VANCOUVER, BC, Jan. 14, 2024 /PRNewswire/ -- (TSX: LUN) (Nasdaq
Stockholm: LUMI) Lundin Mining Corporation ("Lundin Mining"
or the "Company") is pleased to announce production results for the
year ended December 31, 2023 and
provides production guidance for the three-year period of 2024
through 2026, as well as cash cost, capital and exploration
expenditure forecasts for 2024. View PDF version
Highlights
- 2023 production results:
- On a consolidated basis the Company achieved
guidance1. Production for all metals was at the midpoint
or above for all guidance ranges.
- On a 100% basis consolidated copper production was a record for
the Company at 314,798 tonnes (t), and copper-equivalent
consolidated production was over 550,000 t.2
- Candelaria achieved guidance. Copper production was 152,012 t
and gold production was 89,700 ounces (oz).
- Caserones copper production was 65,210 t for the second half of
the year which exceeded original guidance3, and on a
full year basis was 139,520 t.
- Chapada achieved guidance. Copper production was 45,719 t, and
gold production was on the upper end of guidance at 59,268 oz for
the year.
- Consolidated zinc production was 185,161 t, which was at
the midpoint of the guidance. Production at Neves-Corvo was on the
upper end of zinc guidance while Zinkgruvan was slightly below zinc
guidance.
- Consolidated gold production was 148,968 oz which was on the
upper end of guidance.
- Nickel production at Eagle was 16,429 t and copper
production was 13,600 t both of which exceeded original
guidance.
- 2024 guidance on a consolidated basis is largely in line with
last year's production
guidance:
- Copper production guidance of 366,000 – 400,000 t.
- Zinc production guidance of 195,000 – 215,000 t.
- Gold production guidance of 155,000 – 170,000 t.
- Nickel production guidance of 10,000 – 13,000 t.
____________________________________________
|
1 Guidance
as most recently disclosed in the Company's Management Discussion
and Analysis for the three and nine months ended September 30,
2023.
|
2 Calculated
based on the ratios of 2023 average metal prices of Cu: $3.85/lb,
Zn: $1.20/lb, Ni: $9.74/lb, Mo: $24.19/lb, Pb: $0.97/lb Ag:
$23.50/oz and Au: $1,941/oz.
|
3 Caserones guidance is for the
second half of 2023. See "Lundin Mining Announces Closing of the
Acquisition of Majority Interest in the Caserones Copper-Molybdenum
Mine in Chile and Commitments for New $800 Million Term Loan" dated
July 13, 2023.
|
|
This news release
contains non-GAAP measures and forward-looking information about
expected future events and financial and operating performance of
the Company. Please refer to the Historical Non-GAAP Measure
Comparatives section and the risks and assumptions set out in our
Cautionary Statement on Forward-Looking Information section of this
press release. All dollar amounts are expressed in U.S. dollars,
unless otherwise noted.
|
Jack Lundin, President and CEO,
commented "2023 was a significant year for Lundin Mining and we
are well positioned for growth in 2024. The 51% acquisition of
Caserones led to a record in annual copper production. We have
initiated comprehensive value optimization efforts across our Latin
American sites. We are beginning to execute on some of these
initiatives at Chapada and Candelaria and the kickoff of
optimization work at Caserones will begin this quarter. An exciting
exploration program has begun on both the Chilean and Argentinian
side of the Vicuña district. We will look to drive value from the
drill bit as this has proven to be a key contributor to the overall
value creation at Lundin Mining.
"Across our critical metals portfolio, the zinc expansion
project at Neves Corvo, otherwise known as ZEP, is coming to
fruition, leading to back-to-back quarterly record zinc production
at this operation. At Zinkgruvan in 2023, improved recoveries from
the sequential flotation project were achieved, however, a longer
than anticipated ramp up resulted in a slight miss on guidance. Our
nickel operation, Eagle, continues to perform and hit the upper end
of guidance.
"During the year, the cumulative result was over 550,000
tonnes of consolidated copper equivalent production. This year's
guidance shows an increase of over 20% for copper production and
10% for zinc production over 2023. As we turn the page on a
transformational year for the Company, our focus remains on
achieving operational excellence by consistently maintaining
elevated safety standards, all while meeting production guidance at
competitive costs."
