The information contained
within this announcement is deemed by the Company to constitute
inside information as stipulated under the Market Abuse Regulations
(EU) No. 596/2014 ("MAR")
Kodal
Minerals Plc / Index: AIM / Epic: KOD / Sector: Mining
14 November 2024
Kodal Minerals
plc
("Kodal
Minerals", "Kodal" or the "Company")
Bougouni Lithium Project
Development Update and
High Grade Intersections
returned for Boumou Prospect Diamond Drilling
Kodal Minerals, the mineral
exploration and development company, is pleased to provide an
update on the progress of construction of the Stage 1 Dense Media
Separation ("DMS") processing plant and mining at the Ngoualana
open pit mine at its flagship Bougouni Lithium Project in Southern
Mali ("Bougouni" or the "Project"). The Project is fully funded
through the US$117.5m Hainan funding transaction (as announced by
the Company on 15 November 2023) (the "Hainan Transaction"). The
Hainan Transaction included a US$100m investment into Kodal Mining
UK Limited ("KMUK"), a company owned 51% by the Hainan Group and
49% by Kodal, which is the developer of the Project.
Highlights:
· The start of production at Bougouni remains on track for the
first quarter of 2025 and remains within the US$65 million capital
development budget.
· The shipment carrying remaining steelwork, platework, mechanical equipment, electrical
equipment and piping materials arrived at the Abidjan Port in Côte
d'Ivoire. These items have been unloaded and are en route to
site.
·
Following completion of the abnormally
long wet season construction progress is
accelerating and
structural steel erection work has
progressed well with all major buildings taking shape, including
the main DMS module, the screening building and the filtration
building.
·
Electrical generator units are currently being
delivered with the first two units having reached the Conakry port
in Guinea and will be transported to the site as soon as
possible. The remainder of the electrical generator units are
currently being shipped to the Abidjan Port.
· Open pit mining activities at the Ngoualana deposit continue
to advance ahead of schedule, with several blasts conducted in the
hard rock. The main Ngoualana ore body is exposed and a total of
59,500 tonnes of ore grading on average 1.20%
Li2O was mined in preparation for
commissioning.
· Assay results have been received for the majority of the
Boumou prospect diamond drilling programme, which confirms
consistent wide, high grade drill intersections
including:
o 50.5m at 1.45% Li2O from 139.5m and
12.75m at 1.80% Li2O from
126.8m in drill hole KLDH029;
o 36.5m at 1.30% Li2O from 76.35m in drill hole
KLDH038;
o 21m
at 1.51% Li2O from 109.8m in drill hole KLDH039;
and
o 51m
at 1.39% Li2O from 110.75m in drill hole
KLDH041.
Bernard Aylward, CEO of Kodal Minerals,
remarked: "The acceleration in the
Bougouni Lithium Project development is very pleasing. The
crushing circuit and the DMS processing plant is rapidly taking
shape and the commissioning of the crushing circuit will commence
in December 2024 followed by the DMS units."
"Additionally, the diamond core drilling results received from
the Boumou prospect confirm the continuity of the wide, high grade
pegmatite veins and highlight the potential to continue to expand
the mineral resource base at the Boumou prospect. Further
drilling is planned for the prospect to target extensions of the
main zone as well as target new zones with off-set positions from
interpreted fault structures. The next phase of drilling will
also include geotechnical drilling and metallurgical sampling for
assessment of the open pit development of the Boumou
prospect."
"As announced on 1 November 2024, a binding memorandum of
understanding was signed with the Government of Mali to confirm the
transfer of the mining licence to KMUK's subsidiary mining company
that will operate the Bougouni mine and the first half of the US$15
million settlement payment has been made by KMUK to ensure we
finalise this transfer shortly. Kodal and Hainan are
continuing discussions regarding the off-take agreement and who
will have ultimate responsibility for the settlement payment to the
Mali Government."
FURTHER
INFORMATION
Bougouni Mining Licence
transfer
As announced on 1 November 2024,
KMUK signed a binding agreement with the Mali Government to
finalise the transfer of the Bougouni mining licence to the project
mining company as the final compliance item to allow full mining
and export of product. The first half of the US$15m
settlement payment has been made to the Mali Government and the
licence transfer process is expected to be completed
shortly.
Kodal and Hainan are continuing
discussions on finalising the off-take agreement and key commercial
terms have been agreed by the parties. Discussions are also
continuing between the parties regarding the Mali Government
settlement payment in connection with the mining licence
transfer. An update on the discussions will be provided in
due course.
Project Development
Programme
The start of production
at Bougouni
remains on track for commencement in the
first quarter of 2025. The abnormally long wet season appears to be
over and construction activities are progressing
well.
Five shipments have arrived in West
Africa and the majority of material has been delivered to
site. There is one major shipment outstanding at sea which is
carrying the remaining electrical generator
units. Two electrical generator units arrived in
West Africa this week at the port of Conakry, Guinea, and they are
anticipated to be transported to site before the end of the month.
The early shipment of these two electrical
generator units will mitigate the impact of
delays to commissioning. Initially the Company was investigating
the hire of temporary electrical
generators to be utilised to conduct the advance
pre-commissioning of equipment, but the early shipment of
two electrical generators will now fulfil this activity.
The construction on site will
continue to proceed as quickly as possible, with all steelwork,
platework, mechanical equipment, electrical equipment and piping
materials delivered.
Mining
Mining activities continue to
progress well in advance of commissioning and future production
requirements. The open pit mine has now advanced to predominantly
mining hard rock ore and waste mining. Blasting is continuing as
required to meet the overall mining schedule. The Ngoualana ore
body is well exposed and a total of 59,500 tonnes of ore grading on
average 1.20% Li2O has been mined, which is sufficient
ore for the commissioning phase.
