Taseko Mines Limited (TSX: TKO; NYSE American: TGB; LSE: TKO)
("Taseko" or the "Company") reports full year 2024 Adjusted EBITDA*
of $224 million and Earnings from mining operations before
depletion and amortization and non-recurring items* of $244
million. Revenues for 2024 were $608 million from the sale of 108
million pounds of copper and 1.4 million pounds of molybdenum. For
the year, a Net loss of $13 million ($0.05 loss per share) was
recorded and Adjusted net income* was $57 million ($0.19 per
share).
For the fourth quarter, Adjusted EBITDA* was $56
million, Earnings from mining operations before depletion and
amortization and non-recurring items* was $59 million and Cash
flows from operations was $73 million. A Net loss of $21 million
($0.07 loss per share) was recorded and Adjusted net income* was
$10 million ($0.03 per share).
Gibraltar produced 29 million pounds of copper
and 578 thousand pounds of molybdenum in the fourth quarter at
Total operating costs (C1) of $2.42 per pound of copper produced.
Mill throughput averaged 89,600 tons per day, which is the highest
ever achieved for a quarter at Gibraltar.
For the year, copper production was 106 million
pounds, in line with the revised production guidance, and
molybdenum production was 1.4 million pounds. Higher than normal
scheduled downtime in both concentrators and an 18-day labour
strike impacted annual production by approximately 15 million
pounds in 2024. Copper grades in 2024 averaged 0.23% and Total
operating costs (C1) were US$2.66 per pound produced.
Copper production in 2025 is expected to
increase to 120 to 130 million pounds as mill operating time
returns to normal levels and the restart of the SX/EW plant adds
additional capacity. However, production will be weighted to the
back half of the year and the first quarter will be the lowest
production quarter as lower grade ore stockpiles will be used to
supplement mined ore from a new pushback in the Connector pit.
At Florence Copper, construction is advancing on
schedule, including all critical path items, and the overall
project completion was over 60% as of the end of January. A total
of 58 out of the 90 production wells to be drilled during the
construction phase have now been completed. In the SX/EW area,
construction activities are focussed on mechanical, piping and
electrical installations. The erection of the electrowinning
building has commenced, and construction of the tank farm is well
advanced. Work in the pipe corridor continues with lining and pipe
installation nearly complete.
Stuart McDonald, President and CEO of Taseko,
commented, “We had a strong finish to the year at Gibraltar and,
with both concentrators operating well, the mine achieved a new
record for quarterly mill throughput. With stable milling
operations expected in 2025 we expect a significant improvement in
annual production of copper and molybdenum, although we will see
lower head grades in the first part of the year during a new
pushback in the Connector pit. The refurbishment of the SX/EW plant
is progressing on schedule and first cathode production at
Gibraltar is anticipated in the second quarter.”
Mr. McDonald continued, “We remain pleased with
the construction progress at Florence. Four drill rigs are
advancing wellfield drilling which is scheduled for completion in
the second quarter. Our construction workforce is currently at
approximately 360 workers, and will reach peak manpower levels this
quarter. First copper production continues to be targeted before
the end of the year.”
“The Company remains in a solid financial
position with a year end cash balance of $173 million and available
liquidity of approximately $331 million, including our undrawn
credit facility. Recent trends in global markets are benefitting
Gibraltar as copper prices have risen 8% since the start of the
year, and the Canadian dollar has weakened relative to the US
dollar. Gibraltar’s cost structure will also benefit this year from
copper offtake contracts at average TC/RCs of zero, higher
by-product credits from increased molybdenum production, and lower
oil prices. Our copper price protection at a minimum price of
US$4.00 per pound for all of 2025, provides additional downside
protection. We’re very excited about the year ahead as we’re now
less than 12 months from first copper production at Florence
Copper, which is going to dramatically improve our business
outlook,” added Mr. McDonald.
“In the longer term, the Yellowhead project
represents another major growth opportunity for our North American
copper business. We’re advancing project permitting this year and
also publishing a new technical report, with updated costing and
metal prices, and incorporating the new Canadian tax credits
available for copper mine development,” concluded Mr. McDonald.
2024 Annual Review
- Earnings from mining operations
before depletion, amortization and non-recurring items* for the
year was $243.6 million, Adjusted EBITDA* was $224.0 million, and
cash flow from operations was $232.6 million;
- GAAP net loss for the year totalled
$13.4 million ($0.05 loss per share) and Adjusted net income* was
$56.9 million ($0.19 per share);
- Total operating costs (C1)* for the
year were US$2.66 per pound produced and the average realized
copper price was US$4.17 per pound;
- The Gibraltar mine produced 105.6
million pounds of copper and 1.4 million pounds of molybdenum in
2024. Copper head grades were 0.23% and mill recoveries averaged
78.5% for the year;
- Gibraltar sold 108.0 million pounds
of copper for the year (100% basis), resulting in $608.1 million of
revenue to Taseko;
- In January 2024, the Company
commenced construction of the commercial production facility at its
wholly-owned Florence Copper project. Construction activities are
advancing on schedule and the project is approximately 56% complete
at year end. First copper is expected to be produced in the fourth
quarter of 2025;
- In March 2024, Taseko acquired the
remaining 12.5% interest in Gibraltar, increasing its effective
interest in the mine from 87.5% to 100%. An initial payment of $5
million was paid on closing with remaining consideration to be paid
in annual instalments commencing in March 2026, with payments based
on the average LME copper price subject to a cap tied to a
percentage of Gibraltar’s cashflow; and
- In April 2024, the
Company completed an offering of US$500 million aggregate
principal amount of 8.25% Senior Secured Notes due 2030. A portion
of the proceeds was used to redeem the outstanding US$400 million
Senior Secured Notes due 2026 and pay related transaction costs
with the remaining proceeds available for capital expenditures,
working capital, and general corporate purposes.
*Non-GAAP performance measure. See end of news release.
Fourth Quarter Review
- Fourth quarter earnings from mining
operations before depletion, amortization and non-recurring items*
was $59.4 million, Adjusted EBITDA* was $55.6 million, and cash
flow from operations was $73.3 million;
- GAAP net loss for the quarter
totalled $21.2 million ($0.07 loss per share) and Adjusted net
income* was $10.5 million ($0.03 per share);
- Gibraltar produced 28.6 million
pounds of copper for the quarter. Average head grades were 0.22%
and copper recoveries were 78.2% for the quarter;
- Gibraltar sold 27.4 million pounds
of copper in the quarter (100% basis) at an average realized copper
price of US$4.13 per pound;
- Total operating costs (C1)* for the
quarter were US$2.42 per pound produced;
- At Florence, seventeen production
wells were constructed in the quarter, bringing the total completed
wells to 51 out of the 90 planned. Development of the main pipe
corridor from the wellfield to the processing plant are mostly
completed. Electrical, mechanical and piping installations are
underway for the solvent extraction and electrowinning (“SX/EW”)
plant and other site infrastructure;
- In November 2024, the Company
entered into an amendment to its revolving credit facility,
extending the maturity date to November 2027, and increasing the
facility amount to US$110 million from US$80 million. No amounts
are currently drawn against the revolving credit facility;
- In December 2024, the Company
closed a transaction with Osisko Gold Royalties, amending the
Gibraltar silver stream agreement and increasing the attributable
silver percentage from 87.5% to 100% in exchange for an additional
cash payment of US$12.7 million; and
- The Company had a cash balance of
$173 million and approximately $331 million of available liquidity
at December 31, 2024 including its undrawn corporate credit
facility.
