Pan
African Resources PLC
(Incorporated
and registered in England and Wales under the Companies Act 1985
with registration number 3937466 on 25 February 2000)
Share code
on AIM: PAF
Share code
on JSE: PAN
ISIN:
GB0004300496
ADR ticker
code: PAFRY
(Pan
African or the Company or the Group)
|
|
(Key
features are reported in United
States dollar (US$) or South African rand (ZAR), to the
extent relevant)
UNaudited INTERIM FINANCIAL results for THE SIX Months
ended 31 december
2024
KEY
FEATURES
Production
-
Group gold
production for the six months ended 31
December 2024 (current reporting period) of 84,705oz, a
slight reduction of 3.3% relative to the previous six months
(H2FY2024: 87,581oz)
-
As
announced in the December 2024
operational update, Evander Mines’ underground production was
impacted by the delay in commissioning of the subvertical shaft for
ore hoisting, which was partially offset by early production from
the Mogale Tailings Retreatment (MTR) operation
-
The Group
is well positioned for much-improved production in H2FY2025, with a
further significant increase in production expected for FY2026.
Full-year guidance for FY2025 of approximately 215,000oz (FY2024:
186,039oz) is maintained, an increase of 16% from the prior
year
-
The
subvertical hoisting shaft at Evander Mines was fully commissioned
during January 2025
-
MTR
production is now fully ramped up, ahead of schedule and with final
project capital below budget
-
Full-year
gold production (48,000oz to 60,000oz) from Tennant Consolidated
Mining Group (TCMG) in Australia
is planned for FY2026.
Safety
-
Regrettably,
the Group experienced one fatality during the reporting period
(FY2024: one), following an underground mud rush incident at
Evander Mines’ 7 Shaft on 30 December
2024
-
Improvement
in lost-time injury frequency rate (LTIFR) to 1.55 per million man
hours (FY2024: 1.82)
and reportable injury frequency rate (RIFR) to 0.55 per million man
hours (FY2024: 0.78)
-
Total
reportable injury frequency rate (TRIFR) regressed to 8.25 per
million man hours (FY2024: 6.52), which is being
addressed
-
The MTR
operation achieved a 1.8 million fatality-free shift milestone
during the construction phase, with:
-
over 1,600
employees and contractors on-site
-
zero
reportable injuries and only one lost-time injury.
Costs
and cost outlook
-
All-in
sustaining costs (AISC
) for the
reporting period of US$1,675/oz
(H1FY2024: US$1,295/oz)
impacted by:
-
a decrease
in production from Evander Mines’ underground operations for
reasons previously highlighted
-
multiple
Eskom transformer failures at Barberton Mines, as flagged in the
operational update published on 12 December
2024, negatively impacting production from the operation. A
number of mitigation measures have been implemented to avoid a
recurrence of this issue
-
appreciation
of the average exchange rate by 4.0% to US$/ZAR:17.95 (H1FY2024:
US$/ZAR:18.69)
-
once-off
long-term employee incentive expenses to the value of US$4.3 million (US$53.3/oz) included in the cost of
production
-
AISC
of
US$1,466/oz (FY2024: US$1,170/oz) for our lower-cost operations
(Elikhulu Tailings Retreatment Plant, Barberton Tailings
Retreatment Plant, MTR operation, Evander Mines underground and
Fairview Mine), which account for approximately 86%
(FY2024: 84%)
of annual production
-
AISC
guidance
for H2FY2025 is anticipated to be between US$1,450/oz to US$1,500/oz, with the expected cost reduction
versus H1FY2025 as a result of improved performance from the
underground operations and MTR being in production for the full
period.
Financial
-
Revenue
remained robust at US$189.3 million
(H1FY2024: restated US$191.1 million)
with only a slight decrease of 1% compared to the previous year as
a result of a 13% decrease in gold production and the impact of the
synthetic gold forward sale transaction of approximately
US$17.4 million on profits for the
reporting period, offset by a 21% increase in the US$ gold price
received
-
Profit for
the reporting period increased by 10% to US$44.6 million (H1FY2024: restated US$40.7 million),
and includes a gain on acquisition relating to the TCMG transaction
of US$25.2 million
-
Earnings
per share (EPS) increased by 10.3% to US 2.35 cents per share (H1FY2024: restated US
2.13 cents per share) and headline
earnings per share
(HEPS)
decreased by 43.7% to US 1.20 cents
per share (H1FY2024: restated US 2.13
cents per share). Included in EPS in the current reporting
period is a gain on acquisition relating to the TCMG transaction.
