Bitdeer Technologies Group (NASDAQ: BTDR)
(“
Bitdeer” or the “
Company”), a
world-leading technology company for blockchain and
high-performance computing, today announced its unaudited mining
and operations updates for September 2024.
Operational Update
- Self-mined Bitcoin: 164 Bitcoins.
- Mining Rig Manufacturing and R&D:
- SEALMINER A1 mass production remains on schedule for Q4 2024
and is expected to contribute 3.4 EH/s to Bitdeer’s proprietary
hashrate. Deployment will align with the energization of the Texas
hydro-cooling conversion and Tydal, Norway phase 1 in late Q4 2024
and early Q1 2025.
- SEAL02 chip initial tape-out wafers were received from TSMC in
mid-September. Initial verification and prototype testing indicated
a 13.5 J/TH efficiency, while running at low voltage, ultra
power-saving mode.
- SEAL02 chips will be integrated into Bitdeer’s SEALMINER A2
mining machines, with mass production scheduled to commence in
November 2024.
- Design of SEAL03, Bitdeer’s third-generation chip, remains on
track to tape-out in Q4 2024 with a chip efficiency of 10
J/TH.
- HPC/AI:
- TLM Group successfully completed its feasibility assessment of
Bitdeer’s Massillon and Clarington/Hannibal sites in Ohio,
reporting largely positive results regarding their suitability for
Tier 3 HPC/AI datacenters, due to the availability of land, power,
fiber and water resources. The Company has commenced discussions
with development partners and potential end users for these
sites.
- TLM Group’s feasibility assessments of Bitdeer’s other global
sites is ongoing.
- Bitdeer AI cloud services powered by NVIDIA DGX SuperPod with
H100 systems remained near 100% average utilization for this
month.
- Launched pilot H100 capacity in Canada, further expanding
Bitdeer’s global GPU service offerings and aims to enhance the
availability and scalability of high-performance cloud computing
resources for customers, supporting AI training, inference, and
various computationally intensive applications.
- Launched AI Workflow platform, providing quick model inference
capabilities.
- Hosting:
- Client-hosted mining machine numbers remained steady from
August, with the overall hash rate increase of 0.3 EH/s due to
improved mix of newly hosted, higher-efficiency machines in Texas.
The Company expects the remaining excess capacity to be filled over
the next two quarters with new customers’ machines and Bitdeer’s
SEALMINERs for self-mining starting in September 2024 and
continuing through Q1 2025.
- Mining Datacenters:
- Construction of the Tydal, Norway, 40 MW phase 1 expansion
remains on track to be energized in December 2024.
- Rockdale, Texas, USA, 100 MW hydro-cooling conversion is
planned for phased completion between December 2024 and February
2025.
- Jigmeling, Bhutan, 500 MW construction remains on track with
the primary substation expected to be completed by Q1 2025.
Management Commentary
“We are thrilled with the successful tape-out of our SEAL02
chip,” stated Linghui Kong, Chief Business Officer of Bitdeer. “The
13.5 J/TH efficiency, indicated at low voltage in ultra
power-saving mode, is at the forefront of the industry’s efficiency
standards and showcases our R&D team’s innovation and
commitment to reshaping the ASICs market. Given recent deal
announcements in the industry, we believe Bitcoin miners are
seeking more diversified technology solutions and supply chain
flexibility. Our second-generation chip will power our SEALMINER A2
mining machines, which is scheduled to go into mass production and
be released to the market by the end of 2024.”
Mr. Kong continued, “Regarding our mining operations, our
self-mined Bitcoins remained about flat from August. Hosting
hashrate increased sequentially by 0.3 EH/s as a result of certain
new customers hosting later generation, more efficient miners with
us. Looking forward, we remain on track to refill our excess
capacity with new hosted miners as well as Bitdeer’s own SEALMINERs
for self-mining between Q4 2024 and Q1 2025.”
