by the use of forward-looking
terminology such as "expect", “assume”, “estimate”, “potential”,
“outlook”, “on track”, “continue”, “ongoing”, "will", “believe”,
“anticipate”, "intend", "estimate", "forecast", "budget", “target”,
“plan” or variations of such words and phrases and similar
expressions or statements that certain actions, events or results
“may", “could”, “would”, "might" or "will" be taken, occur or be
achieved or the negative connotation of such terms. Forward-looking
statements contained in this press release are based on
expectations, estimates and projections as of the date of this
press release.
Forward-looking statements in this press release
include, but may not be limited to, information, expectations and
guidance as to strategy, plans, future financial and operating
performance, such as expectations and guidance regarding: costs
(including cash costs, AISC, mine-site AISC, capital expenditures ,
exploration spending), cost structure and anticipated declining
cost profile; budgets; growth capital; sustaining capital; cash
flow; foreign exchange rates; gold and other metal price
assumptions; anticipated gold production, production rates, timing
of production, production potential and growth; returns to
stakeholders; the mine plan for and expected results from the
Puerto Del Aire (PDA) project as well as the Phase 3+ expansion at
Island Gold and timing of its progress and completion; feasibility
of, development of, and mine plan for, the Lynn Lake project and
potential growth in production resulting from the Lynn Lake
project; continued improvements at the Magino operation; expected
synergies and long-term opportunities from the integration of
Magino with Island Gold; future expansions of the Island Gold
District; upcoming catalysts, including expected timing, such as
the Burnt Timber and Linkwood study, 2024 Mineral Reserve and
Resource update, Island Gold District Life of Mine Plan and
expansion study as well as exploration updates; mining, milling and
processing and rates; mined and processed gold grades and weights;
mine life; Mineral Reserve life; planned exploration, drilling
targets, exploration potential and results; as well as any other
statements related to the Company's production forecasts and plans,
expected sustaining costs, expected improvements in cash flows and
margins, expectations of changes in capital expenditures, expansion
plans, project timelines, and expected sustainable productivity
increases, expected increases in mining activities and
corresponding cost efficiencies, cost estimates, sufficiency of
working capital for future commitments, Mineral Reserve and Mineral
Resource estimates, and other statements or information that
express management's expectations or estimates of future
performance, operational, geological or financial results.
The Company cautions that forward-looking
statements are necessarily based upon several factors and
assumptions that, while considered reasonable by management at the
time of making such statements, are inherently subject to
significant business, economic, technical, legal, political and
competitive uncertainties and contingencies. Known and unknown
factors could cause actual results to differ materially from those
projected in the forward-looking statements, and undue reliance
should not be placed on such statements and information.
Such factors and assumptions underlying the
forward-looking statements in this press release, include (without
limitation): changes to current estimates of Mineral Reserves and
Resources; changes to production estimates (which assume accuracy
of projected ore grade, mining rates, recovery timing and recovery
rate estimates and may be impacted by unscheduled maintenance,
weather issues, labour and contractor availability and other
operating or technical difficulties); operations may be exposed to
new illnesses, diseases, epidemics and pandemics (and any related
regulatory or government responses) and associated impact on the
broader market and the trading price of the Company’s shares;
provincial, state and federal orders or mandates (including with
respect to mining operations generally or auxiliary businesses or
services required for the Company’s operations) in Canada, Mexico,
the United States and Türkiye, all of which may affect many aspects
of the Company’s operations including the ability to transport
personnel to and from site, contractor and supply availability and
the ability to sell or deliver gold doré bars; fluctuations in the
price of gold or certain other commodities such as, diesel fuel,
natural gas and electricity; changes in foreign exchange rates
(particularly the Canadian dollar, U.S. dollar, Mexican peso and
Turkish Lira); the impact of inflation; changes in the Company’s
credit rating; any decision to declare a dividend; employee and
community relations; labour and contractor availability (and being
able to secure the same on favourable terms); the impact of
litigation and administrative proceedings (including but not
limited to the investment treaty claim announced on April 20, 2021
against the Republic of Türkiye by the Company’s wholly-owned
Netherlands subsidiaries, Alamos Gold Holdings Coöperatief U.A. and
Alamos Gold Holdings B.V., the application for judicial review of
the positive Decision Statement issued by the Ministry of