*Non-GAAP performance measure. See end of news release.
Highlights
Operating Data
(Gibraltar - 100% basis) |
Three months endedDecember
31, |
Year endedDecember 31, |
|
2024 |
2023 |
Change |
|
2024 |
2023 |
Change |
|
Tons mined (millions) |
24.0 |
24.1 |
(0.1 |
) |
88.3 |
88.1 |
0.2 |
|
Tons milled (millions) |
8.3 |
7.6 |
0.7 |
|
29.3 |
30.0 |
(0.7 |
) |
Production (million pounds
Cu) |
28.6 |
34.2 |
(5.6 |
) |
105.6 |
122.6 |
(17.0 |
) |
Sales
(million pounds Cu) |
27.4 |
35.9 |
(8.5 |
) |
108.0 |
120.7 |
(12.7 |
) |
Financial
Data |
Three months endedDecember
31, |
Year endedDecember 31, |
(Cdn$ thousands, except per share amounts) |
2024 |
|
2023 |
Change |
|
2024 |
|
2023 |
Change |
|
Revenues |
167,799 |
|
153,694 |
14,105 |
|
608,093 |
|
524,972 |
83,121 |
|
Cash flows from
operations |
73,292 |
|
62,835 |
10,457 |
|
232,615 |
|
151,092 |
81,523 |
|
Net (loss) income |
(21,207 |
) |
38,076 |
(59,283 |
) |
(13,444 |
) |
82,726 |
(96,170 |
) |
Per share - basic (“EPS”) |
(0.07 |
) |
0.13 |
(0.20 |
) |
(0.05 |
) |
0.29 |
(0.34 |
) |
Earnings from mining operations
before depletion, amortization and non-recurring items* |
59,405 |
|
73,106 |
(13,701 |
) |
243,646 |
|
207,354 |
36,292 |
|
Adjusted EBITDA* |
55,602 |
|
69,107 |
(13,505 |
) |
223,991 |
|
190,079 |
33,912 |
|
Adjusted net income* |
10,468 |
|
24,061 |
(13,593 |
) |
56,927 |
|
44,431 |
12,496 |
|
Per share - basic (“Adjusted
EPS”)* |
0.03 |
|
0.08 |
(0.05 |
) |
0.19 |
|
0.15 |
0.04 |
|
|
|
|
|
|
|
|
|
|
|
|
Effective as of March 25, 2024, the Company
increased its ownership in Gibraltar from 87.5% to 100%. As a
result, the financial results reported in this MD&A include
100% of Gibraltar’s income and expenses for the period March 25,
2024, to December 31, 2024 (87.5% for the period March 16, 2023 to
March 24, 2024, and 75% prior to March 15, 2023).
The Company finalized the accounting for the
acquisition of the remaining 50% interest in Cariboo from Dowa
Metals & Mining Co., Ltd. (“Dowa”) and Furukawa Co., Ltd.
(“Furukawa”) and the related 12.5% interest in Gibraltar in the
fourth quarter of 2024. For more information on the Company’s
acquisition of Cariboo, please refer to the Financial Statements –
Note 3.
*Non-GAAP performance measure. See end of news release.
Review of Operations
Gibraltar mine
Operating data (100% basis) |
Q4 2024 |
Q3 2024 |
Q2 2024 |
Q1 2024 |
Q4 2023 |
YE 2024 |
YE 2023 |
Tons mined (millions) |
|
23.9 |
|
|
23.2 |
|
|
18.4 |
|
|
22.8 |
|
|
24.1 |
|
|
88.3 |
|
|
88.1 |
|
Tons milled (millions) |
|
8.3 |
|
|
7.6 |
|
|
5.7 |
|
|
7.7 |
|
|
7.6 |
|
|
29.3 |
|
|
30.0 |
|
Strip ratio |
|
1.9 |
|
|
1.2 |
|
|
1.6 |
|
|
1.7 |
|
|
1.5 |
|
|
1.6 |
|
|
1.3 |
|
Site operating cost per ton
milled (Cdn$)* |
$12.18 |
|
$14.23 |
|
$13.93 |
|
$11.73 |
|
$9.72 |
|
$12.93 |
|
$12.16 |
|
Copper
concentrate |
|
|
|
|
|
|
|
Head grade (%) |
|
0.22 |
|
|
0.23 |
|
|
0.23 |
|
|
0.24 |
|
|
0.27 |
|
|
0.23 |
|
|
0.25 |
|
Copper recovery (%) |
|
78.2 |
|
|
78.9 |
|
|
77.7 |
|
|
79.0 |
|
|
82.2 |
|
|
78.5 |
|
|
82.6 |
|
Production (million pounds Cu) |
|
28.6 |
|
|
27.1 |
|
|
20.2 |
|
|
29.7 |
|
|
34.2 |
|
|
105.6 |
|
|
122.6 |
|
Sales (million pounds Cu) |
|
27.4 |
|
|
26.3 |
|
|
22.6 |
|
|
31.7 |
|
|
35.9 |
|
|
108.0 |
|
|
120.7 |
|
Inventory (million pounds Cu) |
|
4.1 |
|
|
2.9 |
|
|
2.3 |
|
|
4.9 |
|
|
6.9 |
|
|
4.1 |
|
|
6.9 |
|
Molybdenum
concentrate |
|
|
|
|
|
|
|
Production (thousand pounds Mo) |
|
578 |
|
|
421 |
|
|
185 |
|
|
247 |
|
|
369 |
|
|
1,432 |
|
|
1,202 |
|
Sales (thousand pounds Mo) |
|
607 |
|
|
348 |
|
|
221 |
|
|
258 |
|
|
364 |
|
|
1,434 |
|
|
1,190 |
|
Per unit data (US$ per
pound produced)* |
|
|
|
|
|
|
|
Site operating costs* |
$2.52 |
|
$2.91 |
|
$2.88 |
|
$2.21 |
|
$1.59 |
|
$2.61 |
|
$2.19 |
|
By-product credits* |
|
(0.42 |
) |
|
(0.25 |
) |
|
(0.26 |
) |
|
(0.17 |
) |
|
(0.13 |
) |
|
(0.28 |
) |
|
(0.20 |
) |
Site operating costs, net of by-productcredits* |
$2.10 |
|
$2.66 |
|
$2.62 |
|
$2.04 |
|
$1.46 |
|
$2.33 |
|
$1.99 |
|
Off-property costs |
|
0.32 |
|
|
0.26 |
|
|
0.37 |
|
|
0.42 |
|
|
0.45 |
|
|
0.33 |
|
|
0.38 |
|
Total
operating costs (C1)* |
$2.42 |
|
$2.92 |
|
$2.99 |
|
$2.46 |
|
$1.91 |
|
$2.66 |
|
$2.37 |
|
Operations Analysis
Full Year Results
Gibraltar produced 105.6 million pounds of
copper for the year compared to 122.6 million pounds of copper in
2023 with lower mill running time being the primary factor for the
decreased production.
Both concentrators were down for 18 days in June
when the unionized workforce went on strike. The strike overlapped
with planned downtime in Concentrator #1 for its primary crusher
move as well as major maintenance on its SAG, which extended the
downtime to approximately seven weeks. Concentrator #2 was also
down in January 2024 for a planned major component
replacement on its ball mill. The reduced operating hours in
2024 resulted in approximately 15 million fewer copper pounds being
produced compared to normal milling rates at similar grades and
recoveries.