Summary of 2023 Production
|
|
Q4
2023
Production
|
Full Year
2023
Production
|
2023
Original
Guidance4
|
2023 Revised
Guidance5
|
|
Copper
(t)
|
|
|
|
|
|
|
|
|
|
|
Candelaria (100%
basis)
|
41,618
|
152,012
|
145,000
|
-
|
155,000
|
147,000
|
-
|
153,000
|
|
|
Caserones (100% basis
H2) 6
|
35,389
|
65,210
|
60,000
|
-
|
64,000
|
65,000
|
-
|
69,000
|
|
|
Chapada
|
12,872
|
45,719
|
43,000
|
-
|
48,000
|
45,000
|
-
|
48,000
|
|
|
Eagle
|
3,334
|
13,600
|
12,000
|
-
|
15,000
|
12,000
|
-
|
15,000
|
|
|
Neves-Corvo
|
9,623
|
33,823
|
33,000
|
-
|
38,000
|
33,000
|
-
|
36,000
|
|
|
Zinkgruvan
|
501
|
4,434
|
3,000
|
-
|
4,000
|
3,000
|
-
|
4,000
|
|
|
Total
Copper
|
103,337
|
314,798
|
296,000
|
-
|
325,000
|
305,000
|
-
|
325,000
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Zinc
(t)
|
|
|
|
|
|
|
|
|
|
|
Neves-Corvo
|
31,035
|
108,812
|
100,000
|
-
|
110,000
|
103,000
|
-
|
110,000
|
|
|
Zinkgruvan
|
19,684
|
76,349
|
80,000
|
-
|
85,000
|
78,000
|
-
|
82,000
|
|
|
Total
Zinc
|
50,719
|
185,161
|
180,000
|
-
|
195,000
|
181,000
|
-
|
192,000
|
|
|
|
|
|
|
|
|
|
|
|
|
Gold
(oz)
|
|
|
|
|
|
|
|
|
|
|
Candelaria (100%
basis)
|
24,787
|
89,700
|
85,000
|
-
|
92,000
|
87,000
|
-
|
92,000
|
|
|
Chapada
|
19,025
|
59,268
|
55,000
|
-
|
60,000
|
55,000
|
-
|
60,000
|
|
|
Total
Gold
|
43,812
|
148,968
|
140,000
|
-
|
150,000
|
142,000
|
-
|
152,000
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Nickel
(t)
|
|
|
|
|
|
|
|
|
|
|
Eagle
|
3,729
|
16,429
|
13,000
|
-
|
16,000
|
15,000
|
-
|
17,000
|
|
|
Total
Nickel
|
3,729
|
16,429
|
13,000
|
-
|
17,000
|
15,000
|
-
|
18,000
|
|
|
|
|
|
|
|
|
|
|
|
|
Molybdenum
(t)
|
|
|
|
|
|
|
|
|
|
Caserones (100% basis
H2)6
|
928
|
2,024
|
1,500
|
-
|
2,000
|
1,500
|
-
|
2,000
|
|
|
Total
Molybdenum
|
928
|
2,024
|
1,500
|
-
|
2,000
|
1,500
|
-
|
2,000
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
____________________________________________
|
4 Guidance
as announced by news release "Lundin Mining Announces 2022
Production Results & Provides 2023 Guidance" dated January 12,
2023, and "Lundin Mining Announces Closing of the Acquisition of
Majority Interest in the Caserones Copper-Molybdenum Mine in Chile
and Commitments for New $800 Million Term Loan" dated July 13,
2023.
|
5 Guidance
as most recently disclosed in the Company's Management Discussion
and Analysis for the three and nine months ended September 30,
2023.
|
6 Caserones guidance is for the
second half of 2023. As per previous disclosure, revised production
guidance for the second half of 2023 was 65,000 t to 69,000 t and
molybdenum was 1,500 t to 2,000 t.
|
Three-Year Production Outlook 2024 -
2026
- 2024 updated guidance outlook is in line with previously
disclosed production ranges. Consolidated copper production in 2024
has stayed consistent with previous estimates, consolidated zinc
production ranges have been slightly adjusted and consolidated gold
production ranges have increased for 2024. In 2025 consolidated
copper and gold ranges have increased while zinc guidance has
stayed in line with previous disclosure.
- Copper production is forecast to be 366,000 - 400,000 t on a
consolidated basis in 2024. Higher consolidated copper production
is forecast for 2024, mainly due to mine sequencing and the mine
plan copper grade profile at Candelaria. Caserones copper
production guidance has been increased to 120,000 - 130,000 t on an
annual basis to reflect higher planned throughput rates in the
mill.
- Zinc production is forecast to increase to 195,000 - 215,000 t
on a consolidated basis in 2024, increasing further over the
three-year period to reach 220,000 - 240,000 t in 2025 and
2026.
