Taseko Provides Construction Update on Florence Copper Project
14 Janeiro 2025 - 10:00AM
Taseko Mines Limited (TSX: TKO; NYSE American: TGB; LSE: TKO)
("Taseko" or the "Company") is pleased to update the progress at
its 100%-owned Florence Copper project in Florence, Arizona.
As of December 31, 2024, the overall project
completion was at 56% and first copper production continues to be
targeted before the end of 2025. Construction activities are
advancing on schedule and nearly 450,000 project hours have been
worked with no reportable injuries or environmental incidents.
Currently, there are approximately 290 construction and support
personnel on site.
Summary of key activities in the fourth
quarter:
- Process ponds
and surface water runoff pond construction completed
- Solvent
extraction settler and launder modules placed and welding of the
modules was commenced
- 17 production
wells were fully constructed in the quarter, for a total of 51
wells out of 90 to be drilled during the construction phase
- Development of
the main pipe corridor (from wellfield to process plant) is mostly
completed and installation of high density polyethylene piping in
the corridor is ongoing
- Field erected
process and service tank construction commenced
- Mechanical and
piping installations are underway throughout the SX/EW plant
- Erection of
structural steel for the solvent extraction pipe rack is nearing
completion and piping installation is underway
- Electrical work
commenced
- Water treatment
building was erected, and preparations made to start the
electrowinning building erection
Stuart McDonald, President & CEO of Taseko,
commented, “We are very pleased with the progress that has been
made in the first 12 months of construction. The project remains on
schedule, and construction costs remain in line with our previous
guidance. We are now less than a year from anticipated first copper
production and, in addition to construction activities, our site
management team is focussed on operational readiness, key vendor
agreements and recruiting.”
“With continued growth in US copper demand and
an increasing focus on security of supply chains for critical
materials, it is great timing to be bringing on a new source of
domestic copper supply. Florence Copper is the only greenfield
copper mine currently under construction in the USA and will soon
become the third largest copper cathode producer in the
country1.”
“We have recently been informed that our
application for the Department of Energy’s 48C(e) tax credit has
been declined. However, Taseko remains in a strong financial
position with C$330 million of available liquidity at year-end,
including the undrawn US$110 million revolving credit facility,”
concluded Mr. McDonald.
Updated photos can be found on our website at
https://tasekomines.com/properties/florence-copper/#construction-updates.
1Based on Wood Mackenzie data
For further information on Taseko, see the
Company’s website at www.tasekomines.com or contact:
Investor enquiries Brian Bergot, Vice President,
Investor Relations – 778-373-4554
Stuart McDonaldPresident and CEO
No regulatory authority has approved or
disapproved of the information contained in this news release.
Caution Regarding Forward-Looking
Information
This document contains “forward-looking
statements” that were based on Taseko’s expectations, estimates and
projections as of the dates as of which those statements were made.
Generally, these forward-looking statements can be identified by
the use of forward-looking terminology such as “outlook”,
“anticipate”, “project”, “target”, “believe”, “estimate”, “expect”,
“intend”, “should” and similar expressions.