*Non-GAAP performance measure. See end of news release.
Operations Analysis - Continued
A total of 88.3 million tons were mined in the
year consistent with the 88.1 million tons mined in 2023. The strip
ratio increased to 1.6 from 1.3 as mining operations transitioned
into the Connector pit in 2024. The Gibraltar pit, which was the
main source of ore in 2023, had a lower strip ratio. Ore stockpiles
also increased by 5.0 million tons in 2024, comprised primarily of
oxide ore from the upper benches of the Connector pit. The oxide
ore stockpiled will allow the restart of the Gibraltar SX/EW plant
in the second quarter of 2025.
Total site costs* at Gibraltar of $413.9 million
(100% basis) were $16.9 million lower than 2023 due to lower input
costs such as diesel and the impact of the 18-day labour strike in
June 2024 which reduced site operating costs in the second quarter
of 2024.
Transportation costs for the year ended December
31, 2024 increased by $5.4 million over the same prior period, due
to higher costs for rail, ocean freight and port handling costs,
and trucking related costs.
Molybdenum production was 1.4 million pounds in
the year compared to 1.2 million pounds in the prior year.
Molybdenum prices weakened in 2024 with an average molybdenum price
of US$21.30 per pound, a decrease of 12% compared to the 2023
average price of US$24.19 per pound.
Off-property costs per pound produced* were
US$0.33 for the year, which is US$0.05 lower than the prior year
primarily due to a decrease in realized treatment and refining
charges (TC/RC) rates due to the tightening smelter market.
Total operating costs per pound produced (C1)* was US$2.66 for
the year, compared to US$2.37 in the prior year and the increase
was substantially attributed to lower production and less
capitalized stripping costs as shown in the bridge graph below:
https://www.globenewswire.com/NewsRoom/AttachmentNg/223b49e5-9f9a-47ca-b30d-2b225d76603f
Fourth Quarter Results
Gibraltar produced 28.6 million pounds of copper
in the quarter. Copper head grades were 0.22% and copper recoveries
in the fourth quarter were 78%, in line with recent quarters. Mill
throughput was 8.3 million tons, consistently above nameplate
capacity throughout the quarter and benefitting from the softer
characteristics of the ore feed.
A total of 24.0 million tons were mined in the
fourth quarter at an average strip ratio of 1.9 and the majority of
ore and waste mining occurred in the Connector pit.
Total site costs* at Gibraltar of $102.5 million
(100% basis) were lower than the third quarter of 2024, with the
prior quarter including repairs and maintenance costs associated
with a large maintenance project on one of the shovels.
*Non-GAAP performance measure. See end of news release.
Operations Analysis - Continued
Molybdenum production was 578 thousand pounds in
the fourth quarter. The 57% increase in quarter-over-quarter
production is primarily due to higher molybdenum grade in the
Connector pit ore. At an average molybdenum price of US$21.71 per
pound, molybdenum generated a meaningful by-product credit per
pound of copper produced of US$0.42 in the fourth quarter.
Off-property costs per pound produced* were
US$0.32 for the fourth quarter, in line with average costs for the
year.
Gibraltar Outlook
With the major project and related mill
maintenance work completed in 2024, increased mill availability and
higher throughput is expected to be the primary driver of improved
copper production in 2025. Refurbishment of Gibraltar’s SX/EW
plant, which has been idle since 2015, is underway and the plant is
expected to start producing copper cathode in the second quarter.
Total copper production for the year is expected to be in the range
of 120 to 130 million pounds.
Mining activities have transitioned to the
Connector pit, which will be the main source of mill feed going
forward. A new pushback in the Connector pit has been initiated in
early 2025 resulting in a higher strip ratio in the first quarter.
Lower grade ore stockpiles will be utilized to supplement mined ore
during this period, and as a result 2025 copper production will be
weighted to the second half of the year.
Molybdenum production is forecast to increase in
2025 as molybdenum head grades are expected to be notably higher in
the Connector pit ore compared to the Gibraltar pit ore.
The Company has previously entered into offtake
contracts for Gibraltar concentrate production in 2025 and 2026,
which will result in significantly lower treatment and refining
costs (“TC/RCs”). In 2024, TC/RCs accounted for approximately
US$0.09 per pound of off-property costs, and with the new offtake
contracts, the Company expects average TC/RCs to reduce to zero in
2025 and 2026.
The Company benefits from a strengthening of the
US dollar relative to the Canadian dollar as our sales contracts
are priced in US dollars whereas our Gibraltar mine costs are
primarily incurred in Canadian dollars.
The Company also has a prudent hedging program
in place to protect a minimum copper price during the Florence
construction period. Currently, the Company has copper collar
contracts that secure a minimum copper price of US$4.00 per pound
for 108 million pounds of copper for 2025. The copper collar
contracts also have ceiling prices between US$5.00 and US$5.40 per
pound (refer to the section “Hedging Strategy” for details).
Florence Copper
The Company has all the key permits in place for
the commercial production facility at Florence Copper and
construction of the Florence Copper commercial production facility
continues to advance on schedule. Nearly 450,000 project hours have
been worked with no reportable injuries or environmental incidents.
The Company has a fixed-price contract with the general contractor
for construction of the SX/EW plant and associated surface
infrastructure.
A total of 51 production wells out of a total of
90 new wells had been completed as of December 31, 2024. Process
ponds and surface water runoff pond construction are complete, and
development of the main pipe corridor is substantially complete
with the installation of high density polyethylene piping in the
corridor ongoing. Mechanical and piping installations are underway
throughout the SX/EW plant, erection of structural steel for
solvent extraction pipe rack is nearing completion, and the
electrical work has commenced.
Florence Copper - Continued
Florence Copper Quarterly Capital Spend
|
Three months ended |
Year ended |
(US$ in
thousands) |
December 31, 2024 |
December 31, 2024 |
Site and PTF operations |
6,007 |
19,512 |
Commercial facility
construction costs |
57,647 |
154,970 |
Other
capital costs |
- |
28,943 |
Total Florence project expenditures |
63,654 |
203,425 |
Construction costs in the fourth quarter were
US$57.6 million, and US$155.0 million has been incurred for the
year ended December 31, 2024. Other capital costs of US$28.9
million include final payments for delivery of long-lead equipment
that was ordered in 2022, and the construction of an evaporation
pond to provide additional water management flexibility.
Construction of this evaporation pond was completed in the third
quarter of 2024.
The Company has closed several Florence project
level financings to fund initial commercial facility construction
costs. In October the Company received the fourth deposit of US$10
million from the US$50 million copper stream transaction with
Mitsui & Co. (U.S.A.) Inc. (“Mitsui”). The final deposit of
US$10 million was received in January 2025.
Remaining project construction costs are
expected to be funded with the Company’s available liquidity and
cashflow from its 100% ownership interest in Gibraltar. The Company
also has in place an undrawn corporate revolving credit facility
for US$110 million.
The Company has a technical report entitled “NI
43-101 Technical Report Florence Copper Project, Pinal County,
Arizona” dated March 30, 2023 (the “2023 Technical Report”) on
SEDAR+. The 2023 Technical Report was prepared in accordance with
NI 43-101 and incorporated the results of testwork from the
Production Test Facility (“PTF”) as well as updated capital and
operating costs (Q3 2022 basis) for the commercial production
facility.