This gain is excluded from HEPS
-
Net cash
used in operating activities of US$11.7
million (H1FY2024: US$27.2
million), negatively impacted by the opportunity cost of
US$17.4 million that resulted from
the abovementioned synthetic gold forward sale transaction utilised
to part fund MTR’s construction as well as increased finance
costs
-
Net
debt
increased
to US$228.5 million (H1FY2024:
US$64.3 million), primarily as a
result of the construction of the MTR operation and the
consolidation of debt acquired as part of the TCMG
acquisition
-
Available
cash and undrawn facilities at period-end of US$32.3 million (H1FY2024: US$117.7 million)
-
Net
dividend of US$23.7 million paid to
shareholders in December 2024 (FY2024
dividend).
Near-term
growth projects
-
Mogale
Tailings Retreatment operation
-
Studies
are underway to increase annual production from 50,000oz to
approximately 60,000oz in the next year, through:
- the
installation of additional reactors to further improve
recoveries
-
the
addition of two carbon-in-leach (CIL) tanks to increase throughput
from 800ktpm to 1Mtpm
-
a
prefeasibility study on the inclusion of a hard rock crushing
circuit enabling the processing of nearby remnant hard rock
resources
-
a full
feasibility study on the Soweto Cluster tailings storage facilities
(TSFs) is underway and expected to be completed by September 2025, with the study focusing
on:
-
the
possibility of constructing a new processing facility in closer
proximity to the Soweto Cluster TSFs, which would be a stand-alone
operation, also producing approximately 50,000oz per
year
-
the option
to include additional proximal TSF resources that will further add
to the life- of-mine (LoM) of the project.
-
Barberton
Tailings Retreatment Plant (BTRP)
-
Construction
of the pump station to reprocess the Bramber dormant TSF at the
BTRP is expected to commence in Q4FY2025, with commissioning
expected in Q3FY2026
- This will
extend the LoM of the BTRP from two years to seven years from
current surface sources
-
TCMG
project in Australia
-
transaction
to acquire TCMG for US$54.2 million
was completed in December 2024, as
follows:
- An initial
cash investment of US$3.4 million for
an 8% shareholding in TCMG, with the all-scrip acquisition for the
remaining 92% of the business through the new issue of less than 6%
of the Company’s shares valued at US$50.8m.
- Production
from TCMG is expected to initially add more than 20% to annual
Group production from current reserves, with significant upside
exploration potential in its asset portfolio
-
Construction
of the Nobles Gold carbon in leach (CIL) processing plant has been
accelerated and is progressing ahead of schedule and within budget.
Commissioning of the plant and first gold is now expected in
Q4FY2025.
Expected
FY2026 production forecastThe
Group anticipates significant growth in production as outlined in
the table below:
Operation
|
Production
range
|
Elikhulu
|
48,000
|
53,000
|
MTR
|
48,000
|
53,000
|
BTRP
|
10,000
|
12,000
|
TCMG
|
48,000
|
60,000
|
Barberton
Mines underground*
|
68,000
|
75,000
|
Evander
Mines underground
|
48,000
|
55,000
|
Total
|
270,000
|
308,000
|
*Assumes
rightsizing of Barberton Mines’ underground operations as detailed
in the operations section of the full
announcement.
Group
cash flow generation and dividends
The final
settlement in terms of the synthetic gold forward sale transaction
will be at the end of February 2025,
after which the Group will fully benefit from the prevailing spot
gold price of approximately US$2,860/oz (ZAR1,690,000/kg) which is 21% higher (24% in rand
terms) compared with the average price of US$2,359/oz (ZAR1,361,202/kg) received in the current
reporting period.
At
prevailing gold prices and with increased high-margin production as
outlined in this announcement, the Group is expected to be
materially de-geared in the next 12 to 18 months. This will allow a
review of the Group’s dividend policy after financial year-end,
which could include instating interim dividend payments going
forward.