The Company is stockpiling high
grade and low grade ore separately in readiness for commissioning.
The low grade ore will be used initially during the early
commissioning phase of the crushing modules. Only after the circuit
has been bedded down and rock boxes filled in the various chutes
will high grade ore be introduced.
SMPP Installation
Contractor
The SMPP
("Structural, Mechanical, Platework and Piping") contractor,
Bambara Resources SARL together with its key subcontractor, Yantai
Jinpeng Mining Machinery Company from China, are progressing well
with installation works. Steel structural erection is progressing
simultaneously at the screening building, the DMS plant itself, and
the downstream filtration circuit. Assembly of conveyors is also
progressing.
Platforms and handrails are
progressing floor by floor as the buildings advance. These
activities are essential for providing safe working access for the
follow-on activities of piping and electrical
installations.
Expert engineers each from Beijing
HighDynamic (supplier of the crushing modules) and Haiwang
(supplier of the DMS equipment) continue to work closely with the
installation team on site. This approach has been well received by
the installation team as any technical queries are answered
immediately on site and not reliant on excess reference to the
headquarters in China. Representatives from both companies will
assist with the commissioning and training process.
Boumou Assay
Results
Most of the outstanding assays for
the Boumou diamond core drilling programme have now been
received. The remaining samples are a series of check
sampling and infill sampling between pegmatite zones to confirm the
low-grade waste material and possible wider mining zones of the
wide high grade pegmatite veins.
The drilling has confirmed the
continuity and depth extension of the core pegmatite veins that
mark the extension of the Boumou prospect. The drilling programme
has also highlighted a fault zone that may control an offset of the
pegmatite zone and highlight further exploration
opportunities.
The next steps for the Boumou
prospect include further infill and extension drilling prior to an
updated mineral resource estimate and a phase of geotechnical and
metallurgical drilling to allow the engineering assessment of the
open pit potential of the Boumou prospect.
A summary table of the initial
mineralised intersections for the assay results received to date is
presented below:
Hole_ID
|
From
|
To
|
Width
|
Grade
Li2O
|
KLDH029
|
109
|
122.5
|
13.5
|
1.31
|
|
139.5
|
190
|
50.5
|
1.45
|
|
100.5
|
108.5
|
8
|
1.80
|
|
126.8
|
139.55
|
12.75
|
1.80
|
KLDH034
|
119.48
|
148.6
|
29.12
|
1.37
|
KLDH035
|
129.68
|
146.2
|
16.52
|
1.28
|
KLDH037
|
181.68
|
205.10
|
23.42
|
1.32
|
KLDH038
|
76.35
|
112.85
|
36.5
|
1.30
|
KLDH039
|
109.80
|
130.80
|
21
|
1.51
|
KLDH040
|
206
|
233.50
|
27.50
|
1.42
|
KLDH041
|
110.75
|
161.75
|
51
|
1.39
|
|
237.80
|
249.80
|
12
|
1.35
|
KLDH042
|
81.50
|
96.50
|
15
|
1.65
|
|
197.90
|
215.40
|
17.5
|
1.34
|
KLDH043
|
110.75
|
125.75
|
15
|
1.13
|
KLDH048
|
81.50
|
97.50
|
16
|
1.44
|
|
221.96
|
237.46
|
15.5
|
1.31
|
KLDH049
|
48.50
|
62.0
|
13.5
|
1.73
|
KLDH051
|
126.50
|
148.50
|
22
|
1.09
|
|
214.50
|
225.50
|
11
|
1.19
|
Notes: Drill holes are diamond core drill holes. Drill
holes have been sampled on a 0.5m basis with samples collected from
½ cut HQ size core. All drill holes are geologically logged, and
sampling for analysis is based on geological boundaries.
Samples analysed by ALS Global. Assay results are reported as Li%
and converted to Li2O% by a factor of 2.153.
Intersections are reported using geological boundaries for logged
pegmatite, with a nominal 0.5%Li2O lower-cut-off and allowing
for internal dilution in zones of broad pegmatite
mineralisation.
A full report on the Boumou prospect
will be prepared when all assay results have been
received.
**ENDS**
For further information, please
visit www.kodalminerals.com or contact the following:
Kodal Minerals plc
Bernard Aylward, CEO
|
Tel: +61 418 943 345
|
Allenby Capital Limited, Nominated
Adviser
Jeremy Porter/Vivek
Bhardwaj
|
Tel: 020 3328 5656
|
SP Angel Corporate Finance LLP,
Financial Adviser & Joint Broker
John Mackay/Adam Cowl
|
Tel: 020 3470 0470
|
Canaccord Genuity Limited, Joint
Broker
James Asensio/Charlie
Hammond
|
Tel: 0207 523 4680
|
Burson Buchanan, Financial
PR
Bobby Morse/Oonagh Reidy
|
Tel: +44 (0)20 7466 5000
kodal@buchanancomms.co.uk
|
The exploration results and activity
reported in this announcement have been reviewed by Mr Bernard
Aylward who is a Member of the Australasian Institute of Mining and
Metallurgy. Mr Aylward has sufficient experience that is relevant
to the style of mineralisation and type of deposit under
consideration and to the activity being undertaken to qualify as a
Qualified Person as defined in the AIM Note for Mining and Oil
& Gas Companies dated June 2009. Mr Aylward consents to the
inclusion in this announcement of the matters based on his
information in the form and context in which it appears.