Project highlights based on the 2023 Technical
Report:
- Net present value of US$930 million
(at $US 3.75 copper price, 8% after-tax discount rate)
- Internal rate of return of 47%
(after-tax)
- Payback period of 2.6 years
- Operating costs (C1) of US$1.11 per
pound of copper
- Annual production capacity of 85
million pounds of LME grade A cathode copper
- 22 year mine life
- Total life of mine production of
1.5 billion pounds of copper
- Remaining initial capital cost of
US$232 million (Q3 2022 basis)
Based on the 2023 Technical report, the
estimated remaining construction costs for the commercial facility
were US$232 million (basis Q3 2022), and management expects that
total costs will be within 10% to 15% of that estimate. Florence
Copper remains on track for first copper production in late
2025.
Long-term Growth Strategy
Taseko’s strategy has been to grow the Company
by acquiring and developing a pipeline of projects focused on
copper in North America. We continue to believe this will generate
long-term returns for shareholders. Our other development projects
are located in British Columbia, Canada.
Yellowhead Copper Project
The Yellowhead Project (“Yellowhead”) is
expected to produce 4.4 billion pounds of copper over a 25-year
mine life at an average C1* cost, net of by-product credit, of
US$1.67 per pound. During the first 5 years of operation,
Yellowhead will produce an average of 200 million pounds of copper
per year at an average C1* cost, net of by-product credit, of
US$1.43 per pound. The Yellowhead project also contains valuable
precious metal by-products with 440,000 ounces of gold and 19
million ounces of silver production over the life of mine.
The economic analysis in the 2020 Technical
Report was prepared using long-term copper price of US$3.10 per
pound, a gold price of US$1,350 per ounce, and silver price of
US$18 per ounce. This report entitled “Technical Report on the
Mineral Reserve Update at the Yellowhead Copper Project, British
Columbia, Canada” was published on January 16, 2020, under the
supervision of Richard Weymark, P. Eng., MBA, Vice President,
Engineering for Taseko and a Qualified Person as defined by NI
43-101. Taseko plans to publish a new technical report in 2025
using updated long-term metal price assumptions, updated project
costing, and incorporating the new Canadian tax credits available
for copper mine development.
The Company is ready to enter the environmental
assessment process and plans to submit an Initial Project
Description to formally commence this process with the regulators
in the second quarter this year. The Company is also focusing
discussions with the regulators on developing a workplan to
streamline the overall permitting process. Taseko opened a
project office in 2024 to support ongoing engagement with local
communities including First Nations.
New Prosperity Gold-Copper Project
In late 2019, the Tŝilhqot’in Nation, as
represented by Tŝilhqot’in National Government, and Taseko Mines
Limited entered into a confidential dialogue, with the involvement
of the Province of British Columbia, seeking a long-term resolution
of the conflict regarding Taseko’s proposed copper-gold mine
previously known as New Prosperity, acknowledging Taseko’s
commercial interests and the Tŝilhqot’in Nation’s opposition to the
project.
This dialogue has been supported by the parties’
agreement, beginning December 2019, to a series of standstill
agreements on certain outstanding litigation and regulatory matters
relating to Taseko’s tenures and the area in the vicinity of Teztan
Biny (Fish Lake).
The dialogue process has made meaningful
progress in recent months and is close to completion. The
Tŝilhqot’in Nation and Taseko acknowledge the constructive nature
of discussions, and the opportunity to conclude a long-term and
mutually acceptable resolution of the conflict that also makes an
important contribution to the goals of reconciliation in
Canada.
Aley Niobium Project
The converter pilot test is ongoing to provide
additional process data to support the design of commercial process
facilities and final product samples to support product marketing
initiatives. The Company has also initiated a scoping study to
investigate the potential production of niobium oxide at Aley to
supply the growing market for niobium-based batteries.
Conference Call and WebcastThe Company will host a
telephone conference call and live webcast on Thursday, February
20, 2025, at 11:00 a.m. Eastern Time (8:00 a.m. Pacific) to discuss
these results. After opening remarks by management, there
will be a question-and-answer session open to analysts and
investors.Participants can join by conference call dial-in or
webcast:Conference Call Dial-In
- Participants can dial in to the conference call; however,
pre-registration is required
- To register, visit https://bit.ly/Q42024_Dialin
- Once registered, an email will be sent, including dial-in
details and a unique access code required to join the live
call
- Please ensure you have registered at least 15 minutes prior to
the conference call start time
Webcast
- A live webcast of the conference call can be accessed at Taseko
Mines | Events
- The webcast will be archived for later playback until March 13,
2025 at Taseko Mines | Events
|
For further information on Taseko, please see
the Company's website at www.tasekomines.com or contact:
Brian Bergot, Vice President, Investor Relations
– 778-373-4554, toll free 1-800-667-2114
Stuart McDonaldPresident & CEO
No regulatory authority has approved or
disapproved of the information in this news release.
Non-GAAP Performance
Measures
This document includes certain non-GAAP
performance measures that do not have a standardized meaning
prescribed by IFRS. These measures may differ from those used by,
and may not be comparable to such measures as reported by, other
issuers. The Company believes that these measures are commonly used
by certain investors, in conjunction with conventional IFRS
measures, to enhance their understanding of the Company’s
performance. These measures have been derived from the Company’s
financial statements and applied on a consistent basis. The
following tables below provide a reconciliation of these non-GAAP
measures to the most directly comparable IFRS Accounting Standards
measure.
Total operating costs and site operating costs,
net of by-product credits
Total costs of sales include all costs absorbed
into inventory, as well as transportation costs and insurance
recoverable. Site operating costs are calculated by removing net
changes in inventory, depletion and amortization, insurance
recoverable, and transportation costs from cost of sales. Site
operating costs, net of by-product credits is calculated by
subtracting by-product credits from the site operating costs. Site
operating costs, net of by-product credits per pound are calculated
by dividing the aggregate of the applicable costs by copper pounds
produced. Total operating costs per pound is the sum of site
operating costs, net of by-product credits and off-property costs
divided by the copper pounds produced. By-product credits are
calculated based on actual sales of molybdenum (net of treatment
costs) and silver during the period divided by the total pounds of
copper produced during the period. These measures are calculated on
a consistent basis for the periods presented.