- Consolidated gold production is forecast to be 155,000 -
170,000 oz in 2024 and then taper through the three-year outlook
period. Higher consolidated gold production in 2024 is due mainly
to mine sequencing and the planned gold grade profile at
Candelaria.
- Nickel production is forecast to be 10,000 - 13,000 t in 2024
and then taper over the three-year period. The production profile
is driven by the planned mine sequencing and nickel grade as the
Eagle East and Upper Keel orebodies at Eagle are nearing the end of
their mine life.
Production
Outlook7
|
|
2024
|
|
2025
|
|
2026
|
Copper
(t)
|
|
|
|
|
|
|
|
|
|
|
|
|
Candelaria (100%
basis)
|
160,000
|
-
|
170,000
|
|
150,000
|
-
|
160,000
|
|
150,000
|
-
|
160,000
|
|
Caserones (100%
basis)
|
120,000
|
-
|
130,000
|
|
125,000
|
-
|
135,000
|
|
125,000
|
-
|
135,000
|
|
Chapada
|
43,000
|
-
|
48,000
|
|
40,000
|
-
|
45,000
|
|
40,000
|
-
|
45,000
|
|
Eagle
|
9,000
|
-
|
12,000
|
|
5,000
|
-
|
8,000
|
|
5,000
|
-
|
8,000
|
|
Neves-Corvo
|
30,000
|
-
|
35,000
|
|
35,000
|
-
|
40,000
|
|
33,000
|
-
|
38,000
|
|
Zinkgruvan
|
4,000
|
-
|
5,000
|
|
3,000
|
-
|
4,000
|
|
3,000
|
-
|
4,000
|
|
Total
Copper
|
366,000
|
-
|
400,000
|
|
358,000
|
-
|
392,000
|
|
356,000
|
-
|
390,000
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Zinc
(t)
|
|
|
|
|
|
|
|
|
|
|
|
|
Neves-Corvo
|
120,000
|
-
|
130,000
|
|
140,000
|
-
|
150,000
|
|
140,000
|
-
|
150,000
|
|
Zinkgruvan
|
75,000
|
-
|
85,000
|
|
80,000
|
-
|
90,000
|
|
80,000
|
-
|
90,000
|
|
Total
Zinc
|
195,000
|
-
|
215,000
|
|
220,000
|
-
|
240,000
|
|
220,000
|
-
|
240,000
|
|
|
|
|
|
|
Gold
(oz)
|
|
|
|
|
|
|
|
|
|
|
|
|
Candelaria (100% basis)
8
|
100,000
|
-
|
110,000
|
|
90,000
|
-
|
100,000
|
|
85,000
|
-
|
95,000
|
|
Chapada
|
55,000
|
-
|
60,000
|
|
55,000
|
-
|
60,000
|
|
55,000
|
-
|
60,000
|
|
Total
Gold
|
155,000
|
-
|
170,000
|
|
145,000
|
-
|
160,000
|
|
140,000
|
-
|
155,000
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Nickel
(t)
|
|
|
|
|
|
|
|
|
|
|
|
|
Eagle
|
10,000
|
-
|
13,000
|
|
5,000
|
-
|
8,000
|
|
4,000
|
-
|
7,000
|
|
Total
Nickel
|
10,000
|
-
|
13,000
|
|
5,000
|
-
|
8,000
|
|
4,000
|
-
|
7,000
|
|
|
|
|
|
|
|
|
|
|
|
|
Molybdenum
(t)
|
|
|
|
|
|
|
|
|
|
|
|
|
Caserones (100%
basis)
|
2,500
|
-
|
3,000
|
|
1,500
|
-
|
2,000
|
|
2,500
|
-
|
3,000
|
|
Total
Molybdenum
|
2,500
|
-
|
3,000
|
|
1,500
|
-
|
2,000
|
|
2,500
|
-
|
3,000
|
|
|
|
|
|
|
|
|
|
|
|
|
|
____________________________________________
|
7 Production
guidance is based on certain estimates and assumptions, including
but not limited to Mineral Resources and Mineral Reserves,
geological formations, grade and continuity of deposits and
metallurgical characteristics.
|
8 68%
of Candelaria's total gold and silver production are subject
to a streaming agreement.
|
- Candelaria: Annual fluctuations in copper and gold
production forecasts for the next three years are primarily due to
sequencing of the Candelaria open pit. An increase in annual
production this year is expected from higher copper and gold grades
in the lower benches of Phase 11. Initial ore from Phase 12 will
begin in 2024 and increase through 2026.
Over the guidance period, total mill throughput is forecast to
range between 27 - 29 million tonnes per annum ("Mtpa").
