Soluna Announces Monthly Business Update
10 Fevereiro 2025 - 10:00AM
Business Wire
Soluna Holdings, Inc. (“SHI” or the “Company”), (NASDAQ: SLNH),
a developer of green data centers for intensive computing
applications including Bitcoin mining and AI, announced its January
2025 project site-level operations, developments, and updates.
This press release features multimedia. View
the full release here:
https://www.businesswire.com/news/home/20250210842442/en/
The construction of Soluna's Project
Dorothy 2 is underway.(Photo: Business Wire)
The Company has provided the following Corporate and Site
Updates.
Key Company Metrics:
The monthly metrics are now available here.
Corporate Highlights:
- Upcoming Webinar - Water Tower Research will host CEO
John Belizaire for a Fireside Chat on Monday, February 10th at
11:00 AM ET. They will discuss company updates, project milestones,
and Soluna’s pipeline. Register here to watch.
- New AMA - CFO John Tunsion recently answered
shareholders’ frequently asked questions in another installment of
our Ask Me Anything (AMA) series. Read it here.
- New Podcast Episodes - CEO John Belizaire hosts
interviews with Soluna’s team and industry experts in a new limited
series focused on AI, sustainability, and Soluna Cloud. Listen to
the latest episodes here.
- S-1 Registration Statement for SEPA Effective - The
registration statement filed in conjunction with our Yorkville
Advisors Standby Equity Purchase Agreement (“SEPA”) went
effective.
Key Project Updates:
Project Dorothy 1A (25 MW, Bitcoin Hosting) / Project Dorothy
1B (25 MW, Bitcoin Prop-Mining):
- Dorothy 1A and 1B incurred a 1-week planned outage for the
Dorothy 2 substation interconnection.
- The planned outage was used to upgrade the core network
switches which will increase network security and reliability.
- Additionally, critical power infrastructure maintenance was
performed.
- Following the outage, both sites have returned to full
operation and are benefiting from warmer temperatures in the region
resulting in minimal curtailments.
Project Dorothy 2 (48 MW, Bitcoin Hosting):
- The substation interconnection was successfully completed,
potentially paving the way for the initial energization of the
site.
- Coordination is underway with key partners to finalize grid and
wind farm telemetry data to complete the energization checklist for
ERCOT operations.
- We completed a hosting tender with Hyperscale miners who have
an interest in contracting for hosting.
- A late February initial energization date is expected. Phase 1
commissioning and deployments are expected to begin early
April.
- The latest photos of the construction progress can be found
here.
Project Grace (2 MW at Dorothy 2, AI Cloud/Hosting):
- Behind-the-meter (BTM) architecture is progressing well with
three different cooling technologies identified that can meet BTM
Requirements.
Project Ada (1 MW, AI Cloud with HPE):
- A new 128-GPU Atlas Cloud cluster went live on February 4th
replacing the previously announced deal.
- 2 new contracts for GPUs are in the final stages of negotiation
which, if entered into, would sell out the initial cluster with
HPE.
- The AI pipeline now exceeds 1,500 Nvidia H100 GPUs since the
DeepSeek announcements. Inbound requests for H200s have also
increased.
Project Sophie (25 MW, Bitcoin Hosting with Profit Share, AI
Hosting):
- The site is operating at 65% capacity due to an equipment
failure within the utility substation during the recent cold snap
last month.
- Our hyperscale mining partners are satisfied with the rapid
resolution of the outage.
- The local utility has secured the parts that failed and is
expected to complete the repair in March.
Project Kati (166 MW, Bitcoin Hosting and AI):
- Negotiations are underway with suppliers on long-lead
electrical infrastructure.
- The design scope is being finalized for the first 83 MW of
Bitcoin Hosting with an EPC bid process expected to be facilitated
in late February.
- We anticipate the next phase of the substation interconnection
work will occur in April.
Customer Success:
- We are in the process of deploying a 3rd expansion request with
the customer Bit Digital.
- Deploying the second batch of next-generation units (S21s) at
Project Dorothy.
- Completed deployment of 2nd expansion request with customer
Bitmine Immersion Technologies.
- Reviewing partner proposals for Dorothy 2 Bitcoin Hosting
availability.
View Soluna’s recent AMA here. View Soluna 2024 Earnings Power
Presentation here.
Safe Harbor Statement
This announcement contains forward-looking statements. These
statements are made under the "safe harbor" provisions of the U.S.
Private Securities Litigation Reform Act of 1995. These
forward-looking statements include all statements, other than
statements of historical fact, regarding our current views and
assumptions with respect to future events regarding our business
and other statements that are predictive in nature. These
forward-looking statements can be identified by terminology such as
“will,” “expects,” “anticipates,” “future,” “intends,” “plans,”
“believes,” “estimates,” “confident” and similar statements.
Readers are cautioned that any forward-looking information provided
by us or on our behalf is not a guarantee of future performance.
Actual results may differ materially from those contained in these
forward-looking statements as a result of various factors disclosed
in our filings with the SEC, including the “Risk Factors” section
of our Annual Report on Form 10-K filed with the SEC on April 1,
2024. All forward-looking statements speak only as of the date on
which they are made, and we undertake no duty to update or revise
any forward-looking statements, whether as a result of new
information, future events, or otherwise, except to the extent
required by law.
About Soluna Holdings, Inc (SLNH)
Soluna is on a mission to make renewable energy a global
superpower using computing as a catalyst. The company designs,
develops, and operates digital infrastructure that transforms
surplus renewable energy into global computing resources. Soluna’s
pioneering data centers are strategically co-located with wind,
solar, or hydroelectric power plants to support high-performance
computing applications including Bitcoin Mining, Generative AI, and
other compute-intensive applications. Soluna’s proprietary software
MaestroOS(™) helps energize a greener grid while delivering
cost-effective and sustainable computing solutions, and superior
returns. To learn more visit solunacomputing.com. Follow us on X
(formerly Twitter) at @SolunaHoldings.
View source
version on businesswire.com: https://www.businesswire.com/news/home/20250210842442/en/
Sam Sova Partner and CEO SOVA Sam@letsgosova.com