(Cdn$ in thousands, unless otherwise indicated) |
2024Q4 |
2024Q3 |
2024Q2 |
2024Q11 |
2024YE1 |
Cost of sales |
134,940 |
|
124,833 |
|
108,637 |
|
122,528 |
|
490,938 |
|
Less: |
|
|
|
|
|
Depletion and amortization |
(24,641 |
) |
(20,466 |
) |
(13,721 |
) |
(15,024 |
) |
(73,852 |
) |
Net change in inventories of finished goods |
4,064 |
|
2,938 |
|
(10,462 |
) |
(20,392 |
) |
(23,852 |
) |
Net change in inventories of ore stockpiles |
(3,698 |
) |
9,089 |
|
1,758 |
|
2,719 |
|
9,868 |
|
Transportation costs |
(10,170 |
) |
(8,682 |
) |
(6,408 |
) |
(10,153 |
) |
(35,413 |
) |
Site operating costs |
100,495 |
|
107,712 |
|
79,804 |
|
79,678 |
|
367,689 |
|
Less by-product credits: |
|
|
|
|
|
Molybdenum, net of treatment costs |
(16,507 |
) |
(8,962 |
) |
(7,071 |
) |
(6,112 |
) |
(38,652 |
) |
Silver, excluding amortization of deferred revenue |
(139 |
) |
(241 |
) |
(144 |
) |
(137 |
) |
(661 |
) |
Site operating costs, net of by-product credits |
83,849 |
|
98,509 |
|
72,589 |
|
73,429 |
|
328,376 |
|
Total copper produced (thousand pounds) |
28,595 |
|
27,101 |
|
20,225 |
|
26,694 |
|
102,615 |
|
Total costs per pound produced |
2.94 |
|
3.63 |
|
3.59 |
|
2.75 |
|
3.20 |
|
Average exchange rate for the period (CAD/USD) |
1.40 |
|
1.36 |
|
1.37 |
|
1.35 |
|
1.37 |
|
Site operating costs, net of by-product credits(US$ per pound) |
2.10 |
|
2.66 |
|
2.62 |
|
2.04 |
|
2.33 |
|
Site operating costs, net of by-product credits |
83,849 |
|
98,509 |
|
72,589 |
|
73,429 |
|
328,376 |
|
Add off-property costs: |
|
|
|
|
|
Treatment and refining costs |
2,435 |
|
816 |
|
3,941 |
|
4,816 |
|
12,008 |
|
Transportation costs |
10,170 |
|
8,682 |
|
6,408 |
|
10,153 |
|
35,413 |
|
Total operating costs |
96,454 |
|
108,007 |
|
82,938 |
|
88,398 |
|
375,797 |
|
Total operating costs (C1) (US$ per pound) |
2.42 |
|
2.92 |
|
2.99 |
|
2.46 |
|
2.66 |
|
1 Q1 2024 includes the impact from the March 25,
2024 acquisition of Cariboo from Dowa and Furukawa, which increased
the Company’s Gibraltar mine ownership from 87.5% to 100%.
Non-GAAP Performance Measures -
Continued
Total operating costs and site operating costs,
net of by-product credits (Continued)
(Cdn$ in thousands, unless otherwise indicated) |
2023Q4 |
2023Q3 |
2023Q2 |
2023Q11 |
2023YE1 |
Cost of sales |
93,914 |
|
94,383 |
|
99,854 |
|
86,407 |
|
374,558 |
|
Less: |
|
|
|
|
|
Depletion and amortization |
(13,326 |
) |
(15,993 |
) |
(15,594 |
) |
(12,027 |
) |
(56,940 |
) |
Net change in inventories of finished goods |
(1,678 |
) |
4,267 |
|
3,356 |
|
(399 |
) |
5,546 |
|
Net change in inventories of ore stockpiles |
(3,771 |
) |
12,172 |
|
2,724 |
|
5,561 |
|
16,686 |
|
Transportation costs |
(10,294 |
) |
(7,681 |
) |
(6,966 |
) |
(5,104 |
) |
(30,045 |
) |
Site operating costs |
64,845 |
|
87,148 |
|
83,374 |
|
74,438 |
|
309,805 |
|
Oxide ore stockpile reclassification from capitalized
stripping |
- |
|
- |
|
(3,183 |
) |
3,183 |
|
- |
|
Less by-product credits: |
|
|
|
|
|
Molybdenum, net of treatment costs |
(5,441 |
) |
(9,900 |
) |
(4,018 |
) |
(9,208 |
) |
(28,567 |
) |
Silver, excluding amortization of deferred revenue |
124 |
|
290 |
|
(103 |
) |
(160 |
) |
151 |
|
Site operating costs, net of by-product credits |
59,528 |
|
77,538 |
|
76,070 |
|
68,253 |
|
281,389 |
|
Total copper produced (thousand pounds) |
29,883 |
|
30,978 |
|
24,640 |
|
19,491 |
|
104,992 |
|
Total costs per pound produced |
1.99 |
|
2.50 |
|
3.09 |
|
3.50 |
|
2.68 |
|
Average exchange rate for the period (CAD/USD) |
1.36 |
|
1.34 |
|
1.34 |
|
1.35 |
|
1.35 |
|
Site operating costs, net of by-product credits(US$ per pound) |
1.46 |
|
1.87 |
|
2.30 |
|
2.59 |
|
1.99 |
|
Site operating costs, net of by-product credits |
59,528 |
|
77,538 |
|
76,070 |
|
68,253 |
|
281,389 |
|
Add off-property costs: |
|
|
|
|
|
Treatment and refining costs |
7,885 |
|
6,123 |
|
4,986 |
|
4,142 |
|
23,136 |
|
Transportation costs |
10,294 |
|
7,681 |
|
6,966 |
|
5,104 |
|
30,045 |
|
Total operating costs |
77,707 |
|
91,342 |
|
88,022 |
|
77,499 |
|
334,570 |
|
Total operating costs (C1) (US$ per pound) |
1.91 |
|
2.20 |
|
2.66 |
|
2.94 |
|
2.37 |
|
1 Q1 2023 includes the impact from the March 15,
2023 acquisition of Cariboo from Sojitz, which increased the
Company’s Gibraltar mine ownership from 75% to 87.5%.
Non-GAAP Performance Measures -
Continued
Total Site Costs
Total site costs are comprised of the site
operating costs charged to cost of sales as well as mining costs
capitalized to property, plant and equipment in the period. This
measure is intended to capture Taseko’s share of the total site
operating costs incurred in the quarter at Gibraltar calculated on
a consistent basis for the periods presented.
(Cdn$ in thousands, unless otherwise indicated) –100% basis (except
for Q1 2024) |
2024Q4 |
2024Q3 |
2024Q2 |
2024Q11 |
2024YE1 |
Site operating costs |
100,495 |
107,712 |
79,804 |
79,678 |
367,689 |
Add: |
|
|
|
|
|
Capitalized stripping costs |
1,981 |
3,631 |
10,732 |
16,152 |
32,496 |
Total site costs – Taseko share |
102,476 |
111,343 |
90,536 |
95,830 |
400,185 |
Total site costs – 100% basis |
102,476 |
111,343 |
90,536 |
109,520 |
413,875 |
1 Q1 2024 includes the impact from the March 25,
2024 acquisition of Cariboo from Dowa and Furukawa, which increased
the Company’s Gibraltar mine ownership from 87.5% to 100%.
(Cdn$ in thousands, unless otherwise indicated) –87.5% basis
(except for Q1 2023) |
2023Q4 |
2023Q3 |
2023Q2 |
2023Q11 |
2023YE1 |
Site operating costs |
64,845 |
87,148 |
83,374 |
74,438 |
309,805 |
Add: |
|
|
|
|
|
Capitalized stripping costs |
31,916 |
2,083 |
8,832 |
12,721 |
55,552 |
Total site costs – Taseko share |
96,761 |
89,231 |
92,206 |
87,159 |
365,357 |
Total site costs – 100% basis |
110,584 |
101,978 |
105,378 |
112,799 |
430,739 |
1 Q1 2023 includes the impact from the March 15,
2023 acquisition of Cariboo from Sojitz, which increased the
Company’s Gibraltar mine ownership from 75% to 87.5%.