Debottlenecking initiatives of the Candelaria plant pebble crushing
circuit were completed in 2023. Based on the planned mill feed
blend and the ore hardness throughput model, annual throughput is
expected to approximate 29 Mtpa commencing in 2025.
Candelaria's 2024 copper and gold production are forecast to be
weighted to the second half of the year, primarily owing to mine
sequencing and the resultant grade profiles.
- Caserones: During 2024, ore to the concentrator will
come from Phases 5 and 6 which is expected to have a lower grade
profile compared to 2023. Annual ore throughput is projected to be
approximately 34 – 36 Mtpa. Cathode production will range between
15 – 19 ktpa. In 2025 and 2026 ore will be supplied from Phases 6
and 7 which is projected to have similar grades to 2024.
- Chapada: Production guidance is based on the current
throughput capacity of approximately 23.5 Mtpa over the three-year
period with annual fluctuations primarily due to mine sequencing
and the forecasted copper and gold grade profiles.
Ore mining is planned from the North, Southwest, South and Baru
pits through 2025 followed by South, Southwest and Baru.
- Eagle: Eagle will be producing ore at similar rates as
in 2023 and will be primarily sourced from Eagle East. Metal
production is modestly weighted to the first half of the year
driven by the higher-grade zone on the lower levels of Eagle East.
Development of the Upper Eagle East zone referred to as the 'Keel
Zone' will progress to enable access to those zones in late 2024
with production ramp up in 2025/26. The remaining stopes in the
upper zones at Eagle will remain productive through 2024 as
supplemental ore to meet the annual production plan.
- Neves-Corvo: Copper production guidance is consistent
with prior expectations. 2024 copper production is forecast to be
weighted to the second half of the year owing to mine sequencing
and the resultant grade profiles. Additional ground support in the
mine will be required in the Lombador orebody to maintain mining
rates.
- Zinkgruvan: Zinc metal production is forecasted to
increase over the three-year period with increased production
volume and refinement of operating plans. Zinc head grades are
expected to be consistent over the period. Metal recovery rates and
concentrate grades are anticipated to improve with further
adjustments to the recently improved sequential flotation process.
Zinkgruvan's 2024 zinc production is forecast to be modestly
weighted to the first half of the year, primarily owing to higher
zinc ore throughput. Development towards Dalby and Mellanby
orebodies will open new production areas in later 2025.
2024 Cash
Cost9 Guidance
- 2024 cash cost guidance is estimated to be:
Cash
Cost
|
202410
|
|
Copper
|
|
|
Candelaria11
|
$1.60/lb
|
-
|
$1.80/lb
|
|
|
Caserones
|
$2.60lb
|
-
|
$2.80/lb
|
|
|
Chapada
|
$1.95/lb
|
-
|
$2.15/lb
|
|
|
Neves-Corvo
|
$1.95/lb
|
-
|
$2.15/lb
|
|
|
|
|
|
|
|
Zinc
|
|
|
|
|
|
Zinkgruvan
|
$0.45/lb
|
-
|
$0.50/lb
|
|
|
|
|
|
|
|
Nickel
|
|
|
|
|
|
Eagle
|
$2.80/lb
|
-
|
$3.00/lb
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
- Candelaria: Cash cost is forecast to be $1.60/lb – $1.80/lb
of copper, after by-product credits. The cash cost is expected to
benefit from a higher production profile and realized savings from
synergies between Candelaria and Caserones. By-product credits have
been adjusted for the terms of the gold streaming agreement.
- Caserones: Cash cost is forecast to be $2.60/lb – $2.80/lb
of copper, after by-product credits. The forecasted increase in
Caserones cash cost compared to 2023 reflects lower grade, higher
operating costs, as well as lower by-product credits. Mill
throughput is forecast to increase by 2 – 3 Mtpa compared to 2023
based on the expected plant utilization and improved availability
of the mill.
- Chapada: Cash cost is forecast to be $1.95/lb – $2.15/lb
of copper in 2024, after unencumbered gold by-product credits. The
forecasted decrease in Chapada's cash costs compared to 2023
reflects lower mine movement volumes and expected savings as the
result of cost savings initiatives that were identified late last
year as part of an operational optimization process. Effects of
copper stream agreements are reflected in the realized copper
revenue.
- Eagle: Cash cost is forecast to be $2.80/lb – $3.00/lb
of nickel in 2024, after by-product copper credits. The forecast
increase compared to 2023 is primarily a reflection of planned
lower production volumes and by-product credits.