Production and Operations Summary
Metrics |
Sep 2024 |
Aug 2024 |
Sep 2023 |
Total hash rate under management1
(EH/s) |
17.1 |
16.8 |
21.2 |
- Proprietary hash rate |
8.6 |
8.6 |
8.7 |
• Self-mining |
8.1 |
7.8 |
7.2 |
• Cloud Hash Rate |
0.5 |
0.8 |
1.5 |
- Hosting |
8.5 |
8.2 |
12.5 |
Mining machines under management |
167,000 |
167,000 |
221,000 |
- Self-owned2 |
87,000 |
87,000 |
92,000 |
- Hosted |
78,000 |
80,000 |
129,000 |
Bitcoin mined (self-mining only) |
164 |
166 |
482 |
1 Total hash rate under management as of
September 30, 2024 across the Company’s three primary business
lines: Self-mining, Cloud Hash Rate, and Hosting.
- Self-mining refers to cryptocurrency mining
for the Company’s own account, which allows it to directly capture
the high appreciation potential of cryptocurrency.
- Cloud Hash Rate offers hash rate subscription
plans and shares mining income with customers under certain
arrangements. The Cloud Hash Rate stated above reflects the
contracted hash rate with customers at month-end. However,
throughout the month, the Cloud Hash Rate may transition to
Self-mining hash rate if customers opt to not make their monthly
electricity payments for various reasons.
- Hosting encompasses a one-stop mining machine
hosting solution including deployment, maintenance, and management
services for efficient cryptocurrency mining.
2 Self-owned mining machines are for the
Company’s self-mining business and Cloud Hash Rate business.
Infrastructure Construction Update
Rockdale, Texas - 100 MW Hydro-cooling
conversion underway:
- Demolition work has been completed.
- Cooling system design completed and waiting to begin
construction.
- First batch of cooling towers arrived at the site.
- Energization timeline to occur in phases between Q4 2024 and Q1
2025.
Tydal, Norway - 175 MW site expansion is
progressing well, with several key milestones achieved:
- Buildings and groundwork completed, along with the construction
of the transformer foundation and housing.
- Orders for transformer and electrical equipment have been
placed, with delivery and installation currently in progress.
Additionally, the procurement and delivery of containers and
hydro-cooling systems are underway, and drainage systems
construction is ongoing.
- Construction of the substation is ongoing and expected to be
completed by the end of October 2024.
- Tydal, Norway Expansion Phase 1 of 40 MW remains on track to be
energized by Q4 2024.
Massillon, Ohio - 221 MW site is also making
progress:
- Substation conceptual design is completed and long lead-time
electrical equipment for the substation has been ordered.
- Engineering, Procurement, and Construction (EPC) contractor has
been selected for the substation construction.
- Civil work is ongoing, with the majority expected to be
completed by the end of Q4 2024 or Q1 2025.
- Building design is completed, and construction is anticipated
to begin in Q4 2024, earlier than expected.
- Estimated energization timeline remains on track for
mid-to-late 2025.
Jigmeling, Bhutan - 500MW site is progressing
well, with the following key milestones achieved:
- Civil work is anticipated to be completed by the end of
September 2024. Construction of transformer and container
foundations is in progress and will be completed in phases, with
the last phase expected by the end of February 2025.
- 132kv/140MW and 220kv/360MW substation designs are completed
with construction anticipated to be ready by the end of Q1
2025.
- Orders for the procurement of transformers and electrical
equipment have been placed, with delivery and installation to be
completed in phases over the next two quarters.
- Procurement and delivery of containers and hydro-cooling
systems are in progress, with completion in phases by the end of Q1
2025.