Non-GAAP Performance Measures -
Continued
Adjusted net income (loss) and Adjusted EPS
Adjusted net income (loss) removes the effect of
the following transactions from net income as reported under
IFRS:
- Unrealized foreign currency
gains/losses;
- Unrealized gain/loss on
derivatives;
- Other operating costs;
- Call premium on settlement of
debt;
- Loss on settlement of long-term
debt, net of capitalized interest;
- Bargain purchase gains on Cariboo
acquisition;
- Gain on acquisition of control of
Gibraltar;
- Realized gain on sale of finished
goods inventory;
- Inventory write-ups to net
realizable value that was sold or processed;
- Accretion and fair value adjustment
on Florence royalty obligation; and
- Finance and other non-recurring
costs for Cariboo acquisition.
Management believes these transactions do not
reflect the underlying operating performance of our core mining
business and are not necessarily indicative of future operating
results. Furthermore, unrealized gains/losses on derivative
instruments, changes in the fair value of financial instruments,
and unrealized foreign currency gains/losses are not necessarily
reflective of the underlying operating results for the reporting
periods presented.
Adjusted EPS is the Adjusted net income (loss)
attributable to common shareholders of the Company divided by the
weighted average number of common shares outstanding during the
period.
Non-GAAP Performance Measures -
Continued
Adjusted net income (loss) and Adjusted EPS (Continued)
(Cdn$ in thousands, except per share amounts) |
2024Q4 |
2024Q3 |
2024Q2 |
2024Q1 |
2024YE |
Net (loss) income |
(21,207 |
) |
(180 |
) |
(10,953 |
) |
18,896 |
|
(13,444 |
) |
Unrealized foreign exchange loss (gain) |
40,462 |
|
(7,259 |
) |
5,408 |
|
13,688 |
|
52,299 |
|
Unrealized (gain) loss on derivatives |
(25,514 |
) |
1,821 |
|
10,033 |
|
3,519 |
|
(10,141 |
) |
Other operating costs1 |
4,132 |
|
4,098 |
|
10,435 |
|
- |
|
18,665 |
|
Call premium on settlement of debt |
- |
|
- |
|
9,571 |
|
- |
|
9,571 |
|
Loss on settlement of long term debt, net ofcapitalized
interest |
- |
|
- |
|
2,904 |
|
- |
|
2,904 |
|
Gain on Cariboo acquisition |
- |
|
- |
|
- |
|
(47,426 |
) |
(47,426 |
) |
Gain on acquisition of control of Gibraltar2 |
- |
|
- |
|
- |
|
(14,982 |
) |
(14,982 |
) |
Realized gain on sale of inventory3 |
- |
|
- |
|
3,768 |
|
13,354 |
|
17,122 |
|
Inventory write-ups to net realizable value that wassold or
processed4 |
1,905 |
|
3,266 |
|
4,056 |
|
- |
|
9,227 |
|
Accretion and fair value adjustment on Florenceroyalty
obligation |
3,682 |
|
3,703 |
|
2,132 |
|
3,416 |
|
12,933 |
|
Accretion and fair value adjustment on considerationpayable to
Cariboo |
4,543 |
|
9,423 |
|
8,399 |
|
1,555 |
|
23,920 |
|
Non-recurring other expenses for Cariboo adjustment |
- |
|
- |
|
394 |
|
138 |
|
532 |
|
Estimated tax effect of adjustments |
2,465 |
|
(6,644 |
) |
(15,644 |
) |
15,570 |
|
(4,253 |
) |
Adjusted net income |
10,468 |
|
8,228 |
|
30,503 |
|
7,728 |
|
56,927 |
|
Adjusted EPS |
0.03 |
|
0.03 |
|
0.10 |
|
0.03 |
|
0.19 |
|
1 Other operating costs relates to the in-pit
crusher relocation project and care and maintenance costs due to
the June 2024 labour strike.
2 The $15.0 million gain on acquisition of
control of Gibraltar in Q1 2024 relates to the write-up of finished
copper concentrate inventory for Taseko’s 87.5% share to its fair
value at March 25, 2024.
3 Cost of sales for the year ended December 31,
2024 included $17.1 million in write-ups to net realizable value
for concentrate inventory held at the date of acquisition of
control of Gibraltar (March 25, 2024) that were subsequently sold.
The realized portion of the gains recorded in the first quarter for
GAAP purposes was $13.4 million and for the second quarter were
$3.8 million and have been included in Adjusted net income in the
period they were sold.
4 Write-ups to net realizable value for
inventory held at the date of acquisition of control of Gibraltar
(March 25, 2024) totaled $9.2 million. The inventory write-ups in
the first quarter for GAAP purposes have been included in Adjusted
net income in the period they were sold or processed. Cost of sales
for the year ended December 31, 2024 included $9.2 million in
inventory write-ups that were subsequently sold or processed
between the second and fourth quarter.
Non-GAAP Performance Measures -
Continued
(Cdn$ in thousands, except per share amounts) |
2023Q4 |
2023Q3 |
2023Q2 |
2023Q1 |
2023YE |
Net income |
38,076 |
871 |
9,991 |
33,788 |
82,726 |
Unrealized foreign exchange (gain) loss |
(14,541) |
14,582 |
(10,966) |
(950) |
(11,875) |
Unrealized loss (gain) on derivatives |
1,636 |
4,518 |
(6,470) |
2,190 |
1,874 |
Gain on Cariboo acquisition |
- |
- |
- |
(46,212) |
(46,212) |
Finance and other non-recurring costs |
(916) |
1,244 |
1,714 |
- |
2,042 |
Estimated tax effect of adjustments |
(194) |
(1,556) |
1,355 |
16,271 |
15,876 |
Adjusted net income (loss) |
24,061 |
19,659 |
(4,376) |
5,087 |
44,431 |
Adjusted EPS |
0.08 |
0.07 |
(0.02) |
0.02 |
0.15 |
Adjusted EBITDA
Adjusted EBITDA is presented as a supplemental
measure of the Company’s performance and ability to service debt.
Adjusted EBITDA is frequently used by securities analysts,
investors and other interested parties in the evaluation of
companies in the industry, many of which present Adjusted EBITDA
when reporting their results. Issuers of “high yield” securities
also present Adjusted EBITDA because investors, analysts and rating
agencies consider it useful in measuring the ability of those
issuers to meet debt service obligations.
Adjusted EBITDA represents net income before
interest, income taxes, and depreciation and also eliminates the
impact of a number of items that are not considered indicative of
ongoing operating performance. Certain items of expense are added
and certain items of income are deducted from net income that are
not likely to recur or are not indicative of the Company’s
underlying operating results for the reporting periods presented or
for future operating performance and consist of:
- Unrealized foreign exchange
gains/losses;
- Unrealized gain/loss on
derivatives;
- Amortization of share-based
compensation expense;
- Other operating costs;
- Call premium on settlement of
debt;
- Loss on settlement of long-term
debt;
- Bargain purchase gains on Cariboo
acquisition;
- Gain on acquisition of control of
Gibraltar;
- Realized gain on sale of finished
goods inventory;
- Inventory write-ups to net
realizable value that was sold or processed; and
- Finance and other non-recurring
costs for Cariboo acquisition.