- Neves-Corvo: Cash cost is forecast to be $1.95/lb – $2.15/lb
of copper in 2024, after zinc and lead by-product credits. The cash
cost is expected to improve compared to the previous year as zinc
and lead production volumes increase.
- Zinkgruvan: Cash cost is forecast to be $0.45/lb – $0.50/lb
of zinc, after copper and lead by-product credits, consistent with
2023 levels.
____________________________________________
|
9 This is a
non-GAAP measure. For equivalent historical non-GAAP financial
measure comparatives see the Historical Non-GAAP Measure
Comparatives section of this press release. Please also see the
Management's Discussion and Analysis for the year ended December
31, 2022 and nine months ended September 30, 2023.
|
10 2024 cash
costs are based on various assumptions and estimates, including,
but not limited to: production volumes, commodity prices (2024 -
Cu: $3.75/lb, Zn: $1.10/lb, Mo: $20.00/lb, Pb: $0.90/lb, Au:
$1,800/oz: Ag: $23.00/oz) foreign currency exchange rates (2024 -
€/USD:1.05, USD/SEK:10.50, CLP/USD:850, USD/BRL:5.00) and operating
costs.
|
11 68% of
Candelaria's total gold and silver production are subject to a
streaming agreement and as such cash costs are calculated based on
receipt of $425/oz and $4.25/oz, respectively, on gold and silver
sales in the year.
|
2024 Capital Expenditure
Guidance
- Capital expenditures are forecast to total $1,065 million on a 100% basis, including
expansionary capital expenditures12 on the Josemaria
Project. The majority of sustaining capital expenditures are for
open pit waste stripping, underground mine development, tailings
storage facility ("TSF") and water management works.
Capital Expenditures
($ millions)
|
202412,13
|
Sustaining
Capital
|
|
|
Candelaria (100%
basis)
|
$300
|
|
Caserones (100%
basis)
|
$205
|
|
Chapada
|
$110
|
|
Eagle
|
$25
|
|
Neves-Corvo
|
$125
|
|
Zinkgruvan
|
$75
|
|
Total Sustaining
Capital
|
$840
|
|
|
|
Josemaria
Project
|
$225
|
|
|
|
Total Capital
Expenditures
|
$1,065
|
- Candelaria ($300 million):
Capitalized waste stripping is forecast to be $170 million, and underground mine development,
including ramp works, of approximately $16
million. Capital expenditure for mobile and mine equipment
is forecast to be $40 million, and
$22 million is estimated for the
continued building of the Los Diques tailings storage facility
("TSF"). Other sustaining capital requirements are estimated at
$40 million.
- Caserones ($205 million):
This includes approximately $80
million for capitalized waste stripping, $60 million for TSF and water management systems,
and $12 million for mine and mobile
equipment. Other sustaining capital requirements are estimated at
$35 million.
- Chapada ($110 million):
Capitalized waste stripping is estimated at approximately
$40 million, $45 million for TSF and water management systems,
and $22 million for mine and mobile
equipment.
- Eagle ($25 million):
Approximately $12 million is for mine
development and growth projects which includes the development of
the Upper Keel zone, and $9 million
for mobile and mine equipment.
- Neves-Corvo ($125
million): Approximately $55
million is forecast for underground mine development,
including infill drilling and $35
million for capital projects in the mill and mine. Capital
expenditures include $10 million for
mine and mobile equipment and $20
million is forecast to be spent for TSF and water
management.
- Zinkgruvan ($75 million):
Approximately $32 million is for
underground development, including development of the Dalby
orebody. Expenditure on the sequential flotation project to improve
concentrate grades and metal recovery rates is forecast to be
$30 million. The remainder of the
sustaining capital expenditure is primarily for TSF works.
- Josemaria Project ($225
million): The estimated capital expenditures in 2024
will continue to support advancing the project prior to a
construction decision. An updated capital cost estimate and project
schedule is pending completion that will incorporate results from
project de-risking initiatives and optimization studies. Capital
expenditures primarily include continuation of hydrology work,
delivery of long-lead mills and motors. Field activities will
include road upgrades and geotechnical work as well as permitting
initiatives, mainly for the powerline, access road and community
relations programs.