Environment and Climate Change Canada commenced by the Mathias
Colomb Cree Nation (MCCN) in respect of the Lynn Lake project and
the MCCN’s corresponding internal appeal of the Environment Act
Licences issued by the Province of Manitoba for the project) and
any resulting court, arbitral and/or administrative decisions;
disruptions affecting operations; availability of and increased
costs associated with mining inputs and labour; risks associated
with the startup of new mines; permitting, construction or other
delays in or with the Phase 3+ Expansion at Island Gold,
development of the PDA project, construction decisions and any
development of the Lynn Lake project, and/or the development or
updating of mine plans; changes with respect to the intended method
of accessing, mining and processing ore from Lynn Lake and the
deposit at PDA; exploration opportunities and potential in the
Mulatos District, at Young Davidson, Island Gold and/or Magino mine
not coming to fruition; inherent risks and hazards associated with
mining and mineral processing including environmental hazards,
industrial accidents, unusual or unexpected formations, pressures
and cave-ins; the risk that the Company’s mines may not perform as
planned; uncertainty with the Company's ability to secure
additional capital to execute its business plans; the speculative
nature of mineral exploration and development, including the risks
of obtaining and maintaining necessary licenses, permits and
authorizations, contests over title to properties; expropriation or
nationalization of property; political or economic developments in
Canada, Mexico, the United States, Türkiye and other jurisdictions
in which the Company may carry on business in the future; increased
costs and risks related to the potential impact of climate change;
changes in national and local government legislation, controls or
regulations (including tax and employment legislation) in
jurisdictions in which the Company does or may carry on business in
the future; the costs and timing of construction and development of
new deposits; risk of loss due to sabotage, protests and other
civil disturbances; disruptions in the maintenance or provision of
required infrastructure and information technology systems, the
impact of global liquidity and credit availability and the values
of assets and liabilities based on projected future cash flows;
risks arising from holding derivative instruments; and business
opportunities that may be pursued by the Company.
For a more detailed discussion of such risks and
other factors that may affect the Company's ability to achieve the
expectations set forth in the forward-looking statements contained
in this press release, see the Company’s latest 40-F/Annual
Information Form and Management’s Discussion and Analysis, each
under the heading “Risk Factors” available on the SEDAR+ website at
www.sedarplus.ca or on EDGAR at www.sec.gov. The foregoing should
be reviewed in conjunction with the information and risk factors
and assumptions found in this press release.
The Company disclaims any intention or
obligation to update or revise any forward-looking statements
whether as a result of new information, future events or otherwise,
except as required by applicable law.
Cautionary non-GAAP Measures and
Additional GAAP MeasuresNote that for purposes of this
section, GAAP refers to IFRS. The Company believes that investors
use certain non-GAAP and additional GAAP measures as indicators to
assess gold mining companies. They are intended to provide
additional information and should not be considered in isolation or
as a substitute for measures of performance prepared with GAAP.
“Cash flow from operating activities before
changes in non-cash working capital” is a non-GAAP performance
measure that could provide an indication of the Company’s ability
to generate cash flows from operations and is calculated by adding
back the change in non-cash working capital to “cash provided by
(used in) operating activities” as presented on the Company’s
consolidated statements of cash flows. “Cash flow per share” is
calculated by dividing “cash flow from operations before changes in
working capital” by the weighted average number of shares
outstanding for the period. “Free cash flow” is a non-GAAP
performance measure that is calculated as cash flows from
operations net of cash flows invested in mineral property, plant
and equipment and exploration and evaluation assets as presented on
the Company’s consolidated statements of cash flows and that would
provide an indication of the Company’s ability to generate cash
flows from its mineral projects. “Mine site free cash flow” is a
non-GAAP measure which includes cash flow from operating activities
at, less capital expenditures at each mine site. “Return on equity”
is defined as earnings from continuing operations divided by the
average total equity for the current and previous year. “Mining
cost per tonne of ore” and “cost per tonne of ore” are non-GAAP
performance measures that could provide an indication of the mining
and processing efficiency and effectiveness of the mine. These
measures are calculated by dividing the relevant mining and
processing costs and total costs by the tonnes of ore processed in
the period. “Cost per tonne of ore” is usually affected by
operating efficiencies and waste-to-ore ratios in the period.