Power Infrastructure Summary
Site / Location |
Capacity (MW) |
Status |
Timing3 |
Electrical capacity |
|
|
|
- Rockdale, Texas |
563 |
Online |
Completed |
- Knoxville, Tennessee |
86 |
Online |
Completed |
- Wenatchee, Washington |
13 |
Online |
Completed |
- Molde, Norway |
84 |
Online |
Completed |
- Tydal, Norway |
50 |
Online |
Completed |
- Gedu, Bhutan |
100 |
Online |
Completed |
Total electrical capacity |
8954 |
|
|
Pipeline capacity |
|
|
|
- Tydal, Norway Phase 1 |
40 |
In progress |
Q4 2024 |
- Tydal, Norway Phase 2 |
135 |
In progress |
Mid 2025 |
- Massillon, Ohio |
221 |
In progress |
Mid-to-late 2025 |
- Clarington, Ohio Phase 1 |
266 |
In progress |
Q3 2025 |
- Clarington, Ohio Phase 2 |
304 |
Pending approval |
Estimate 2026 |
- Jigmeling, Bhutan |
500 |
In progress |
Mid-to-late 2025 |
- Rockdale, Texas |
179 |
In planning |
Estimate 2026 |
Total pipeline capacity |
1,645 |
|
|
Total global electrical capacity |
2,540 |
|
|
3 Indicative timing. All timing references are to calendar
quarters and years.4 Figures may not add due to rounding.
Upcoming Conferences and Events
- October 24-25: Plan ₿ Forum in Lugano, Switzerland
- November 13-14: Cantor Crypto, Digital Assets & AI
Infrastructure Conference in Miami, Florida
- November 20-21: North American Blockchain Summit in Dallas,
Texas
About Bitdeer Technologies Group
Bitdeer is a world-leading technology company
for blockchain and high-performance computing. Bitdeer is committed
to providing comprehensive computing solutions for its customers.
The Company handles complex processes involved in computing such as
equipment procurement, transport logistics, datacenter design and
construction, equipment management, and daily operations. The
Company also offers advanced cloud capabilities to customers with
high demand for artificial intelligence. Headquartered in
Singapore, Bitdeer has deployed datacenters in the United States,
Norway, and Bhutan. To learn more,
visit https://ir.bitdeer.com/ or follow Bitdeer on X @
BitdeerOfficial and LinkedIn @ Bitdeer Group.
Investors and others should note that Bitdeer
may announce material information using its website and/or on its
accounts on social media platforms, including X, formerly known as
Twitter, Facebook, and LinkedIn. Therefore, Bitdeer encourages
investors and others to review the information it posts on the
social media and other communication channels listed on its
website.
Forward-Looking Statements
Statements in this press release about future expectations,
plans, and prospects, as well as any other statements regarding
matters that are not historical facts, may constitute
“forward-looking statements” within the meaning of The Private
Securities Litigation Reform Act of 1995. The words “anticipate,”
“look forward to,” “believe,” “continue,” “could,” “estimate,”
“expect,” “intend,” “may,” “plan,” “potential,” “predict,”
“project,” “should,” “target,” “will,” “would” and similar
expressions are intended to identify forward-looking statements,
although not all forward-looking statements contain these
identifying words. Actual results may differ materially from those
indicated by such forward-looking statements as a result of various
important factors, including factors discussed in the section
entitled “Risk Factors” in Bitdeer’s annual report on Form 20-F, as
well as discussions of potential risks, uncertainties, and other
important factors in Bitdeer’s subsequent filings with
the U.S. Securities and Exchange Commission. Any
forward-looking statements contained in this press release speak
only as of the date hereof. Bitdeer specifically disclaims any
obligation to update any forward-looking statement, whether due to
new information, future events, or otherwise. Readers should not
rely upon the information on this page as current or accurate after
its publication date.
For investor and media inquiries, please
contact:
Investor RelationsOrange GroupYujia
ZhaibitdeerIR@orangegroupadvisors.com
Public RelationsWachsmanBee Shinbitdeer@wachsman.com
Bitdeer Technologies (NASDAQ:BTDR)
Gráfico Histórico do Ativo
De Nov 2024 até Dez 2024
Bitdeer Technologies (NASDAQ:BTDR)
Gráfico Histórico do Ativo
De Dez 2023 até Dez 2024