_____________________________________________
|
12
Expansionary capital expenditure is a non-GAAP measure and
sustaining capital expenditure is a supplementary financial
measure. For historical comparatives see the Historical Non-GAAP
Measure Comparatives section of this press release. Please also see
the Management's Discussion and Analysis for the year ended
December 31, 2022, for discussion of non-GAAP measures.
|
13 Capital
expenditures are based on various assumptions and estimates,
including, but not limited to foreign currency exchange rates (2024
- €/USD:1.05, USD/SEK:10.50, CLP/USD:850, USD/BRL:5.00).
|
2024 Exploration Investment
Guidance
Exploration expenditures are planned to be $48 million in 2024 primarily for in-mine and
near-mine targets at our operations. The largest portion of the
planned expenditure is to be at Caserones (12,900 meters), while at
Josemaria, early exploration drilling (5,200 meters) on additional
new targets is planned. The focus at Caserones will be deeper
in-pit drilling to better define higher grade breccia zones and
exploration drilling to test the sulphide mineral potential below
the underlying Angelica oxide deposit. At Josemaria the exploration
priority will be to test the Cumbre Verde target. At Chapada
additional drilling at Sauva will continue to further define higher
grade resources. At Zinkgruvan, the exploration campaign (55,000
meters) will target mineral extensions demonstrating grades of 10 -
20% zinc.
About Lundin Mining
Lundin Mining is a diversified Canadian base metals mining
company with operations and projects in Argentina, Brazil, Chile, Portugal, Sweden and the
United States of America, primarily producing copper, zinc,
gold and nickel.
The information in this release is subject to the disclosure
requirements of Lundin Mining under the EU Market Abuse Regulation.
The information was submitted for publication, through the agency
of the contact persons set out below on January 14, 2024 at 18:00
Eastern Time.
Other Information
The Technical Information in this press release has been
prepared in accordance with NI 43-101 and has been reviewed and
approved by Arman Barha, P.Eng.,
Vice President, Technical Services of the Company, a "Qualified
Person" under NI 43-101. Mr. Barha has verified the data disclosed
in this release and no limitations were imposed on his verification
process.
Historical Non-GAAP Measure
Comparatives
Cash Cost and Sustaining and Expansionary Expenditures are
non-GAAP financial measures and are not standardized financial
measures under generally accepted accounting principles
under IFRS and, therefore, amounts presented may not be
comparable to similar data presented by other mining companies.
Cash Cost – Year Ended December 31,
2022
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Operations
|
Candelaria
|
Chapada
|
Eagle
|
Neves-Corvo
|
Zinkgruvan
|
|
|
($ thousands, unless
otherwise noted)
|
(Cu)
|
(Cu)
|
(Ni)
|
(Cu)
|
(Zn)
|
Total
|
|
Sales volumes (Payable
metal contained metal in concentrate):
|
|
Tonnes
|
147,251
|
45,563
|
14,427
|
31,592
|
65,6 84
|
|
Pounds
(000s)
|
324,633
|
100,449
|
31,806
|
69,648
|
144,808
|
|
|
|
|
|
|
|
|
|
Production
costs
|
|
|
|
|
|
1,661.358
|
|
Less: Royalties and
other
|
|
|
|
|
|
(53,785)
|
|
|
|
|
|
|
|
1,607,573
|
|
Deduct: By-product
credits
|
(656,534)
|
|
Add: Treatment and
refining charges
|
124,841
|
|
Cash cost
|
637,486
|
209,238
|
25,168
|
158,351
|
45,637
|
1,075,880
|
|
Cash cost per pound
($/lb)
|
1.96
|
2.08
|
0.79
|
2.27
|
0.32
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Capital Expenditures – Year Ended December 31, 2022
($
thousands)
|
Sustaining
|
Expansionary
|
Capitalized Interest
|
Total
|
|
Candelaria
|
389,731
|
—
|
—
|
389,731
|
|
Chapada
|
104,711
|
—
|
—
|
104,711
|
|
Eagle
|
16,413
|
—
|
—
|
16,413
|
|
Josemaria
|
—
|
171,094
|
14
|
171,108
|
|
Neves-Corvo
|
71,222
|
31,899
|
65
|
103,186
|
|
Zinkgruvan
|
48,144
|
—
|
—
|
48,144
|
|
Other
|
9,610
|
—
|
—
|
9,610
|
|
|
639,831
|
202,993
|
79
|
842,903
|
|
Capital expenditures
are reported on a cash basis, as presented in the consolidated
statement of cash flows. Expansionary capital expenditures are
non-GAAP measures. See the Management's Discussion and Analysis for
the year ended December 31, 2022, for discussion of non-GAAP
measures heading "Non-GAAP and Other Performance Measures" on page
28 which is incorporated by reference herein.