“Sustaining capital” are expenditures that do not increase annual
gold ounce production at a mine site and excludes all expenditures
at the Company’s development projects. “Growth capital” are
expenditures primarily incurred at development projects and costs
related to major projects at existing operations, where these
projects will materially benefit the mine site. “Capitalized
exploration” are expenditures that meet the IFRS definition for
capitalization, and are incurred to further expand the known
Mineral Reserve and Resource at existing operations or development
projects. “Total capital expenditures per ounce produced” is a
non-GAAP term used to assess the level of capital intensity of a
project and is calculated by taking the total growth and sustaining
capital of a project divided by ounces produced life of mine.
“Total cash costs per ounce”, “all-in sustaining costs per ounce”,
“mine-site all-in sustaining costs”, and “all-in costs per ounce”
as used in this analysis are non-GAAP terms typically used by gold
mining companies to assess the level of gross margin available to
the Company by subtracting these costs from the unit price realized
during the period. These non-GAAP terms are also used to assess the
ability of a mining company to generate cash flow from operations.
There may be some variation in the method of computation of these
metrics as determined by the Company compared with other mining
companies. In this context, “total cash costs” reflects mining and
processing costs allocated from in-process and doré inventory and
associated royalties with ounces of gold sold in the period. Total
cash costs per ounce are exclusive of exploration costs. “All-in
sustaining costs per ounce” include total cash costs, exploration,
corporate and administrative, share based compensation and
sustaining capital costs. “Mine-site all-in sustaining costs”
include total cash costs, exploration, and sustaining capital costs
for the mine-site, but exclude an allocation of corporate and
administrative and share based compensation. “Adjusted net
earnings” and “adjusted earnings per share” are non-GAAP financial
measures with no standard meaning under IFRS. “Adjusted net
earnings” excludes the following from net earnings: foreign
exchange gain (loss), items included in other loss, certain
non-reoccurring items and foreign exchange gain (loss) recorded in
deferred tax expense. “Adjusted earnings per share” is calculated
by dividing “adjusted net earnings” by the weighted average number
of shares outstanding for the period. Additional GAAP measures that
are presented on the face of the Company’s consolidated statements
of comprehensive income and are not meant to be a substitute for
other subtotals or totals presented in accordance with IFRS, but
rather should be evaluated in conjunction with such IFRS measures.
This includes “Earnings from operations”, which is intended to
provide an indication of the Company’s operating performance, and
represents the amount of earnings before net finance
income/expense, foreign exchange gain/loss, other income/loss, and
income tax expense. Non-GAAP and additional GAAP measures do not
have a standardized meaning prescribed under IFRS and therefore may
not be comparable to similar measures presented by other companies.
A reconciliation of historical non-GAAP and additional GAAP
measures are available in the Company’s latest Management’s
Discussion and Analysis available online on the SEDAR+ website at
www.sedarplus.ca or on EDGAR at www.sec.gov and at
www.alamosgold.com.
Graphs accompanying this announcement are available
at:
https://www.globenewswire.com/NewsRoom/AttachmentNg/42606370-bfae-4488-a3e0-023ad84da0d6
https://www.globenewswire.com/NewsRoom/AttachmentNg/d3cba6ad-8b75-47b8-b2e6-9dafe0a06ea8
Alamos Gold (NYSE:AGI)
Gráfico Histórico do Ativo
De Nov 2024 até Dez 2024
Alamos Gold (NYSE:AGI)
Gráfico Histórico do Ativo
De Dez 2023 até Dez 2024