Environmental,
social and governance initiatives
-
The
Group’s renewable energy initiatives provide a roadmap to
decarbonise an estimated 100MW of power through its renewable
energy projects by 2030
-
The
Evander Mines phase 1 and Fairview renewable energy plants are
performing exceptionally well, generating an estimated 21GWh of
solar power. This contributes approximately 10% of the Group's
total energy, realising a significant saving of US$2.1 million for the reporting period, while
avoiding nearly 19ktCO2e
of Scope 2 emissions
-
A
feasibility study has been completed for a 20MW solar renewable
energy plant, with applications for environmental authorisations
and permitting currently in progress
-
The Group
has embarked on several energy efficiency optimisation projects at
our operations, realising approximately US$0.3 million in savings from these initiatives
for the reporting period, with an additional saving of 3
ktCO2e
in emissions
-
Following
a positive feasibility study, the Evander Mines’ water treatment
plant will be expanded to supply an estimated 4.5ML/day to
5.5ML/day from the current 3ML/day. Construction work to expand the
plant will commence during 2025
-
Rehabilitation
at MTR’s Mogale and Soweto sites
is in progress, with several wetlands being restored since
operations commenced. The Group is on target to rehabilitate 85ha
for FY2025, in accordance with the targets set out for the Group’s
Sustainability Bond
-
The
Group’s closure liabilities are materially funded with a shortfall
of only US$5.2 million related to the
MTR closure liability
This
announcement contains inside information.
CHIEF
EXECUTIVE OFFICER’S STATEMENT
Cobus Loots, Pan African’s chief executive officer,
commented:
“Pan
African has established an excellent safety record over the years,
and we remain committed to our goal of zero harm. We wish to again
express our condolences to the family, friends and co-workers of
our colleague who succumbed to his injuries following a mud rush
incident at a loading box at Evander Mines’ 7 Shaft on 30 December 2024.
Overall,
the Group has improved its safety performance in the period under
review, and we continue to implement ongoing safety awareness and
training programmes. We are especially proud of the safety
achievements at the recently commissioned MTR operation, where we
achieved 1.8 million fatality-free hours and zero reportable
injuries during the construction phase, with over 1,600 employees
and contractors on site.
In the
past few years, we have made excellent progress in positioning Pan
African as a safe, sustainable and growing high-margin producer. We
have diversified our production base from predominantly older
underground mines to a more balanced portfolio of surface and
underground assets. During the reporting period, we successfully
commissioned our MTR operation, ahead of schedule and with a saving
of some US$8 million on the upfront
project capital. MTR is another flagship tailings retreatment asset
for our Group, which will produce approximately 50,000oz of gold
per annum for a period of 20 years or more, if we include all of
our West Rand tailings reserves and resources. MTR also presents
scope for further production growth, with the ability to grow gold
output to approximately 60,000oz in the year ahead, via plant
expansion initiatives.
In
terms of additional diversification and near-term production
growth, we are delighted to have concluded the TCMG transaction in
December 2024. The construction of
the TCMG processing plant at its Nobles project is now nearing
completion, ahead of schedule and within its approximate
US$32.2 million capital budget. This
processing plant will be the largest to ever operate in the Tennant
Creek mineral field, aligned with our approach of achieving
economies of scale by operating bulk processing facilities. We have
also now accelerated the timing of anticipated gold production from
this asset, with estimated production of 48,000oz to 60,000oz in
the next financial year, at a very competitive
AISC
. In
addition to near-term, low cost gold production from surface
operations, the Tennant Creek mineral field presents exciting
exploration potential, some 1,700km2
of
highly prospective ground in Australia’s highest grade goldfield,
both from wholly-owned and joint venture
properties.
Including
production from TCMG, production from low cost surface sources in
the Group will account for over 50% of the Group’s annual
production in FY2026, estimated at between 270,000oz and 308,000oz
per annum. These surface assets will assist in ensuring Pan African
maintains a competitive AISC
profile,
comparing favourably to the rest of the global
industry.
Underground
mining in South Africa still
represents a significant portion of Pan African’s production base,
with the Group having invested meaningful capital into our
long-life assets in recent years. The Group flagged the challenges
experienced at the Evander Mines and Barberton Mines’ underground
operations in the December 2024
operational update. Following several delays, the subvertical
hoisting shaft at our Evander Mines’ underground operations was
finally commissioned during January
2025. Mining at the high-grade D line and F line raises on
24 Level has continued, resulting in accumulated ore in the ore
passes underground, and limited ore reaching the metallurgical
plant through the conveyor belt system. This has resulted in
elevated unit costs at Evander Mines during the reporting period,
which will reduce commensurately in the next months with increased
gold production.