Non-GAAP Performance Measures -
Continued
Adjusted EBITDA (Continued)
(Cdn$ in thousands) |
2024Q4 |
2024Q3 |
2024Q2 |
2024Q1 |
2024YE |
Net (loss) income |
(21,207 |
) |
(180 |
) |
(10,953 |
) |
18,896 |
|
(13,444 |
) |
Add: |
|
|
|
|
|
Depletion and amortization |
24,641 |
|
20,466 |
|
13,721 |
|
15,024 |
|
73,852 |
|
Finance and accretion expense |
21,473 |
|
25,685 |
|
21,271 |
|
19,849 |
|
88,278 |
|
Finance income |
(1,674 |
) |
(1,504 |
) |
(911 |
) |
(1,086 |
) |
(5,175 |
) |
Income tax expense (recovery) |
11,707 |
|
(200 |
) |
(3,247 |
) |
23,282 |
|
31,542 |
|
Unrealized foreign exchange loss (gain) |
40,462 |
|
(7,259 |
) |
5,408 |
|
13,688 |
|
52,299 |
|
Unrealized (gain) loss on derivatives |
(25,514 |
) |
1,821 |
|
10,033 |
|
3,519 |
|
(10,141 |
) |
Amortization of share-based compensation(recovery) expense |
(323 |
) |
1,496 |
|
2,585 |
|
5,667 |
|
9,425 |
|
Other operating costs |
4,132 |
|
4,098 |
|
10,435 |
|
- |
|
18,665 |
|
Call premium on settlement of debt |
- |
|
- |
|
9,571 |
|
- |
|
9,571 |
|
Loss on settlement of long-term debt |
- |
|
- |
|
4,646 |
|
- |
|
4,646 |
|
Gain on Cariboo acquisition |
- |
|
- |
|
- |
|
(47,426 |
) |
(47,426 |
) |
Gain on acquisition of control of Gibraltar1 |
- |
|
- |
|
- |
|
(14,982 |
) |
(14,982 |
) |
Realized gain on sale of inventory2 |
- |
|
- |
|
3,768 |
|
13,354 |
|
17,122 |
|
Inventory write-ups to net realizable value that wassold or
processed3 |
1,905 |
|
3,266 |
|
4,056 |
|
- |
|
9,227 |
|
Non-recurring other expenses for Caribooacquisition |
- |
|
- |
|
394 |
|
138 |
|
532 |
|
Adjusted EBITDA |
55,602 |
|
47,689 |
|
70,777 |
|
49,923 |
|
223,991 |
|
1 The $15.0 million gain on acquisition of
control of Gibraltar in Q1 2024 relates to the write-up of finished
copper concentrate inventory for Taseko’s 87.5% share to its fair
value at March 25, 2024.
2 Cost of sales for the year ended December 31,
2024 included $17.1 million in write-ups to net realizable value
for concentrate inventory held at the date of acquisition of
control of Gibraltar (March 25, 2024) that were subsequently sold.
The realized portion of the gains recorded in the first quarter for
GAAP purposes was $13.4 million and for the second quarter were
$3.8 million and have been included in Adjusted net income in the
period they were sold.
3 Write-ups to net realizable value for
inventory held at the date of acquisition of control of Gibraltar
(March 25, 2024) totaled $9.2 million. The inventory write-ups in
the first quarter for GAAP purposes have been included in Adjusted
net income in the period they were sold or processed. Cost of sales
for the year ended December 31, 2024 included $9.2 million in
inventory write-ups that were subsequently between the second and
fourth quarter.
Non-GAAP Performance Measures -
Continued
Adjusted EBITDA (Continued)
(Cdn$ in thousands) |
2023Q4 |
2023Q3 |
2023Q2 |
2023Q1 |
2023YE |
Net income |
38,076 |
|
871 |
|
9,991 |
|
33,788 |
|
82,726 |
|
Add: |
|
|
|
|
|
Depletion and
amortization |
13,326 |
|
15,993 |
|
15,594 |
|
12,027 |
|
56,940 |
|
Finance and accretion
expense |
12,804 |
|
14,285 |
|
13,468 |
|
12,309 |
|
52,866 |
|
Finance income |
(972 |
) |
(322 |
) |
(757 |
) |
(921 |
) |
(2,972 |
) |
Income tax expense |
17,205 |
|
12,041 |
|
678 |
|
20,219 |
|
50,143 |
|
Unrealized foreign exchange
(gain) loss |
(14,541 |
) |
14,582 |
|
(10,966 |
) |
(950 |
) |
(11,875 |
) |
Unrealized loss (gain) on
derivatives |
1,636 |
|
4,518 |
|
(6,470 |
) |
2,190 |
|
1,874 |
|
Amortization of share-based
compensation expense |
1,573 |
|
727 |
|
417 |
|
3,609 |
|
6,326 |
|
Gain on Cariboo
acquisition |
- |
|
- |
|
- |
|
(46,212 |
) |
(46,212 |
) |
Non-recurring other expenses for Cariboo acquisition |
- |
|
- |
|
263 |
|
- |
|
263 |
|
Adjusted EBITDA |
69,107 |
|
62,695 |
|
22,218 |
|
36,059 |
|
190,079 |
|
Non-GAAP Performance Measures -
Continued
Earnings from mining operations before
depletion, amortization, and non-recurring items
Earnings from mining operations before
depletion, amortization, and non-recurring items is earnings from
mining operations with depletion and amortization, and any items
that are not considered indicative of ongoing operating performance
added back. The Company discloses this measure, which has been
derived from our financial statements and applied on a consistent
basis, to assist in understanding the results of the Company’s
operations and financial position and it is meant to provide
further information about the financial results to investors.
(Cdn$ in thousands) |
2024Q4 |
2024Q3 |
2024Q2 |
2024Q1 |
2024YE |
Earnings from mining operations |
28,727 |
26,686 |
44,948 |
24,419 |
124,780 |
Add: |
|
|
|
|
|
Depletion and amortization |
24,641 |
20,466 |
13,721 |
15,024 |
73,852 |
Realized gain on sale of inventory1 |
- |
- |
3,768 |
13,354 |
17,122 |
Inventory write-ups to net realizable value thatwas sold or
processed2 |
1,905 |
3,266 |
4,056 |
- |
9,227 |
Other operating costs3 |
4,132 |
4,098 |
10,435 |
- |
18,665 |
Earnings from mining operations before depletion,
amortization, and non-recurring items |
59,405 |
54,516 |
76,928 |
52,797 |
243,646 |
1 Cost of sales for the year ended December 31,
2024 included $17.1 million in write-ups to net realizable value
for concentrate inventory held at the date of acquisition of
control of Gibraltar (March 25, 2024) that were subsequently sold.
The realized portion of the gains recorded in the first quarter for
GAAP purposes was $13.4 million and for the second quarter were
$3.8 million and have been included in Adjusted net income in the
period they were sold.
2 Write-ups to net realizable value for
inventory held at the date of acquisition of control of Gibraltar
(March 25, 2024) totaled $9.2 million. The inventory write-ups in
the first quarter for GAAP purposes have been included in Adjusted
net income in the period they were sold or processed. Cost of sales
for the year ended December 31, 2024 included $9.2 million in
inventory write-ups that were subsequently sold or processed in the
second and third quarters.
3 Other operating costs relates to the in-pit
crusher relocation project and care and maintenance costs due to
the June 2024 labour strike.
During the year ended December 31, 2024, the
realized gain on sale of inventory and inventory write-ups to net
realizable value that was sold or processed, relates to inventory
held at the date of acquisition of control of Gibraltar (March 25,
2024) that was written-up from book value to net realizable value
and subsequently sold or processed.