|
|
|
|
|
|
|
|
|
|
|
Cash Cost – Nine Months Ended September 30, 2023
Operations
|
Candelaria
|
Caserones
|
Chapada
|
Eagle
|
Neves-Corvo
|
Zinkgruvan
|
|
|
($ thousands, unless
otherwise noted)
|
(Cu)
|
(Cu)
|
(Cu)
|
(Ni)
|
(Cu)
|
(Zn)
|
Total
|
|
Sales volumes (Payable
metal contained metal in concentrate):
|
|
Tonnes
|
105,585
|
30,385
|
30,681
|
10,234
|
23,000
|
48,028
|
|
Pounds (000s)
|
232,775
|
66,987
|
67,640
|
22,562
|
50,706
|
105,883
|
|
|
|
|
|
|
|
|
|
|
Production
costs
|
|
|
|
|
|
|
1,438,071
|
|
Less: Royalties and
other
|
|
|
|
|
|
(41,717)
|
|
Inventory
fair value adjustment
|
|
|
|
|
(32,185)
|
|
|
|
|
|
|
|
|
1,364,169
|
Deduct: By-product
credits
|
(495,751)
|
|
Add: Treatment and
refining charges
|
125,390
|
|
Cash cost
|
507,884
|
106,866
|
165,170
|
47,228
|
128,206
|
38,454
|
993,808
|
|
Cash cost per pound
($/lb)
|
2.18
|
1.60
|
2.44
|
2.09
|
2.53
|
0.36
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Capital Expenditures – Nine Months Ended September 30, 2023
($
thousands)
|
Sustaining
|
Expansionary
|
Capitalized
Interest
|
Total
|
|
Candelaria
|
300,796
|
—
|
—
|
300.796
|
|
Caserones
|
28,849
|
—
|
—
|
28,849
|
|
Chapada
|
52,433
|
—
|
—
|
52,433
|
|
Eagle
|
15,653
|
—
|
—
|
15,653
|
|
Josemaria
|
—
|
234,831
|
11,011
|
245,842
|
|
Neves-Corvo
|
74,551
|
—
|
—
|
74,551
|
|
Zinkgruvan
|
42,812
|
—
|
—
|
42,812
|
|
Other
|
8,303
|
—
|
—
|
8,303
|
|
|
523,397
|
234,831
|
11,011
|
769,239
|
|
Capital expenditures
are reported on a cash basis, as presented in the consolidated
statement of cash flows. Expansionary capital expenditures are
non-GAAP measures. See the Management's Discussion and Analysis for
the nine months ended September 30, 2023, for discussion of
non-GAAP measures heading "Non-GAAP and Other Performance Measures"
on page 26 which is incorporated by reference herein.
|
|
|
|
|
|
|
|
|
|
|
|
Cautionary Statement on
Forward-Looking Information
Certain of the statements made and information contained
herein is "forward-looking information" within the meaning of
applicable Canadian securities laws. All statements other than
statements of historical facts included in this document constitute
forward-looking information, including but not limited to
statements regarding the Company's plans, prospects and business
strategies; the Company's guidance on the timing and amount of
future production and its expectations regarding the results of
operations; expected costs; permitting requirements and timelines;
timing and possible outcome of pending litigation; the results of
any Preliminary Economic Assessment, Feasibility Study, or Mineral
Resource and Mineral Reserve estimations, life of mine estimates,
and mine and mine closure plans; anticipated market prices of
metals, currency exchange rates, and interest rates; the
development and implementation of the Company's Responsible Mining
Management System; the Company's ability to comply with contractual
and permitting or other regulatory requirements; anticipated
exploration and development activities at the Company's projects;
the Company's integration of acquisitions and any anticipated
benefits thereof; and expectations for other economic, business,
and/or competitive factors. Words such as "believe", "expect",
"anticipate", "contemplate", "target", "plan", "goal", "aim",
"intend", "continue", "budget", "estimate", "may", "will", "can",
"could", "should", "schedule" and similar expressions identify
forward-looking statements.