At
Barberton Mines’ operations, production has normalised following
the Eskom transformer issues previously reported. Contingencies are
now in place to prevent these issues from recurring. We are pleased
that our efforts at Consort have seen this smaller operation turn a
corner and produce positive cash flows in the past months, with
further improvements anticipated in the period ahead. To ensure the
long-term sustainability of Sheba Mine at Barberton Mines, we will
implement a number of improvement and cost-cutting measures before
the end of the financial year.
We
believe Pan African is in an excellent position to capitalise from
record gold prices, with high margins, a stable and growing
production profile, and the Group being materially unhedged from
March 2025. At prevailing gold
prices, we anticipate the Group to de-gear completely in the next
12 to 18 months, allowing us to re-invest, to grow and continue to
provide sector-leading returns to shareholders. The Group will
revisit its dividend policy with regards to dividends post
year-end, should current gold prices be sustained.”
DIRECTORS’ RESPONSIBILITY
The
information in this announcement has been extracted from the
unaudited interim financial results for the six months ended
31 December 2024. The short-form
announcement has not been reviewed by the Company’s auditors. The
unaudited interim financial results have been prepared under the
supervision of the financial director, Marileen Kok. This short-form announcement is
the responsibility of the directors of Pan African and is only a
summary of the information contained in the full announcement which
was released on SENS on 12 February
2025.
Any
investment decisions should be based on the full announcement and
the Group’s detailed operational and financial
summaries.
AVAILABILITY OF THE FULL ANNOUNCEMENT
The full
announcement is accessible via
the JSE
link
https://senspdf.jse.co.za/documents/2025/jse/isse/pan/INT2024.pdf
and
via
the
Company’s website at
https://www.panafricanresources.com/wp-content/uploads/Pan-African-Resources-interim-results-SENS-announcement-2025.pdf
Copies of
the full announcement may also be requested by emailing
ExecPA@paf.co.za and
electronically via
the
sponsor (sponsor@questco.co.za) at no charge during business
hours.
The
Company has a dual primary listing on the JSE Limited in
South Africa and the AIM of the
London Stock Exchange, a secondary listing on the A2X Market as
well as a sponsored Level 1 American Depository Receipt programme
in the United States of America
through the Bank of New York Mellon.
For
further information on Pan African, please visit the Company's
website at
www.panafricanresources.com
Rosebank
12 February 2025
Corporate
information
|
Corporate
Office
The Firs
Building
2nd Floor,
Office 204
Cnr
Cradock and Biermann Avenues
Rosebank,
Johannesburg
South
Africa
Office: +
27 (0) 11 243 2900
info@paf.co.za
|
Registered
Office
107
Cheapside
2nd
Floor
London
EC2V
6DN
United
Kingdom
Office: +
44 (0) 20 3869 0706
|
Chief
executive officer
Cobus
Loots
Office: +
27 (0) 11 243 2900
|
Financial
director and debt officer
Marileen
Kok
Office: +
27 (0) 11 243 2900
|
Head:
Investor relations
Hethen
Hira
Tel: + 27
(0) 11 243 2900
Email:
hhira@paf.co.za
|
Website:
www.panafricanresources.com
|
Company
secretary
Jane
Kirton
St
James's Corporate Services Limited
Office: +
44 (0) 20 3869 0706
|
Nominated
adviser and joint broker
Ross
Allister/Georgia Langoulant
Peel
Hunt LLP
Office:
+44 (0) 20 7418 8900
|
JSE
sponsor
Ciska
Kloppers
Questco
Corporate Advisory Proprietary Limited
Office: +
27 (0) 63 482 3802
|
Joint
broker
Thomas
Rider/Nick Macann
BMO
Capital Markets Limited
Office:
+44 (0) 20 7236 1010
|
|
Joint
broker
Matthew
Armitt/Jennifer Lee
Joh.
Berenberg, Gossler & Co KG (Berenberg)
Office:
+44 (0) 20 3207 7800
|