(Cdn$ in thousands) |
2023Q4 |
2023Q3 |
2023Q2 |
2023Q1 |
2023YE |
Earnings from mining operations |
59,780 |
49,452 |
12,070 |
29,112 |
150,414 |
Add: |
|
|
|
|
|
Depletion and amortization |
13,326 |
15,993 |
15,594 |
12,027 |
56,940 |
Earnings from mining operations before
depletionand amortization |
73,106 |
65,445 |
27,664 |
41,139 |
207,354 |
Non-GAAP Performance Measures -
Continued
Site operating costs per ton milled
The Company discloses this measure, which has
been derived from our financial statements and applied on a
consistent basis, to provide assistance in understanding the
Company’s site operations on a tons milled basis.
(Cdn$ in thousands, except per ton milled amounts) |
2024Q4 |
2024Q3 |
2024Q2 |
2024Q11 |
2024YE1 |
Site operating costs (included in cost
ofsales) – Taseko share |
|
100,495 |
|
107,712 |
|
79,804 |
|
79,678 |
|
367,689 |
Site operating costs – 100% basis |
|
100,495 |
|
107,712 |
|
79,804 |
|
90,040 |
|
378,050 |
Tons milled (thousands) |
|
8,250 |
|
7,572 |
|
5,728 |
|
7,677 |
|
29,227 |
Site operating costs per ton milled |
$12.18 |
$14.23 |
$13.93 |
$11.73 |
$12.93 |
1 Q1 2024 includes the impact from the March 25,
2024 acquisition of Cariboo from Dowa and Furukawa, which increased
the Company’s Gibraltar ownership from 87.5% to 100%.
(Cdn$ in thousands, except per ton milled amounts) |
2023Q4 |
2023Q3 |
2023Q2 |
2023Q11 |
2023YE1 |
Site operating costs (included in cost
ofsales) – Taseko share |
|
64,845 |
|
87,148 |
|
83,374 |
|
74,438 |
|
309,805 |
Site operating costs – 100% basis |
|
74,109 |
|
99,598 |
|
95,285 |
|
95,838 |
|
364,830 |
Tons milled (thousands) |
|
7,626 |
|
8,041 |
|
7,234 |
|
7,093 |
|
29,994 |
Site operating costs per ton milled |
$9.72 |
$12.39 |
$13.17 |
$13.54 |
$12.16 |
1 Q1 2023 includes the impact from the March 15,
2023 acquisition of Cariboo from Sojitz, which increased the
Company’s Gibraltar mine ownership from 75% to 87.5%.
Technical Information
The technical information contained in this
MD&A related to the Florence Copper Project is based upon the
report entitled: “NI 43-101 Technical Report – Florence Copper
Project, Pinal County, Arizona” issued March 30, 2023 with an
effective date of March 15, 2023 which is available on SEDAR+. The
Florence Copper Project Technical Report was prepared under the
supervision of Richard Tremblay, P.Eng., MBA, Richard Weymark,
P.Eng., MBA, and Robert Rotzinger, P.Eng. Mr. Tremblay is employed
by the Company as Chief Operating Officer, Mr. Weymark is Vice
President Engineering, and Robert Rotzinger is Vice President
Capital Projects. All three are Qualified Persons as defined by NI
43–101.
Caution Regarding Forward-Looking
Information
This document contains “forward-looking
statements” that were based on Taseko’s expectations, estimates and
projections as of the dates as of which those statements were made.
Generally, these forward-looking statements can be identified by
the use of forward-looking terminology such as “outlook”,
“anticipate”, “project”, “target”, “believe”, “estimate”, “expect”,
“intend”, “should” and similar expressions.
Forward-looking statements are subject to known
and unknown risks, uncertainties and other factors that may cause
the Company’s actual results, level of activity, performance or
achievements to be materially different from those expressed or
implied by such forward-looking statements. These included but are
not limited to:
- uncertainties about the effect of
COVID-19 and the response of local, provincial, federal and
international governments to the threat of COVID-19 on our
operations (including our suppliers, customers, supply chain,
employees and contractors) and economic conditions generally and in
particular with respect to the demand for copper and other metals
we produce;
- uncertainties and costs related to
the Company’s exploration and development activities, such as those
associated with continuity of mineralization or determining whether
mineral resources or reserves exist on a property;
- uncertainties related to the
accuracy of our estimates of mineral reserves, mineral resources,
production rates and timing of production, future production and
future cash and total costs of production and milling;
- uncertainties related to
feasibility studies that provide estimates of expected or
anticipated costs, expenditures and economic returns from a mining
project;
- uncertainties related to the
ability to obtain necessary licenses permits for development
projects and project delays due to third party opposition;
- uncertainties related to unexpected
judicial or regulatory proceedings;
- changes in, and the effects of, the
laws, regulations and government policies affecting our exploration
and development activities and mining operations, particularly
laws, regulations and policies;
- changes in general economic
conditions, the financial markets and in the demand and market
price for copper, gold and other minerals and commodities, such as
diesel fuel, steel, concrete, electricity and other forms of
energy, mining equipment, and fluctuations in exchange rates,
particularly with respect to the value of the U.S. dollar and
Canadian dollar, and the continued availability of capital and
financing;
- the effects of forward selling
instruments to protect against fluctuations in copper prices and
exchange rate movements and the risks of counterparty defaults, and
mark to market risk;
- the risk of inadequate insurance or
inability to obtain insurance to cover mining risks;
- the risk of loss of key employees;
the risk of changes in accounting policies and methods we use to
report our financial condition, including uncertainties associated
with critical accounting assumptions and estimates;
- environmental issues and
liabilities associated with mining including processing and stock
piling ore; and
- labour strikes, work stoppages, or
other interruptions to, or difficulties in, the employment of
labour in markets in which we operate mines, or environmental
hazards, industrial accidents or other events or occurrences,
including third party interference that interrupt the production of
minerals in our mines.
For further information on Taseko, investors
should review the Company’s annual Form 40-F filing with the United
States Securities and Exchange Commission www.sec.gov and home
jurisdiction filings that are available at www.sedarplus.com.
Cautionary Statement on Forward-Looking
Information
This discussion includes certain statements that
may be deemed "forward-looking statements". All statements in this
discussion, other than statements of historical facts, that address
future production, reserve potential, exploration drilling,
exploitation activities, and events or developments that the
Company expects are forward-looking statements. Although we believe
the expectations expressed in such forward-looking statements are
based on reasonable assumptions, such statements are not guarantees
of future performance and actual results or developments may differ
materially from those in the forward-looking statements. Factors
that could cause actual results to differ materially from those in
forward-looking statements include market prices, exploitation and
exploration successes, continued availability of capital and
financing and general economic, market or business conditions.
Investors are cautioned that any such statements are not guarantees
of future performance and actual results or developments may differ
materially from those projected in the forward-looking statements.
All of the forward-looking statements made in this MD&A are
qualified by these cautionary statements. We disclaim any intention
or obligation to update or revise any forward-looking statements
whether as a result of new information, future events or otherwise,
except to the extent required by applicable law. Further
information concerning risks and uncertainties associated with
these forward-looking statements and our business may be found in
our most recent Form 40-F/Annual Information Form on file with the
SEC and Canadian provincial securities regulatory authorities.
Taseko Mines (TSX:TKO)
Gráfico Histórico do Ativo
De Jan 2025 até Fev 2025
Taseko Mines (TSX:TKO)
Gráfico Histórico do Ativo
De Fev 2024 até Fev 2025