Forward-looking information is necessarily based upon various
estimates and assumptions including, without limitation, the
expectations and beliefs of management, including that the Company
can access financing, appropriate equipment and sufficient labour;
assumed and future price of copper, nickel, zinc, gold and other
metals; anticipated costs; ability to achieve goals; the prompt and
effective integration of acquisitions; that the political
environment in which the Company operates will continue to support
the development and operation of mining projects; and assumptions
related to the factors set forth below. While these factors and
assumptions are considered reasonable by Lundin Mining as at the
date of this document in light of management's experience and
perception of current conditions and expected developments, these
statements are inherently subject to significant business, economic
and competitive uncertainties and contingencies. Known and unknown
factors could cause actual results to differ materially from those
projected in the forward-looking statements and undue reliance
should not be placed on such statements and information. Such
factors include, but are not limited to: global financial
conditions, market volatility and inflation, including pricing and
availability of key supplies and services; risks inherent in mining
including but not limited to risks to the environment, industrial
accidents, catastrophic equipment failures, unusual or unexpected
geological formations or unstable ground conditions, and natural
phenomena such as earthquakes, flooding or unusually severe
weather; uninsurable risks; project financing risks, liquidity
risks and limited financial resources; volatility and fluctuations
in metal and commodity demand and prices; delays or the inability
to obtain, retain or comply with permits; significant reliance on a
single asset; reputation risks related to negative publicity with
respect to the Company or the mining industry in general; health
and safety risks; risks relating to the development of the
Josemaria Project; inability to attract and retain highly skilled
employees; risks associated with climate change; compliance with
environmental, health and safety laws and regulations; unavailable
or inaccessible infrastructure, infrastructure failures, and risks
related to ageing infrastructure; risks inherent in and/or
associated with operating in foreign countries and emerging
markets, including with respect to foreign exchange and capital
controls; economic, political and social instability and mining
regime changes in the Company's operating jurisdictions, including
but not limited to those related to permitting and approvals,
environmental and tailings management, labour, trade relations, and
transportation; risks relating to indebtedness; the inability to
effectively compete in the industry; risks associated with
acquisitions and related integration efforts, including the ability
to achieve anticipated benefits, unanticipated difficulties or
expenditures relating to integration and diversion of management
time on integration; changing taxation regimes; risks related to
mine closure activities, reclamation obligations, environmental
liabilities and closed and historical sites; reliance on key
personnel and reporting and oversight systems, as well as third
parties and consultants in foreign jurisdictions; information
technology and cybersecurity risks; risks associated with the
estimation of Mineral Resources and Mineral Reserves and the
geology, grade and continuity of mineral deposits including but not
limited to models relating thereto; actual ore mined and/or metal
recoveries varying from Mineral Resource and Mineral Reserve
estimates, estimates of grade, tonnage, dilution, mine plans and
metallurgical and other characteristics; ore processing efficiency;
community and stakeholder opposition; financial projections,
including estimates of future expenditures and cash costs, and
estimates of future production may not be reliable; enforcing legal
rights in foreign jurisdictions; environmental and regulatory risks
associated with the structural stability of waste rock dumps or
tailings storage facilities; activist shareholders and proxy
solicitation matters; risks relating to dilution; regulatory
investigations, enforcement, sanctions and/or related or other
litigation; risks relating to payment of dividends; counterparty
and customer concentration risks; the estimation of asset carrying
values; risks associated with the use of derivatives; relationships
with employees and contractors, and the potential for and effects
of labour disputes or other unanticipated difficulties with or
shortages of labour or interruptions in production; conflicts of
interest; existence of a significant shareholder; exchange rate
fluctuations; challenges or defects in title; internal controls;
compliance with foreign laws; potential for the allegation of fraud
and corruption involving the Company, its customers, suppliers or
employees, or the allegation of improper or discriminatory
employment practices, or human rights violations; the threat
associated with outbreaks of viruses and infectious diseases; risks
relating to minor elements contained in concentrate products; and
other risks and uncertainties, including but not limited to those
described in the "Risk and Uncertainties" section of the Company's
Annual Information Form and the "Managing Risks" section of the
Company's MD&A for the year ended December 31, 2022, which are available on SEDAR+
at www.sedarplus.ca under the Company's profile.
All of the forward-looking statements made in this document
are qualified by these cautionary statements. Although the Company
has attempted to identify important factors that could cause actual
results to differ materially from those contained in
forward-looking information, there may be other factors that cause
results not to be as anticipated, estimated, forecast or intended
and readers are cautioned that the foregoing list is not exhaustive
of all factors and assumptions which may have been used. Should one
or more of these risks and uncertainties materialize, or should
underlying assumptions prove incorrect, actual results may vary
materially from those described in forward-looking information.
Accordingly, there can be no assurance that forward-looking
information will prove to be accurate and forward-looking
information is not a guarantee of future performance. Readers are
advised not to place undue reliance on forward-looking information.
The forward-looking information contained herein speaks only as of
the date of this document. The Company disclaims any intention or
obligation to update or revise forward‐looking
information or to explain any material difference between such and
subsequent actual events, except as required by applicable
law.
Stephen Williams, Vice President,
Investor Relations: +1 604 806 3074; Robert Eriksson, Investor
Relations Sweden: +46 8 440 54 50
View original
content:https://www.prnewswire.co.uk/news-releases/lundin-mining-provides-2024-guidance--announces-2023-production-results-302034201.html