Forward-looking statements are subject to known
and unknown risks, uncertainties and other factors that may cause
the Company’s actual results, level of activity, performance or
achievements to be materially different from those expressed or
implied by such forward-looking statements. These included but are
not limited to:
- uncertainties about the future
market price of copper and the other metals that we produce or may
seek to produce;
- changes in general economic
conditions, the financial markets, inflation and interest rates and
in the demand and market price for our input costs, such as diesel
fuel, reagents, steel, concrete, electricity and other forms of
energy, mining equipment, and fluctuations in exchange rates,
particularly with respect to the value of the U.S. dollar and
Canadian dollar, and the continued availability of capital and
financing;
- uncertainties resulting from the
war in Ukraine, and the accompanying international response
including economic sanctions levied against Russia, which has
disrupted the global economy, created increased volatility in
commodity markets (including oil and gas prices), and disrupted
international trade and financial markets, all of which have an
ongoing and uncertain effect on global economics, supply chains,
availability of materials and equipment and execution timelines for
project development;
- inherent risks associated with
mining operations, including our current mining operations at
Gibraltar, and their potential impact on our ability to achieve our
production estimates;
- uncertainties as to our ability to
control our operating costs, including inflationary cost pressures
at Gibraltar without impacting our planned copper production;
- the risk of inadequate insurance or
inability to obtain insurance to cover material mining or
operational risks;
- uncertainties related to the
feasibility study for Florence copper project (the “Florence Copper
Project” or “Florence Copper”) that provides estimates of expected
or anticipated capital and operating costs, expenditures and
economic returns from this mining project, including the impact of
inflation on the estimated costs related to the construction of the
Florence Copper Project and our other development projects;
- the risk that the results from our
operations of the Florence Copper production test facility (“PTF”)
and ongoing engineering work including updated capital and
operating costs will negatively impact our estimates for current
projected economics for commercial operations at Florence
Copper;
- uncertainties related to the
accuracy of our estimates of Mineral Reserves (as defined below),
Mineral Resources (as defined below), production rates and timing
of production, future production and future cash and total costs of
production and milling;
- the risk that we may not be able to
expand or replace reserves as our existing mineral reserves are
mined;
- the availability of, and
uncertainties relating to the development of, additional financing
and infrastructure necessary for the advancement of our development
projects, including with respect to our ability to obtain any
remaining construction financing potentially needed to move forward
with commercial operations at Florence Copper;
- our ability to comply with the
extensive governmental regulation to which our business is
subject;
- uncertainties related to our
ability to obtain necessary title, licenses and permits for our
development projects and project delays due to third party
opposition;
- our ability to deploy strategic
capital and award key contracts to assist with protecting the
Florence Copper project execution plan, mitigating inflation risk
and the potential impact of supply chain disruptions on our
construction schedule and ensuring a smooth transition into
construction;
- uncertainties related to First
Nations claims and consultation issues;
- our reliance on rail transportation
and port terminals for shipping our copper concentrate production
from Gibraltar;
- uncertainties related to unexpected
judicial or regulatory proceedings;
- changes in, and the effects of, the
laws, regulations and government policies affecting our exploration
and development activities and mining operations and mine closure
and bonding requirements;
- our dependence solely on Gibraltar
(as defined below) for revenues and operating cashflows;
- our ability to collect payments
from customers, extend existing concentrate off-take agreements or
enter into new agreements;
- environmental issues and
liabilities associated with mining including processing and stock
piling ore;
- labour strikes, work stoppages, or
other interruptions to, or difficulties in, the employment of
labour in markets in which we operate our mine, industrial
accidents, equipment failure or other events or occurrences,
including third party interference that interrupt the production of
minerals in our mine;
- environmental hazards and risks
associated with climate change, including the potential for damage
to infrastructure and stoppages of operations due to forest fires,
flooding, drought, or other natural events in the vicinity of our
operations;
- litigation risks and the inherent
uncertainty of litigation, including litigation to which Florence
Copper could be subject to;
- our actual costs of reclamation and
mine closure may exceed our current estimates of these
liabilities;
- our ability to meet the financial
reclamation security requirements for the Gibraltar mine and
Florence Project;
- the capital intensive nature of our
business both to sustain current mining operations and to develop
any new projects, including Florence Copper;
- our reliance upon key management
and operating personnel;
- the competitive environment in
which we operate;
- the effects of forward selling
instruments to protect against fluctuations in copper prices,
foreign exchange, interest rates or input costs such as fuel;
and
- the risk of changes in accounting
policies and methods we use to report our financial condition,
including uncertainties associated with critical accounting
assumptions and estimates; and Management Discussion and Analysis
(“MD&A”), quarterly reports and material change reports filed
with and furnished to securities regulators, and those risks which
are discussed under the heading “Risk Factors”.
For further information on Taseko, investors
should review the Company’s annual Form 40-F filing with the United
States Securities and Exchange Commission www.sec.gov and home
jurisdiction filings that are available at www.sedarplus.ca,
including the “Risk Factors” included in our Annual Information
Form.
Taseko Mines (LSE:TKO)
Gráfico Histórico do Ativo
De Dez 2024 até Jan 2025
Taseko Mines (LSE:TKO)
Gráfico Histórico do Ativo
De Jan 2024 até Jan 2025